NRC Practice Exams Flashcards
- 0POP02-IA-0001 Instrument Air*
- *
What are the instrument air compressor Idle / Load pressure setpoints?
- Compressor 11:*
- *Load: 122 psig / Idle: 132 psig**
- Compressor 12:*
- *Load: 119 psig / Idle: 131 psig**
- Compressor 13:*
- *Load: 116 psig / Idle: 130 psig**
- Compressor 14:*
- *Load: 113 psig / Idle: 132 psig**
The question works if you assume all compressors are in idle so pressure must be at least 123 psig. So must add 3 psig to numbers in question.
- 0PGP03-ZO-0035 Reduced Inventory Operations*
- *
During Mid-Loop operations, who must approve work orders that have RCSPA (RCS Perturbation Activities) potential?
Shift Manager
Mid-Loop Coordinator
- 0POP05-EO-FRH1 Response to Loss of Secondary Heat Sink*
- *
While in 0POP05-EO-FRH1, what is required for an adequate bleed and feed?
- (Procedure actually has you establish feed before bleed)
- Adequate Feed:*
- *One Charging Pump**
Two HHSI
- Adequate Bleed:*
- *Two PZR PORVs**
Note:
- To get here the Secondary Heat sink must be required
- (RCS Pressure > SG Pressure AND RCS WR HL Temps > 350 ˚F)
- Also SGs are unavailable to remove heat
- (SG WR Level in ≥ 2 SGs ≤ 50% OR PZR Pressure ≥ 2335 psig)
- Tries to restore feed if SGs are available
- 0POP04-DJ-0001 Loss of Class 1E 125 VDC Power*
- *
What must be done to declare a Class 1E battery OPERABLE if it was not aligned to an OPERABLE battery charger for > 15 mins?
Ensure 0PSP06-DJ-0001 (Monthly Surveillance Test) completed satisfactorily
- 0POP05-EO-FRC2 Response to Degraded Core Cooling*
- *
While in 0POP05-EO-FRC2 (Response to Degraded Core Cooling), what is the purpose of depressurizing all intact SGs to 305 psig?
Allow LHSI pumps to inject
Allow Accumulators to inject
- 0POP04-RC-0001 High RCS Activity*
- *
What will mitigate the consequences of a high reactor coolant system activity?
- All MODES:*
- *Raise Letdown Flow**
Put Cation Bed in Service
- MODE 5 ONLY:*
- *Put RCPP in service**
Note:
Validated by chemistry samples
- 0POP02-EE-0001 ESF DC Distribution System*
- *
What is the correct order of breaker operation when energizing a battery charger?
Close DC Breaker
Close AC Breaker
Note:
Class 1E Battery chargers should be paralled for ≤ 15 mins.
- 0POP04-RC-0002 RCP Off Normal*
- *
What is the basis for shutting the #1 Seal Leakoff valve 3 to 5 minutes after securing the RCP when the #1 Seal Leakoff flow pegs high?
Ensures the RCP shaft has stopped rotating to minimize damage to the #2 Seal
- 0POP08-FH-0009 Core Refueling*
- *
What are the two responsibilities of the core load supervisor as defined in 0POP08-FH-0009 Core Refueling?
Implementation of the procedure
Concurring with any changes to an approved Fuel Transfer Form (FTF)
- 0POP05-EO-FRC1 Response to Inadequate Core Cooling*
- *
What is checked to determine if core cooling is adequate?
CETs < 1200 ˚F
≥ 2 HL Temps < 350 ˚F
RVWL ≥ 20% Plenum
- LCO 3.4.9.3 COMS*
- *
What relief valve is allowed to replace a PZR PORV while COMS is armed?
RHR Relief in an operating RHR Loop
- Note:*
- Basis in MODE 4: Inadvertent SI signal (One HHSI Pump)
- Basis in MODE 5: Full charging with a loss of letdown
- 0POP05-EO-FRH2 Response to SG Overpressure*
- *
What is the overall strategy for 0POP05-EO-FRH2 Response to SG Overpressure?
Dump Steam from SGs