NEC Contracts Flashcards

1
Q

What are the 7 types of contract

A

A - Priced contract with Activity Schedule
B - Priced contract with BOQ
C - Target cost with activity schedule
D - Target cost with BOQ
E - Cost reimbursable
F - Management contract
G - Term contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Discuss Option A contract

A

A - Priced contract with Activity Schedule

  • Background:
    o Maximum risk for contractor
    o Payment is made only upon completion of activities and associated defects
    o Important to ensure activity schedule is broken down adequately to ensure required cashflow is achieved
  • Pros:
    o Greater cost certainty for client
    o Simple payment process – easy to confirm an activity is complete
  • Cons:
    o No provision for part payment. If there is an issue completing an activity, no payment is made until it is complete.
    o Client needs to assess the tendered price to ensure they are getting value (with a target cost, they will gain back money if the tender price was too high, so less risk)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Discuss Option B contract

A

B - Priced contract with BOQ

  • Pros:
    o Better cash flow – interim payment made based on % completion of items in the BoQ (i.e. install 5no posts, 3no complete, pay that amount)
    o Easy to track changes – if 5no posts allowed in BoQ, and 7no were required, this is easily identified.
    o Risk is more split:
     Client takes risk for the quantities in the BoQ (less contractor risk).
     Contractor takes risk with the rates (need to cover everything)
  • Cons:
    o Higher degree of design development required by the client (to inform BoQ)
    o For multiple elements of work in a single rate, it can be difficult to assess % work complete
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Discuss Option C contract

A

C - Target cost with activity schedule

  • Background:
    o Payment made on a monthly basis for the Price for Work Done to Date (= Defined Cost + Fee) minus previous payments.
    o Pain / gain at project completion. Calculated by comparing the Defined Cost (+ Fee) at completion against the Target Cost. Pain/gain split based on predefined boundaries.
  • Pros:
    o Target cost incentivises collaboration as both parties share in the success or failure of the project.
    o Better cash flow for contractor compared to Option A (interim payment).
  • Cons:
    o Share of pain/gain is settled upon completion. The client must continue paying the contractor until completion, regardless of whether they are over the target cost. This could cause money stream issues for the client.
    o If share ranges disproportionately favour the client, this could introduce significant risk to the client.
    o More complicated to calculate the due payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Discuss Option D contract

A

Option D – Target cost with a BoQ:

  • Pros:
    o Target cost incentives.
    o BoQ quantities risk sits with the client.
  • Cons:
    o Target costs cons.
    o Unlike Option B, it is not a re-measurement contract. If there is an error in the quantities stated within BoQ, the price won’t be amended. Potential to cause financial loss (to either contractor or client).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Discuss Option E contract

A

Option E – Cost reimbursable:
* Background:
o Contractor paid all their incurred Defined Costs + an agreed Overhead and Profit %

  • Pros:
    o Ability to set up a contract quickly and with little or no scope definition
  • Cons:
    o Significant cost risk to the client
    o Inability for both parties to plan their cashflow
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Discuss Option F contract

A

F - Management contract

  • Background:
    o Tailored for the management contractor procurement route
    o Works subbed out to subcontractors who are employed / managed by a main contractor on behalf of the client.
  • Pros:
    o Can be used by an inexperienced client to sub out responsibility for procurement and management
  • Cons:
    o All the cost risk sits with the client
    o Requires high levels of trust between organisations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Discuss Option G contract

A

G - Term contract

  • Background:
    o Used on a PSC contractor to appoint consultants
    o Uses a priced task schedule – similar to an Activity Schedule. Consultant provides costs against each task.
    o As and when the Employer wants to call-off some of the services, they issue a Task Order for a specific task only.
    o Used when the Employer can define the type of services they require, but not the quantity.
  • Pros:
    o Allows flexibility in procurement
  • Cons:
    o Not suited to high complexity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the role of an NEC Supervisor?

A

Under UK law have to ‘do as stated in the contract’ and be impartial
Role is to check Contractor’s compliance with Scope and any Contractor’s design that has been accepted by the PM
Main role is to notify Defects
They accept nothing!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a defect?

A

Something not in accordance with the Works Information

Part of the works not in accordance with the contractor’s design which the PM accepted*

Part of the works not in accordance with the law

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are defined costs?

A
  • Cost of items in the Schedule of Cost Components (PLANT & PEOPLE)
  • Payments made to Subcontractors for their work BUT you do NOT take account of deductions made for Defects, missing Key Dates etc.
  • Minus Disallowed Costs

51.1 – All contractors costs not included within the Defined Cost are treated as included in the Fee.

The Fee is intended to cover profit and any “off-site overheads”. Two fees, one for the Contractor (direct fee) and another for the Subcontractors (subcontracted fee). Not NEC4.

Schedule of Cost Components + Subcontractor Payments – Disallowed Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are disallowed costs?

