Nec4 Payment Flashcards
1
Q
What are the interim and final , payments for the
Secondary options
A
- A
Total prices for completed activities
Prices for all activities - B
Quantitiesof completed work at B.O. Q rates and any lump sums
Remeasured quantities at B. O. Q rates
3.c
Defined cost plus fee
Tendered price as the activity schedule bus or minus the contractors share
4,.d
Defined cost plus fee
Re measured value of the work in accordance to B. 0.q plus or minus contractors share
5.e
Defined cost plus fee
6.f
Defined cost plus fee