Q

What is the role of the client?

A

The client is strictly a legal party and doesn’t have any direct involvement in the running of the contract, except in certain circumstances they mainly add to the project manager,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the contractual obligations of the client?

A

To pay the contractor and to allow possession of the site
Appoint PM
Provide insurance and missing info

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Appointment of the project manager.?

A

The client appoints the project manager, and they can be in house or external an individual,, or an organization, but they must be listed on the contract data, and they cannot be replaced without giving notice to the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Delegation by the project manager

A

The project manager is allowed to delegate work as long as they notify the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

‘what are the contractual obligations of the supervisor

A

Do tests and inspections e
Issue defects certificate
Notify contractor of defects