Admin Flashcards

1
Q
  • 0POP01-ZQ-0022 Plant OPS Shift Routine*
    • *

Who approves the use of temporary logs?

A

Unit Supervisor
OR
Shift Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • 0PSP03-XC-0002 Initial Containment Inspection*
    • *

What is the purpose of 0PSP03-XC-0002 Initial Containment Inspection to Establish Integrity?

A
  • *Visual Inspection to ensure no loose debris present**
  • Could clog emergency sump strainers during LOCA*

Verify 48” containment purge valves closed

Verify 18” Supplementary purge valves open/closed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  • 0POP01-ZO-0006 Risk Management Actions*
    • *

What does front stop completion time and the back stop completion time mean?

A
  • Front Stop Completion Time:*
  • *LCO action times in conventional Tech Specs**
  • Back Stop Completion Time:*
  • *Ultimate LCO Action Times permitted by Risk Management Tech Specs (RMTS)**
  • Takes precedence over any Risk-Informed Completion Time calculated to be greater than 30 days*

Note:
Risk-Management Technical Specifications (RMTS): Plant-specific set of configuration-based Technical Specifications, based on a formally approved configuration risk management program and associated probabilistic risk assessment, designed to supplement previous conventional plant Technical Specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • 0PGP03-ZO-0041 Primary to Secondary Leakage*
    • *

What puts you in action level 3 for primary to secondary leakage?

A

Leakage from 1 S/G:

  • Condition 1:*
  • *≥ 75 gpd and ↑ 30 gpd/hr**
  • Not required be entered for spikes*
  • Condition 2:*
  • *≥ 75 gpd w/ loss of radiation monitors**
  • May terminate S/D if Rad monitors restored and < 75 gpd*
  • Condition 3:*
  • *> 150 gpd**
  • Must be entered for spikes*
  • Go to POP04-RC-0004 (SG Tube Leakage)
  • Condition 1 OR 2: ↓50% [1 hr] and Be in MODE 3 [Following 2 hrs]
  • Condition 3: Be in MODE 3 [6 hrs]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • 0POP03-ZG-0007 Plant Cooldown*
    • *

What must CV-0198 RMW Isolation be throttled to in MODE 5?

A

< 110 GPM

Note:
Limited to < 125 gpm per LCO 3.4.1.4.1 Cold S/D Loops Filled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • 0PGP03-ZA-0090 Work Process Program*
    • *

What is a high risk work activity?

A

Cause / Would Cause:

Unit loses all power generation capability

Reduce power ≥ 20%

Entry into LCO that requires S/D in ≤ 24 hrs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  • Conduct of Operations*
    • *

According to 10CFR50.72, Immediate Notification Requirements for Operating Nuclear Power Reactors, what situations require the NRC to be notified within 1 hour?

A

Emergency Class Declared

Deviation from Tech Specs

Safety Limit / T.S. Section 2.0 Exceeded

Unplanned Criticality

Radiological, Security, Environmental Events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  • 0PGP03-ZF-0018 FPS Functional Requirements*
    • *

How often is it required to flush the Fire Protection Header?

A

Once per year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • 0PGP03-ZO-0046 RCS Leakage Monitoring*
    • *

What are the action levels for identified leakage?

A
  • Action Level 1:*
  • *≥ 3.0 gpm - < 5.0 gpm**
  • Action Level 2:*
  • *≥ 5.0 gpm**
  • Action Level 3:*
  • *Expected to exceed 10 gpm within 24 hrs**
  • LCO 3.4.6.2:*
  • *> 10.0 gpm**
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  • 0POP01-ZA-0001 Admin Guidelines*
    • *

When are valves in the AFWST pit required to be checked?

A

If security barrier is breached

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  • 0PGPO3-ZG-RMTS Risk-Managed Tech Spec Program*
    • *

When can risk management tech specs (CRMP) be applied?

A

MODES 1 - 2

Applies to extended LCO times.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  • 0PGP03-ZR-0051 Radiological Access / Work Controls*
    • *

What is the maximum yearly dose that a visitor that is not qualified for unescorted access to the RCA can obtain?

A
  • *75 mrem TEDE**
  • Working Visitor*
  • *10 mrem TEDE**
  • Non-Working Visitor*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What actions shall be performed for a secondary chemistry action level 1?

A

Generate CR

Return parameter < Action Level 1 Value

Have 21 days until it becomes action Level 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • 0PGP03-ZF-0001 Fire Protection Program*
    • *

While performing a hourly fire watch, what does 0PGP03-ZF-0001 (Fire Protection Program) specifically say is not allowed?

A

Using a cell phone / mp3 / gaming devices

  • Hourly fire watches may have other duties.
  • Continuous fire watches may have NO other duties.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  • 0POP01-ZA-0014 License Operator Maintenance*
    • *

What is required to maintain an active license each quarter?

A

Seven (7) 8 hr shifts

Five (5) 12 hr shifts

Physicals are valid

  • *Enrolled in License Operator Requal Training**
  • License Operator Upgrade Training does NOT count*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  • 0PGP03-ZA-0514 Barrier Impairment*
    • *

Who must be specifically notified if a fire suppression system is OOS for > 48 hours?

