Multiple Choice Flashcards
With which kind of project delivery method are the architect’s duties and responsibilities during preconstruction most limited?
A. Construction Manager as Adviser
B. Design - Bid - Build
C. Design - Build
D. Integrated Project Delivery
D. Integrated Project Delivery. When IPD is used , the architect’s responsibilities are more limited than in the other three methods because the bidding or negotiation for large portions of the work has already been done. The architect is still responsible for working with permitting agencies to ensure code compliance, answering questions from subcontractors and vendors bidding for relatively small portions of the work, and reviewing prefabrication studies.
In addition to making a base bid for a project as specified, each contractor is asked to state how much less his or her bid will be if eight large twin windows shown in the plans and elevations are replaced with smaller casement windows. This is an example of the use of:
A. add alternatives
B. allowances
C. deduct alternatives
D. reduction
C. Deduct alternatives. A request that the contractor supply, in addition to a base bid on the project as specified, a price for some variation, such as a change in materials or in some component of construction, is called an alternate. When the alternate will lead to a reduction in the bid, it is a deduct alternate.
During construction, the architect is obligated to visit the site to keep the client informed about the progress and quality of the work. According to the basic provisions of AIA Document B101, these visits mus occur:
A. every week
B. every two weeks
C. as appropriate to the stage of the contractor’s operations
D. only if they have been written into the agreement as additional services
C. Site visits are part of the basic services of contract administration, but no specific time interval for them is given in the contract. AIA Document B101 states that the architect shall visit the site at intervals appropriate to the stage of the contractor’s operations or as agreed by the owner and the architect.
An architect suspects that blocking has been installed in the wrong location and asks that a portion of the work be uncovered. When the drywall is removed, the blocking is found to be in the correct location. Who is responsible for the removal and replacement of the portion of the wall?
A. architect
B. owner
C. contractor
D. architect and owner should split the cost
B. The owner is responsible for paying for uncovering and rebuilding the wall. Presumably, the architect requested that the drywall be removed because there was a reason to suspect that the construction was in error and the architect was protecting the owner’s interests.
If the blocking had been in the wrong location, the contractor is responsible for the cost of uncovering and repairing the work.
Which of the following is the contractor solely responsible for?
A. field reports to the owner
B. selection of subcontractors
C. scaffolding
D. reviewing claims of subcontractors
C. Scaffolding is part of the means of construction, which is the contractor’s responsibility.
Field reports are the responsibility of the architect. Selection of subcontractors is subject to the approval of both the architect and the owner. If a subcontractor makes a claim to the contractor, the contractor in turn makes a claim to the owner that is reviewed by the architect.
A pressure test on plumbing supply piping require by the specifications reveals a leak in the system. According to AIA Document A201, the responsibility for fixing the leak and paying for a follow- up test rests with the:
A. owner
B. contractor
C. plumbing subcontractor
D. owner and contractor jointly.
B. AIA Document A201, section 13.5.3 requires the contractor to be responsible for all costs made necessary by failures, including costs of repeated tests.
The punch list is created and maintained by the
A. architect
B. authority having jurisdiction
C. contractor
D. owner
A - The architect. - The punch list is a list of items still needing completion. It is created and maintained by the architect.
In most cases, the person responsible for coordinating the process of commissioning a large building should be
A. the architect
B. the constructor
C. the owner
D. a third-party agent
D - commissioning a large building can be a complicated process, and in most cases it should be done by an independent, third-party agent.
Which of the following statements about post-occupancy evaluations (POEs) is true?
A. typically made three to six months after occupancy
B. a standard part of an architect’s services
C. typically paid for by the client
D. performed for the benefit of the client, not the architect
A - A post-occupancy evaluation is a review of a completed project, typically made three to six months after occupancy. However, it is not a standard part of an architect’s services. Is is most often performed at the architect’s expense for the benefit of the architectural firm.
Under the bid process, when are addenda issued?
A. Prior to receipt of bids
B. after receipt of bids but before work commences
C. after the award of the contract
D. during construction.
A - An addendum is a written or graphic document issued by the architect prior to submission of contractors’ bids that modifies or interprets the bidding documents. Addenda may be issued in response to errors discovered in the bidding documents, changes the client wants to make, questions from bidders, or additions or deletions needed. Addenda must be sent to all bidders at least four days prior to the bid date. Most bid forms as bidders to acknowledge receipt of any addenda to help ensure that all bids are based on the same information.
