NCARB Sample Questions Flashcards
The most important factor affecting the strength of concrete is the
water-to-cement ratio
Factors affecting the strength of concrete. The higher the w/c ratio the weaker the concrete. In addition, lower w/c is better for durability. A w/c 0.40 is the norm for parking garages. You may see w/c or w/cm on the test. w = water, c = cement, cm = cementitious material. Fly ash and other additives are part of the cm
The drilled pier (caisson) shown above is belled in order to
The shaft is belled to increase the bearing area.
The bell also increases uplift resistance. It does not increase frictional resistance. Frictional resistance is achieved through “skin friction”, friction between the sides of the shaft and the soils. Normally you do not use skin friction with under-reamed (belled) piers. Drilled piers and caissons are interchangeable.
A slump cone is used primarily to provide an indication of which of the following characteristics of concrete?
Strength and workability
The slump tests measures how much the wet concrete drops under the weight of concrete. The more slump the lower the strength and durability. The more slump the easier it is to work the concrete.
The use of water reducers allow concrete of higher slumps with negatively affecting the strength of the concrete. The slump does affect the finishing of the concrete. A high slump may delay the finishing operations. A low slump may result in harsh finishing due to the concrete setting up faster than it can be finished. Appearance and color are not directly affected by slump but if you have a slab with a 4” slump next to a slab with an 8” slump there will be a difference in color and finish.
Since the 1960’s, thin-shell concrete roof structures have seldom been utilized in the United States and Canada primarily because
formwork is prohibitively expensive
Formwork is the easy answer. Formwork is normally 50% of the cost of cast-in-place concrete. For thin shells, the cost of formwork is a higher percentage of the overall cost. Thin shells use less concrete (and I think steel) that other concrete structures. Building codes refer to ACI documents that allow thin shell construction. Design fees are higher but unfortunately (for the SER) nowhere near the cost of formwork.
The most frequently used footing type at the exterior wall for load-bearing wall support systems is
continuous wall footings
Shallow spread footings are the common foundation for structures in most areas of the country. Continuous wall footings and isolated pad footings at columns. Areas where you do not use spread footings include areas of highly expansive clays or areas with un-controlled fill material.
What is the section modulus for the geometric section illustrated above?
57.3 in3
You cannot determine the S for this member directly (try to if you do not believe me). You must determine “I” and then divide by “c”. This member is symmetrical so the solution is easy. Take the “I” of the gross area (6 * 10^3)/12 [500] and subtract the “I” of the two void areas = 2 * (2.5 * 8^3)/12) [2 * 106.67) = 213.33] = 286.67. “c” equals 1/2 the depth = 5” Therefore S = 286.67/5 = 57.33. This works for member that are symmetrical, (wide flange and channels) where the centroid of the elements used in the calculations coincide with the final member.
When considering permitted live load reductions for the column shown above, what is the live load for the floor supported by the column?
67 kips
Trick question. The question is “What is the live load for the floor”. It does not ask for the live load for the design of the column nor the reduced live load. The (I my opinion) correct answer is 80 psf. Since THEY indicate the answer is in kips THEY must want you to multiply the live load (0.080 ksf) times the area of the column 33’-4” x 25’-0” to determine the live load for the floor. Read carefully!!!
If the soil bearing capacity is 3000 psf [143 500 N/m2] and the applied load is 48,000 lbs [212 kN], which of the following is the area for the footing?
16 SF
48,000/3000 = 16 sf. They give an easy one after a trick question!
Which of the following best defines the P-delta effect?
o Lateral forces on the foundations
o Bending forces in the vertical members
o Horizontal forces in the roof sections
o Moment forces at the joint
Bending forces in the vertical members
Bending forces in the vertical members. P-delta is caused by the drift of the building (delta) under lateral load) times the axial load in the column (P). This may increase the moment in the vertical member (columns) 10 to 15%.
Concrete should reach its design compressive strength in how many days?
28
Concrete is specified using the 28-day compressive strength. The 3-day strength is used to determine when shores can be removed. The 7-day strength is used as an indicator of the strength and is normally 75% of the 28-day strength. I have never used the “32”. I have used 56-day strength for slabs-on-grade.
When concrete is held under sustained stress, the strain will continue to increase with time. Which of the following defines this time-dependent phenomenon?
o Shrinkage
o Temperature expansion
o Creep
o Contraction
Creep
Shrinkage, temperature expansion and contraction are not related to stress. Creep is time dependent and related to the dead load stress in the concrete.
Steel roof joists are manufactured with camber to
compensate for deflection
My answer is none of the above. Their answer is compensate for deflection. The amount of camber on joists might be enough to compensate for the deflection due to the self-weight of the joist and nothing more. Not even close to providing enough for positive roof drainage.
In a renovation of an existing residential building, in which piping of conduit needs to be run through a 2 x 12 [50 x 300 mm] (actual) wood floor joist, which of the following is the minimum dimension required by the IBC [NBC] from the top or bottom of the joist to the bored hole?
2.0 in [50 mm]
An 18th century farmhouse on the National Historic Reg- ister with exposed timber framing is to be restored and opened for tours. Which of the following is the most historically correct method of addressing the lack of live- load capacity of the floor framing?
o Replace the undersized framing with new adequately sized members.
o Sister the existing joists and beams.
o Limit the number of visitors in spaces to the available
live load.
o Reduce the span of the floor framing.
o Limit the number of visitors in spaces to the available
live load.
All are acceptable structural methods of correcting the problem but only limiting the number of visitors (which is allowed by code) maintains the historic nature of the facility.
Cast-in-place concrete beams and columns with No. 11 [35M] rebar or smaller reinforcing bars that are not ex- posed to weather or in contact with the ground should have a minimum coverage of concrete over the bars of
1.5 inches
The question is for beams and columns, which has a minimum of 1.5 inches of cover for these bars. Concrete exposed to or cast against earth have a different set of criteria.