A

Amounts not justified by accounts / records
Costs incurred because a required EW was not submitted
Defects after Completion
Defects cause by non-compliance by Contractor
Anything not used to Provide the Works (could be plant/material but an allowance is made for reasonable wastage)
Costs relating to Adjudication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Important timescales

A
  • 25.3 – 4no weeks from meeting a Key Date for the PM to assess the additional costs
  • 31.3 – 2no weeks for PM to accept the programme
  • 51.1 – PM certifies (confirms) payment within 1no week of each assessment date (assessment date is the date (each month or so) that due payment is calculated)
  • 51.2 – Certified payment is made within three weeks of the assessment date
  • 61.3 – 8no weeks to notify a compensation event once it has been identified
  • 61.4 – 1no week for the PM to respond to a CE
  • 62.3 – Contractor submits quotations within 3no weeks of instruction
  • 62.3 – PM replies to a quotation within 2no weeks of receipt
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is an activity schedule?

A
  • List of activities that need to be completed with price for each
  • Commonly used on D&B contracts.
  • Bidder takes risk on quantities.
  • Need well defined Scope to produce a good activity schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a BOQ?

A
  • Measured quantities of items identified in drawings with rate for each item e.g. £ / m of drainage
  • Client takes the risk of the quantities.
  • In order for the client to build up their part, they will normally require a developed design. Common for design to be completed beforehand. Therefore more suited for use on a traditional contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

NEC3 v NEC4

A

Now written gender neutral
Name changes (Works Information -> Scope, Employer -> Client)
Some new secondary options – X29 Climate change (used to incentivise carbon reduction)
Some fixes – only one “Fee” now, not two for own and subcontracted costs

17
Q

Secondary X Clauses

A

X5 – Sectional Completion:
* If included, an area of works can have delayed damages applied.

X7 – Delay damages:
* Payment per day – defined within the contract
* Calculated as time between Completion Date and Completion
* Meant to be proportional to the cost’s the client will incur due to delays (rather than being purely punitive)

X17 – Low performance damages

X18 – limits of liability – limits total liability (i.e. liability accrues)

18
Q

Completion Date

A

o If missed, Delay Damages may be due. This needs to be added into the contract as an optional clause (X7).
o You are entitled to pay for the work you have done LESS the costs associated with Delay Damages.
o 50.2 states the amount due (for each payment) is:
Amount due = Price for Work Done to Date – Amounts to be paid by the Contractor
Therefore delay payments may be taken before Completion

19
Q

Key Dates

A

o If missed, the Employer can recover additional costs that they have incurred as a result of the missed key date.
o Can only be recovered after the Condition for the Key Date is met.
o PM has 4no weeks to determine what the additional costs were

20
Q

Early Warning

A

Contractor and PM notify an EW as soon as they become aware of an event that:
* Increases the total of the prices
* Delays completion
* Delays and Key Date
* Impairs the performance of the works
No requirement to submit an EW for an event which already has a CE

When an EW is notified:
* PM adds it to the Risk Register (EW register)
* C or PM can instruct the other to attend a risk reduction meeting. Aim is to avoid or minimise the risk and to seek solutions.
If an EW is not notified, and leads to a CE event, the CE is assessed as though it was. This can result in DISALLOWED COSTS.

21
Q

Compensation Events

A

Something which changes the:
* Prices
* Planned Completion Date (IMPORTANCE of the accepted programme) (63.3)
* Planned date for meeting conditions of a Key Date (63.3)
* NOTE – a planned completion date is defined as per the accepted programme. This is why it is important to keep the programme up to date.

Important timescales:
* Max 8no weeks to notify a CE once becoming aware of it
* 1no week for PM to respond
* 2no weeks for PM to respond after being notified of their failure to response
* 3no weeks to provide a Quotation
* 2no weeks for PM to Review a Quotation

22
Q

Liability

A
  • Fit for purpose:
    o No excuse / legal defence.
    o Under consumer protection Act we are responsible for “unknown issues”
    o ECC contract (unless changed using X15)
  • Reasonable due skill and care:
    o Just need to show that we followed codes and due processes
    o PSC is typically due skill and care

Limits to amounts:
* Limited – typically try to get it to 10x our fee. This is the total amount we are liable for.
* Aggregate – liability limit for each event. A lot more risk

Can insure against it:
* Professional Indemnity insurance cover – to give protection if a client sues you because you have made a mistake in your work.
* Public liability insurance cover – to protect you against compensation claims made by a third party for injury or damage (for any business which comes into contact with members of the public)
* Employers’ Liability cover – is a legal requirement for businesses who employ staff. It pays the compensation, should an employer sue you for work related injury or illness.

23
Q

How does SMA contract work?

A

Based on an NEC Option C, but uses an ABPM (approved budget pricing model) to set target price using average price of works across the country (£100/m for drainage) and applying to the design including inflation & location.

Coming under ABPM means you make x amount of budget fee, also includes KPI fee, Costain’s base fee of 6%

Very hands off, trying to focus on delivery rather than cost. No CE’s unless comes from PMI that changes scope. Requires costing and forecasting to be accurate to remain in ABPM.

24
Q

how did you manage budget for packages?

A

ensured there was a detailed scope for works and if not reviewing with QS to capture any potential future change. This was reviewed each month to ensure cost reporting is accurate.

reviewed applications each month & CE’s - used diaries and as-builts to ensure accuracy