A

STP’s Insurer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  • 0PGP03-ZO-0039 Configuration Management*
    • *

How often is the operator aid review performed?

A

Quarterly

Performed by issuing authority.

Note:
The continuing need for each Operator Aid does not need to be verified. (kinda strange)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  • 0PSP03-ZQ-0028 Operator Logs*
    • *

If AFD alarm has been inoperable for > 24 hrs, how often must AFD be logged?

A

Every 30 mins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  • Conduct of Operations*
    • *

When can the STA stand watch as the Unit Supervisor, Primary RO, or Secondary RO?

A

US / RO must be available to re-relieve the STA if STA becomes activated

US / RO must be in same unit as STA

US / RO must perform shift turnover on same unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  • 0PSP03-XC-0002A Containment Entry (Integrity Established)*
    • *

Who can perform all sections of this surveillance with exception of closing out the surveillance?

A

Non-Licensed work control SRO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q
  • 0PSP03-XC-0002A Containment Entry (Integrity Established)*
    • *

If a Øa occurs while personnel are in containment, where should personnel evacuate?

A

Aux Air Lock

If Aux Air Lock unavailable, must reset Øa and open the PAL OCIV. Personnel can then exit via the PAL.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
  • 0POP01-ZA-0001 Admin Guidelines*
    • *

When are the emergency operations lockers audited?

A

Quarterly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q
  • 0POP08-FH-0009 Core Refueling*
    • *

Which radiation detectors should be functional for moving irradiated fuel?

A

RT-8010B

OR

RT-8050 OR RT-8051

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q
  • 0PGP03-ZO-0046 RCS Leakage Monitoring*
    • *

What must be done for each of the action levels?

A

Action Level 1:
Monitoring
Notifications

Action Level 2:
MAB Walkdowns
Monitoring
Notifications

Off Hours notification for Duty Ops Manager

Action Level 3:
MAB / RCB Walkdowns
Monitoring
HP Surveys / SG Samples
Notifications

Off Hours notification for everyone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What is the objective of secondary chemistry action level 1?

A

Identify and correct the cause of an out-of-normal value without a power reduction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q
  • 0PSP03-XC-0002 Initial Containment Inspection*
    • *

What is the max occupancy of containment during normal operations?

A
  • *72 people**
  • PAL and AAL must be OPERABLE*

Normal Operations is MODE 1 - 4 (Doors normally closed) or MODE 5 with the doors closed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q
  • 0PGP03-ZO-0046 RCS Leakage Monitoring*
    • *

What should be done if a RCS leakage calculation was performed the test results are suspect?

A

Redo the Test

If the 2nd test confirms the 1st test’s results, then the action level entry time shall be the time of the 1st test’s results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q
  • 0PGP03-ZO-0046 RCS Leakage Monitoring*
    • *

Who performs the necessary notifications for 0PGP-ZO-0046 RCS Leakage Monitoring?

A

Shift Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q
  • Probabilistic Risk Assessment*
    • *

What are the risk important operator actions?

A

Manually start idle CRE HVAC train

Start RHR train

Start standby trains after loss of SSPS due to fire.

Perform bleed and feed for loss of heat sink general transient event.

Start PDP after LOOP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q
  • Probabilistic Risk Assessment*
    • *

What are the levels of PRA?

A
  • Level 1:*
  • *Core Damage**
  • CDF / year*
  • Level 2:*
  • *Large Early Release of Radiation**
  • LERF / year*
  • Level 3:*
  • *Public Health Consequences**
  • Early and Late Casualties / year*

Note:
STP does not have level 3 b/c industry standards do not require it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q
  • 0PSP03-XC-0002 Initial Containment Inspection*
    • *

Who can perform the initial containment inspection to establish integrity?

A

SRO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q
  • Probabilistic Risk Assessment*
    • *

What is the level 1 PRA (Likely to cause core damage) top vulnerability?

A

LOOP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q
  • WCG-0001 Work Screening and Processing*
    • *

Who approves high risk plans?

A

Duty Plant Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q
  • 0PGP03-ZO-ECO1A ECO Instructions*
    • *

What requires double valve isolation?

A
  • *Fluid systems > 150 psig or > 200 ˚F**
  • Hazardous System*

SFP Discharge Piping

Systems containing radioactive fluids

Systems containing chemically hazardous fluids

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What are your actions for primary chemistry action level 2?

A

Generate CR

Fix within 24 hrs

If cannot be fixed within 24 hrs, S/D plant to cold S/D.

If heating up plant and > 250 ˚F and Cl, SO4, Fl > 150 ppb for 24 hrs or O2 > 100 ppb for 24 hrs then lower temperature < 250 ˚F.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q
  • 0PGP03-ZI-0007 Confined Space Entry Program*
    • *

What O2 % would be considered safe in regards to Confined Spaces?

A

19.5% - 23.5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q
  • 0PGP03-ZR-0050 Radiation Protection Program*
    • *

What must be done if a woman declares herself pregnant?

