Clause, 15.1. Examples of what would increase the contractors costs and require early warning. _
A
A) Unforeseenground conditions, material shortage, insolvency of subcontractor, design flaws
’
2
Q
What happens if the contractor or project manager fails to give early warning ?
A
If the contractor fails to give early warning its - compensation is capped at what it would have been had if an early warning occurred. Applies even if they were unaware but a reasonable contractor would have been. clause 63. 7
If a pm fails to give early winning its seen as failing to comply with 10.1 which could lead to a contractor claiming for damage or compensation for bread of contract _