A

Restrict RCA Access

Issue new TLD

Figure out dose since conception

Woman, HR, and RP manager agree on new limit

Limit is < 450 mrem/pregnancy

If ≥ 450 mrem since conception, then limit is 50 mrem for the rest of the pregnancy.

Note:
NRC limit is 500 mrem/pregnancy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q
  • 0PGP03-ZO-ECO1A ECO Instructions*
    • *

Whose permission is required to use a check valve, relief valve, or a fail open valve as a tagout boundary?

A

Unit Operations Manager

Maintenance Division Manager / General Maintenance Supervisor

Also need their approval if:

  • Working on system > 140 ˚F without a system vent/drain.
  • Using a freeze seal
  • Working on flange adjacent to boundary valve
  • Any backseated valve used for single valve isolation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q
  • 0PGP03-ZR-0051 Radiological Access / Work Controls*
    • *

When must an area be posted a radiation area, high radiation area, locked high radiation area, and a very high radiation area?

A
  • Radiation Area:*
  • *≥ 5 mR/hr @ 30 cm → < 100 mR/hr @ 30 cm**
  • High Radiation Area:*
  • *≥ 100 mR/hr @ 30 cm → < 1000 mR/hr @ 30 cm**
  • Locked High Radiation Area:*
  • *≥ 1000 mR/hr @ 30 cm → < 500 Rads/hr @ 1 m**
  • Very High Radiation Area:*
  • *≥ 500 Rads/hr @ 1 m**
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What chemistry transients warrant a Rx trip?

A

CP Fully bypassed
AND
Condensate Pump Discharge cation conductivity verified > 1.0 µS/cm

SG Cation conductivity rising
AND
SG Na, Cl, or SO4 > 1000 ppb

SG Cation conductivity > 15 µS/cm
AND
SG Na rising

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q
  • 0PGP03-ZA-0010 Performing/Verifying Activities*
    • *

When is indirect IV used?

A

ALARA (10 mRem)

Safety Condition

Emergency Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What are your actions for primary chemistry action level 1?

A

Generate CR

Bring back in spec within 7 days

If cannot be fixed within 7 days, then more formal corrective actions will be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q
  • 0POP01-ZQ-0022 Plant OPS Shift Routine*
    • *

How far back in the logs should the on-coming watchstanders review?

A

Whichever is less:

Since last watch
OR
Prior 72 hrs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q
  • 0PGP03-ZR-0050 Radiation Protection Program*
    • *

What are the AAL radiation exposure limits?

A
  • TEDE:*
  • *2 R/year**
  • Shallow Dose:*
  • *40 R/year**
  • Lifetime:*
  • *N Rem (N=Age)**

No AAL for eyes b/c TEDE covers your eyes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What are your actions for primary chemistry action level 3?

A

Generate a CR

S/D immediately

Lower temperature to < 250 ˚F as rapidly as possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q
  • Conduct of Operations*
    • *

Who must be notified if a licensed operator fails a random breathalyzer test?

A

Unit Operations Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q
  • 0PGP03-ZR-0050 Radiation Protection Program*
    • *

What are the NRC exposure limits?

A
  • TEDE:*
  • *5 R/year**
  • Eyes:*
  • *15 R/year**
  • Everything Else:*
  • *50 R/year**
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q
  • 0PGP03-ZO-0041 Primary to Secondary Leakage*
    • *

What puts you in action level 1 for primary to secondary leakage?

A
  • Total Leak Rate (All 4 S/Gs):*
  • *≥ 30 gpd**

Monitor CARS / BD / N-16 10 min trends every 15 mins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q
  • 0PGP03-ZR-0051 Radiological Access / Work Controls*
    • *

What is a DAC (Derived Air Concentration)?

A
  • *Person will exceed yearly limit (5 Rem) if he breathes in air 40 hrs a week for 50 weeks.**
  • (2.5 mrem/hr)*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q
  • 0PGP03-ZO-ECO1A ECO Instructions*
    • *

What is a severity Level 1, Level 2, and Level 3 event?

A
  • Level 1:*
  • *Discovered after work has started**
  • Level 2:*
  • *Discovered after ECO released**
  • Level 3:*
  • *Discovered before ECO released**

To classify for these events, the error discovered potentially or could potentially expose a worker to hazardous energy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q
  • 0PGP03-ZO-0003 Temporary Modifications*
    • *

Who is responsible for reviewing a temporary modification PRIOR to the approving of work?

A

SRO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q
  • 0PGP03-ZI-0007 Confined Space Entry Program*
    • *

How many controlled Entry and Exit points will be established for a Permit entry Space?

A

1 Entry

0 Exit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q
  • LCO 6.2.2 Shift Manning*
    • *

When must a RP technician be on site?

A

When fuel is in the reactor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q
  • 0POP08-FH-0003 Fuel Transfer System*
    • *

Who authorizes the operation of the bypass switches on the RFM and FHM?

A

Core Load Supervisor

If Fuel is attached, he must have permission from reactor engineering and the SM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q
  • 0PGP03-ZA-0514 Barrier Impairment*
    • *

When does the requirements of 0PGP03-ZA-0514 not apply to a barrier impairment?

A
  • Fire/HVAC/Flooding/Security:***
  • *Personnel stationed to immediately close the door**
  • Flooding:***
  • *Breached for < 1 shift**

Note:
IVC Doors 002-005 are an exception due to HELBA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q
  • LOT 803.08 Respond to Off-Normal Conditions*
    • *

What is STP required to notify the owner QSE’s of?

A

Power reductions > 25 MWe (Non-Peak)

Power reductions > 5 MWe (Peak)

Unit / Plant Shutdowns

Changes in scheduled power generation

Notifications made by EMS website and then followed by a telephone call.

57
Q
  • 0PGP03-ZR-0051 Radiological Access / Work Controls*
    • *

How you determine the dose rate received from a point source and a line source?

A
  • Point Source:*
  • *DR1(D1)2 = DR2(D2)2**
  • Line Source:*
  • *< L/2 → DR1(D1) = DR2(D2)**
  • *> L/2 → DR1(D1)2 = DR2(D2)**<strong>2</strong>
  • (Point Source Equation)*
58
Q
  • 0PGP03-ZA-0114 Fatigue Rule*
    • *

What are the work hour limits?

A

16 hrs in 24 hrs

26 hrs in 48 hrs

72 hrs in 7 days

  • *10 hr break between days**
  • 8 hr break allowed for crew transition*

34 hr break in any 9 day calendar days

These are rolling time periods

Note:
If a covered worker exceeds 54 hrs in 1 week, then a CR must be generated

59
Q
  • 0PGP03-ZO-0039 Configuration Management*
    • *

Who coordinates the computer point off scan review?

A

Engineering Duty Manager

60
Q
  • 0POP01-ZA-0014 License Operator Maintenance*
    • *

What must be done in order to activate a license?

A
  • *Stand 60 hrs of plant familiarization**
  • Only required for initial activation*

Stand 40 hrs of U/I

Do a plant tour

  • *Discussion with Plant Manager**
  • Command and Control*

Note:
If license was activated in the current quarter, then do not have to perform license maintenance for that quarter to stay active.

61
Q
  • 0PSP03-ZQ-0028 Operator Logs*
    • *

If ECW supply temperature is < 75 ˚F and temperature lowers by ≥ 4 ˚F between consecutive log readings, what must the operator do?

A

Start all ECW pumps

62
Q
  • 0PGP03-ZA-0101 Shutdown Risk Assessment*
    • *

Who performs the final approval of the shutdown risk assessment report?

A

Plant General Manager

63
Q
  • 0PGP03-ZO-0022 Post-Trip Review*
    • *

Who authorizes unit restart after a Category I, II, or III reactor trip?

A

Plant Manager

For a Category III Rx trip, he must review the post trip review report.

Note:
The STA prepares the report and the Plant Operations Review Committee (PORC) reviews the report.

64
Q
  • 0POP01-ZO-0004 Extreme Cold Weather Guidelines*
    • *

When is cold weather guidelines implemented?

A

≤ 40 ˚F for 24 hrs

≤ 34 ˚F

Also done if weather is expected to achieve these temperatures.

Note:
Extreme cold weather season is 10/31 - 3/31.

65
Q
  • 0PGP03-ZF-0001 Fire Protection Program*
    • *

How often must a watch enter an area and still be considered a continuous fire watch?

A

Every 15 minutes

  • Hourly fire watches may have other duties.
  • Continuous fire watches may have NO other duties.
66
Q
  • 0POP01-ZA-0001 Admin Guidelines*
    • *

Following an outage, whose permission is needed to waive the initial valve lineup for a system?

A

Unit’s Operation Manager

One of the following conditions must exist:

  • System has remained in service
  • No work performed on system and system not modified
  • If work performed, then process was controlled by ECO process

Note:
Valves in MAB pit rooms not required to be checked for initial valve lineups

67
Q
  • LOT 802.34 Testing Req. Following Testing*
    • *

What are the equipment groupings per ASME Section XI?

A
  • Class 1:*
  • *RCS Pressure Boundary**
  • Class 2:*
  • *Essential Safety Systems**
  • Class 3:*
  • *Essential Support Systems**
68
Q
  • 0PGP03-ZI-0007 Confined Space Entry Program*
    • *

What is the definition of a confined space?

A

Large enough someone can enter

Limited entry / exit points

Not designed for continuous occupancy

69
Q
  • 0PGP03-ZA-0112 Fatigue Rule Waivers*
    • *

When is a fatigue rule waiver authorized to be used?

A

Mitigates or prevents condition adverse to nuclear safety

  • SM determines if waiver necessary
  • Plant General Manager approves waiver
70
Q
  • 0PGP03-ZO-0042 Reactivity Management*
    • *

A planned reactivity change must be reviewed by a SRO or Rx Engineering if the reactivity change exceeds what amount?

A

± 100 pcm boron

± 2% RTP

Must also be approved by operations management

71
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What is the objective of secondary chemistry action level 2?

A

To minimize corrosion by operating at reduced power while corrective actions are taken.

72
Q
  • 0PGP03-ZO-0041 Primary to Secondary Leakage*
    • *

What puts you in increased monitoring for primary to secondary leakage?

A
  • Total Leak Rate (All 4 S/Gs):*
  • *≥ 5 gpd and < 30 gpd**

Monitor CARS / BD / N-16 every 12 hrs

Note:
≤ 10% rise in 24 hrs, return to normal monitoring.

73
Q
  • 0PGP03-ZO-0003 Temporary Modifications*
    • *

What kind of temporary leak repairs are covered under 0POP03-ZO-0003 Temporary Modifications?

A
  • Requires:*
  • *P&ID Change**
  • Valve kill / packing injection excluded*

Procedure Change

CROE

Training

Note:
Normal temporary leak repairs are covered under 0PGP03-ZO-0009 Temporary Leak Repair

74
Q
  • 0PGP03-ZA-0098 Station Housekeeping*
    • *

How many drains in the RCA may be taped up for your work area?

A

≤ 1 drain at a time

Do not leave unattended.

Note:
If done long term, do a T-MOD

75
Q
  • 0PGP03-ZA-0090 Work Process Program*
    • *

Whose permission is required to start emergent work without an approved work package?

A

Shift Manager

Emergency Director

76
Q
  • 0PGP03-ZO-0046 RCS Leakage Monitoring*
    • *

What are the action levels for unidentified leakage?

A

Absolute Leak Rate:

  • Action Level 1:*
  • *7 Day (Rolling Average) > 0.1 gpm**
  • Action Level 2:*
  • *2 Days (Consecutive) > 0.15 gpm**
  • Action Level 3:*
  • *1 Day > 0.3 gpm**
  • LCO 3.4.6.2:*
  • *> 1.0 gpm**

Baseline Deviation:

  • Action Level 1:*
  • *9 Days (Consecutive) > Baseline Mean**
  • Action Level 2:*
  • *2 of last 3 Days > Baseline Mean + 2 Standard Deviations**
  • Action Level 3:*
  • *1 Day > Baseline Mean + 3 Standard Deviations**
77
Q
  • 0PGP03-ZO-0042 Reactivity Management*
    • *

What are the significant levels of Reactivity Management?

A
  • Level 1: (Highest)*
  • *Significant Event**
  • Fundamental Organizational Breakdown*
  • Level 2:*
  • *Consequential Event**
  • Violation of Design Basis / License*
  • Level 3:*
  • *Unacceptable Event**
  • Violation of Process / Procedures*
  • Level 4:*
  • *Precursor**
  • Level 5: (Lowest)*
  • *Concern**
  • Level 6:*
  • *No Impact**
78
Q
  • 0PSP03-ZQ-0028 Operator Logs*
    • *

What must be done if the QPTR alarm is NOT clear?

A

Perform 0PSP10-NI-0002 every 12 hrs

79
Q
  • WCG-0001 Work Screening and Processing*
    • *

Who approves medium risk plans?

A

Duty Operations Manager

80
Q
  • Conduct of Operations*
    • *

When performing a controlled shutdown for a LCO action statement, how long does it take to shutdown the plant?

A
  • 100% - 20%:*
  • *40%/hr (2 hrs)**
  • 20% - 3%:*
  • *15%/hr (≈ 1 hr)**
  • 3% - MODE 3:*
  • *Remaining time on LCO**

Should start shutting down as soon as you know you will not be able to fix the problem.

Note:
Adjusted to coincide with Tech Spec action times.

81
Q
  • 0PGP03-ZO-0002 Conduct of Operators for Cranes*
    • *

When should outdoor cranes be secured?

A
  • *Wind Speeds > 30 mph**
  • Gust ≤ 35 mph allowed*

Personnel should not be hoisted in manbaskets if winds > 15 mph.

82
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What actions shall be performed for a secondary chemistry action level 2?

A

Generate CR

Take actions for safe and orderly reduction of power to ≤ 50% and achieve ≤ 50% power within 24 hours of entering Action Level 2.

Have 300 hours until action becomes action level 3

Power reduction may be terminated when no longer in action level 2 but may not raise power until out of action level 1.

83
Q
  • 0PGP03-ZA-0090 Work Process Program*
    • *

What classifies as emergency maintenance?

A

Prevent / mitigate an accident

Prevent unplanned release

Protect human life

Prevent significant plant damage

  • Authorized by SM
  • Does NOT need a work package
84
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What is the objective of secondary chemistry action level 3?

A

To correct a condition that can result in rapid corrosion of a secondary side component during continued operation.

Plant shutdown will minimize impurity ingress and limit exposure of steam generator, turbine, and other secondary materials to corrosive solutions.

85
Q
  • Conduct of Operations*
    • *

What is the minimum shift complement?

A

SM (2)

US (2)

STA (1)

RO (4)

ENS Communicator (1)

Safe S/D Plant Operators (4)

  • *Fire Brigade Members (5)**
  • 1 Qualified Fire Brigade Leader*

State / County Communicator (1)

86
Q
  • 0PAP01-ZA-0102 Plant Procedures*
    • *

Who’s approval is required to perform a field change to a procedure?

A

Any SRO

87
Q
  • 0PGP03-ZA-0098 Station Housekeeping*
    • *

In order to eat or drink in a house keeping area, what must the area be zoned as?

A

Zone V

Zone IV is the same except no eating or drinking allowed in Zone IV. (MAB, FHB, ECW, etc.)

Note:
Zone I is the highest degree of cleanliness (Clean room)

88
Q
  • 0PGP03-ZE-0004 Plant Surveillance Program*
    • *

What surveillances does the plant surveillance program procedure govern?

A

Tech Specs

TRM

ODCM

89
Q
  • 0PSP03-XC-0002A Containment Entry (Integrity Established)*
    • *

Who determines what tools, test equipment, or other material may be left inside the RCB once personnel exit containment with integrity established?

A

SM / Unit Supervisor

90
Q
  • LCO 6.2.2 Shift Manning*
    • *

How long can minimum crew staffing be violated?

A

2 hrs

91
Q
  • 0PGP03-ZA-0514 Barrier Impairment*
    • *

Who is responsible for verifying Form 1 of 0PGP03-ZA-0514 is completed accurately?

A
  • *Fire Marshal**
  • FPS Section*
  • *Rapid Response Team Supervisor**
  • HVAC Section*
  • *Mechanical/Civil Supervisor**
  • Flood Barrier Section*
  • *Security Force Supervisor**
  • Security Section*
92
Q
  • 0POP08-FH-0009 Core Refueling*
    • *

When conducting refueling operations, who must be on communications?

A

Refueling Machine

Fuel Handling Machine

FHB Console

RCB Console

Control Room Operator

Rx Engineer

93
Q
  • 0PGP03-ZO-0039 Configuration Management*
    • *

If a computer point was taken off scan, removed from alarm checking, or a substitute value entered, the computer point must be tracked in the points off scan log. When must the review be performed?

A

36 hrs

If another point is available, then review can be extended to 72 hrs.

94
Q
  • 0PGP03-ZI-0007 Confined Space Entry Program*
    • *

Who is responsible for maintaining respirator protection equipment for use in Permit Entry Spaces?

A

Health Physics

95
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

If a chemistry waiver is desired and the waiver is for a control parameter, whose concurrence must be obtained?

A

Plant Manager

Chemistry Manager is required for all waivers.

96
Q
  • Conduct of Operations*
    • *

When is the STA activated?

A

Emergency Plan Entry

EOPs entered

SM / STA discretion

97
Q
  • 0PGP03-ZA-0114 Fatigue Rule*
    • *

What is the minimum amount of time per week that operations personnel must have off?

A
  • Normally: (12 hr shifts)*
  • *2.5 days/week**
  • Outage:*
  • *3 days / 15 day period**

Outage fatigue rules can only apply for 60 days.

98
Q
  • 0POP01-ZO-0006 Risk Management Actions*
    • *

What does the risk assessment calculator assess?

A

Incremental Conditional Core Damage Probability

Weekly Trip Risk Probability

Used in MODES 1 and 2

99
Q
  • 0PGP03-ZF-0011 STPEGS Fire Brigade*
    • *

How often are Fire Brigade meetings conducted?

A

4 per year

100
Q
  • 0PGP03-ZR-0050 Radiation Protection Program*
    • *

If your AAL TEDE is extended past 2 R/year, whose approval is required?

A

2 R - 3 R:
RP Manager
Individual’s Manager

3 R - 4 R:
(Same as 2 R - 3 R)
Plant Manager

4 R - 5 R:
(Same as 3 R - 4 R)
Senior Management Team Member

Note:
Powerpoint had 1.5 R/year as the limit but ZR-50 has 2R/year.

101
Q
  • Conduct of Operations*
    • *

How long does the STA have to get to the control room once notified?

A

10 mins

102
Q
  • Probabilistic Risk Assessment*
    • *

What are the level 1 PRA external events (Likely to cause core damage)?

A

Fire

Flooding

Tornado

Seismic

103
Q
  • 0POP01-ZO-0006 Risk Management Actions*
    • *

Who approves risk management actions?

A

Plant General Manager

Shift Manager in charge of implementing actions.

104
Q
  • 0PGP03-ZA-0098 Station Housekeeping*
    • *

Who approves exemptions for station housekeeping?

A

Plant Manager

105
Q
  • 0PSP03-ZQ-0028 Operator Logs*
    • *

What leakage rate would force the you to declare the containment sump level / flow monitoring system inoperable?

A

> 4.7 gpm

106
Q
  • Survey Maps*
    • *

What do the following symbols mean on a survey map?

A
  • Circle:*
  • *Smear**
  • Triangle:*
  • *Air Sample**
  • Rhombus:*
  • *Large area wipe**
  • Number by itself is a general area reading (<2.5)
  • *120/3.5 means 120 on contact and 3.5 @ 30 cm
107
Q
  • 0PGP03-ZO-ECO1A ECO Instructions*
    • *

Who can waive the IV on an ECO restoration?

A
  • *Issuing Authority**
  • Unit Operations Division Manager (Designee) must concur*

IV waived for significant radiation exposure, personnel safety reduction, or for emergency conditions.

Note:
IV on locked components cannot be waived

108
Q
  • LCO 6.2.2 Shift Manning*
    • *

How many plant operators are required for shift manning to satisfy tech specs?

A
  • MODES 1 -4:*
  • *2 / Unit**
  • At all Times:*
  • *3 Total**
  • At least 1 / Unit*
109
Q
  • 0POP01-ZO-0011 Operability, Functionality, and Reportability Guidance*
    • *

If a prompt determination is performed for a < 72 hr S/D action statement, when should the prompt determination be completed by?

A

≤ 24 hrs

Normally prompt determinations are completed within 1 week.

Note:
For all CRs where the SM/US calls a component OPERABLE but degraded, a prompt determination shall be requested.

110
Q
  • 0PGP03-ZO-0041 Primary to Secondary Leakage*
    • *

What puts you in action level 2 for primary to secondary leakage?

A
  • Leakage from 1 S/G:*
  • *75 gpd - 150 gpd**

Monitor CARS / BD / N-16 10 min trends every 15 mins

If > 75 gpm for ≥ 1 hr:

  • Go to POP04-RC-0004 (SG Tube Leakage)
  • Be in MODE 3 [24 hrs]
    • Time starts when ≥ 75 gpd first indicated
111
Q
  • Probabilistic Risk Assessment*
    • *

What is most likely to cause an early large area release? (Level 2 PRA)

A

Induced SGTR

112
Q
  • 0POP01-ZO-0002 345 kV Switchyard*
    • *

Who can be designated as a STP designated qualified operators?

A

Unit Supervisor

SM

Unit Operations Manager

113
Q
  • 0PGP03-ZR-0050 Radiation Protection Program*
    • *

Who has the authority to lift a Health Physics Stop Work Order?

A

Plant Manager

RP Manager

114
Q
  • 0POP01-ZA-0001 Admin Guidelines*
    • *

When is the locked component deviation log audited?

A

Monthly

  • Note:*
  • Shift Manger/Unit Supervisor responsible for ensuring log updated when locked valve positioned.*
115
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What do the different primary chemistry action levels mean?

A
  • Action Level 1:*
  • *Long term reliability could be affected**
  • Action Level 2:*
  • *Significant damage could be done in a very short time**
  • Action Level 3:*
  • *Inadvisable to keep operating the plant**
116
Q
  • 0POP01-ZQ-0022 Plant OPS Shift Routine*
    • *

Who ensures appropriate entries are made in the control room logbook?

A

Unit Supervisor

117
Q
  • Conduct of Operations*
    • *

While checking the position of a normally locked closed valve, the valve operator cannot be moved due to the locking device. What is the proper method for checking the position of this valve?

A

Remove the locking device

Check valve in closed direction

118
Q
  • Admin Procedures*
    • *

What are the Admin and Tech Spec / TRM Heatup and Cooldown limits for the RCS and PZR?

A

Heatup Rates:

RCS:
Admin: 50 ˚F/hr
Tech Spec: 100 ˚F/hr

PZR:
Admin: 100 ˚F/hr
TRM: 100 ˚F/hr

Cooldown Rates:

RCS:
Admin: 80 ˚F/hr
Tech Spec: 100 ˚F/hr

PZR:
Admin: 160 ˚F/hr
TRM: 200 ˚F/hr

119
Q
  • 0PGP03-ZR-0044 Contamination Control Program*
    • *

What contamination levels are present in a contaminated area and a high contamination area?

A
  • Contaminated Area:*
  • *≥ 1,000 dpm/100cm2 beta/gamma**

20 dpm/100cm2 alpha

  • High Contamination Area:*
  • *≥ 100,000 dpm/100cm2 beta/gamma**

1,000 dpm/100cm2 alpha

120
Q
  • 0PGP03-ZO-0041 Primary to Secondary Leakage*
    • *

When are the N-16 monitors available to detect primary-to-secondary leakage?

A

>25% power

  • Between 20% and 25% the N-16 monitors are unreliable.
  • < 20% the N-16 monitors do not function.
121
Q
  • 0PGP03-ZO-0042 Reactivity Management*
    • *

What is the Plant manager, Operations Manager, Unit Operations Manager, and SM responsible for?

A
  • Plant Manager:*
  • *Ensures reactivity management philosophy**
  • Operations Manager:*
  • *Implements reactivity management program**
  • Unit Operations Manager:*
  • *Determines event classification**
  • Shift Manager:*
  • *Daily application**
122
Q
  • 0PGPO3-ZG-RMTS Risk-Managed Tech Spec Program*
    • *

Can the CRMP be applied if all trains required by the LCO are inoperable?

A

Yes

≥ 1 train must be PRA Functional

123
Q
  • 0PGP03-ZA-0010 Performing/Verifying Activities*
    • *

Who may authorize adding, omitting, or changing a step in a procedure?

A

Shift Manager / Unit Supervisor

Changes are allowed as long as:

  • Does NOT affect personnel / equipment safety
  • Documented in log book / procedure
  • CR generated

Note:
Cannot be used to fix broken procedure.

124
Q
  • 0PGP03-ZF-0011 STPEGS Fire Brigade*
    • *

Who is responsible for providing necessary keys for the Fire Brigade?

A

Security Force Supervisor

125
Q
  • 0POP01-ZO-0004 Extreme Cold Weather Guidelines*
    • *

Who is responsible for implementing the extreme cold weather program?

A

Shift Manger

126
Q
  • 0PGP03-ZF-0018 FPS Functional Requirements*
    • *

A fire door has a self-closing feature. Would the door be considered functional if the self-closing feature was broken but the door would still latch closed?

A

No

Both the self-closing feature and the latch must be working.

127
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What actions shall be performed for a secondary chemistry action level 3?

A

Generate a CR

  • *Take Plant to ≤ 5% power as quickly as safe plant operation permits.**
  • Has to be done regardless of the duration into Action Level 3*
  • Note:*
  • If due to Hydrazine / FW O2 < 2, have 8 hrs to fix and then must go to cold shutdown.*
128
Q
  • 0ERP01-ZV-IN06 Radiological Exposure Guidelines*
    • *

While the E-Plan is activated, what situations allow personnel to exceed 5 REM TEDE?

A
  • 5 REM to 10 REM:*
  • *Protection of Property**

Lifesaving Activities

Protecting Large Populations

  • 10 REM to 25 REM:*
  • *Lifesaving Activities**

Protecting Large Populations

  • > 25 REM:*
  • *Lifesaving Activities**

Protecting Large Populations

PERSONNEL HAVE TO VOLUNTEER

Note:
All personnel can receive 5 REM while in E-Plan without permission.

129
Q
  • 0PGP03-ZO-0046 RCS Leakage Monitoring*
    • *

When can RCS Leakage action levels be exited?

A

Enhanced Unidentified Leak Rate Program indicates exit from the Action Level

Entry into Mode 5

Directed the procedure.

130
Q
  • 0PGP03-ZE-0004 Plant Surveillance Program*
    • *

What must be done if a SR is interrupted and that interruption extends past shift change?

A

Suspend the SR

131
Q
  • 0PGP03-ZR-0050 Radiation Protection Program*
    • *

If your total extended lifetime TEDE is extended past the limit, whose approval is required?

A

< 1 R Past Limit:
RP Manager
Dept Manager
Plant Manager
You

> 1 R Past Limit:
(Same as < 1 R Past Limit)
Senior Management Team Member

132
Q
  • 0PGP04-ZE-0313 Maintenance Rule Program*
    • *

What satisfies the maintenance rule program during different MODES of operation?

A
  • MODES 1 -4:*
  • *CRMP**
  • ≤ MODE 5:*
  • *Shutdown Risk Assessment**
133
Q
  • 0POP08-FH-0009 Core Refueling*
    • *

What is the only form of communication that meets the requirements 0POP08-FH-0009 when moving fuel?

A

A dedicated headset

If the dedicated headset were to fail, even if other forms of communication exist, movement of fuel must be stopped.

134
Q
  • Conduct of Operations*
    • *

When must you notify the FAA that the aviation lights are not working?

A

Lights not working for > 30 mins

135
Q
  • 0PGP03-ZF-0011 STPEGS Fire Brigade*
    • *

How many Fire Drills must a Fire Brigade Member participate in?

A

2 per year

136
Q
  • 0PGP03-ZO-0022 Post-Trip Review*
    • *

What are the different categories of a reactor trip?

A
  • Category 1:*
  • *Cause of Trip Identified**

Safety-Related Equipment functioned properly

  • Category 2:*
  • *Cause of Trip Identified**

Safety-Related Equipment did NOT Function properly

Cause of Malfunction identified

  • Category 3:*
  • *Cause of Trip unknown**

Safety-Related Equipment did NOT Function properly

Cause of Malfunction NOT identified

137
Q
  • 0PGP03-ZO-0046 RCS Leakage Monitoring*
    • *

When is Form 1 (Leakage Log) entered?

A
  • *Any time unidentified leakage changes by 0.2 gpm**
  • Increasing or Decreasing*
138
Q
  • 0PGP03-ZA-0090 Work Process Program*
    • *

What is a work activity risk (WAR)?

A

Impact on operations during MODES 1 - 4

Primary focus is interruption of power generation

Includes impact of removing / returning equipment.

Work Control / Work week manager develops WAR.

139
Q
  • Conduct of Operations*
    • *

When can a SRO perform control board manipulations?

A

When directed by SM during POP04s, POP05s, POP09s, or SAMGs

Taking Action to save a life

Designated as RO in logbook