For a negotiated project, addenda are issued after final pricing/contract documents have been issued but before the final contract to ensure questions, additions, deletions, or changes are captured in the contract cost.
Which of the following statements about bidding is correct?
A. Bidding procedures vary widely from project to project.
B. Bidding is not required for federally funded projects.
C. Open bidding may allow an inexperienced contractor to be awarded a job if the firm submits the lowest price.
D. Competitive bidding takes less time than negotiation and can result in a lower construction cost.
A - Bidding procedures are fairly well established in the construction industry, but each project has unique legal, insurance, and administrative requirements that should be shared with all bidders.
Government-funded projects at the federal, state, or local level are generally required to bid.
The bid process can lengthen total project time due to the time allotted for review of the construction documents and contract negotiation, but the competitive nature of bidding allows the owner to compare prices before hiring a contractor. Open bidding means that nearly anyone can bid, regardless of experience. This encourages a variety of contractors to participate, but when bidding is open, it an be difficult to evaluate qualified bidders. In addition, the cost and complexity of advertising and administering the bidding process may increase.
The architect is reviewing a critical path method (CMP) schedule from the contractor. The critical path is 200 calendar days, the total float is 30 days, and the contractor is planning for a 5-day work week. Based on this information, the architect could conclude that the construction time
A. will be about 40 weeks
B. may be as long as 46 weeks
C. could be shortened to 32 weeks
D. cannot be delayed more than 6 weeks
A - The critical path is the sequence of events that must happen as scheduled in order for a project to be completed on time. Dividing 5 work days per calendar week into 200 total days gives a 40-week construction time.
Float represents the range of time during which noncritical activities may start or end without affecting the overall schedule. Total float is the individual float times added together, and does not influence the critical path time interval.
Contractor’s overhead and profit typically account for what percentage of the construction cost?
A. 5-15%
B. 10-20%
C. 15-30%
D. 15-40%
D - the contractor’s overhead and profit typically constitute 15-40% of the construction cost.
At the beginning of the construction phase, the owner requests a change to the building layout that will require relocating a structural column and modifying the framing in the surrounding areas. The column footing has not been constructed. The structural steel shop drawings have been submitted to the architect by the general contractor, but they have not yet been reviewed or approved by the architect or structural engineer. How should the architect initiate this change?
A. Revise the shop drawings to indicate the new column location and associated framing changes and return the submittal to the general contractor marked “Approved as Noted”.
B. Issue a proposal to the owner for additional design services, and notify the contractor of the pending change.
C. Consult with the general contractor to establish the cost increase.
D. Consult with the steel fabricator and supplier to determine the schedule delay.
B - The architect’s first step should be to prepare an amendment to the owner-architect agreement. This design change has been initiated by the owner, and the architect is entitled to additional compensation for the revisions that will be required to move the column. When the amendment is approved by the owner, the architect may proceed with the design work.
The architect should notify the contractor that this change will be made so that construction work that may be affected by the change can be postponed.
Upon receipt of the revised scope of work and request for proposal from the architect, the contractor can prepare a proposal summarizing the cost of the work and the schedule modifications that will be necessary to make the change. The contractor must coordinate with subcontractors and suppliers to determine how the change will affect their schedules.
When the contractor’s proposal is approved by the owner, the architect may prepare a change order to modify the construction contract.
The contractors solely responsible for which of the following? (Choose the two that apply)
A. field reports to the owner B. field tests C. scaffolding D. reviewing claims of subcontractors E. reviewing shop drawings F. code review of contract documents
B, C - AIA A201 - General Conditions of the Contract for Construction, Article 3.2, discusses the contractor’s responsibilities relative to review of the contract documents, which include bringing any noted discrepancies to the architect’s attention. The contractor is not responsible for verifying that the design documents comply with code requirements. AIA A201, Sec. 3.12.10, states that the contractor is not responsible for providing professional services.
Preparation of field reports to the owner is the responsibility of the architect. If a subcontractor makes a claim to the contractor and the contractor determines it to be valid, the contractor may, in turn, make a claim to the owner. This claim would then be reviewed by the architect. Both the contractor and the architect are responsible for reviewing shop drawings, although only the contractor is responsible for the accuracy of the shop drawings. The architect reviews them for general compliance with the requirements of the contract documents. Scaffolding is part of the means of construction, which is the contractor’s responsibility. AIA A201 makes the contractor responsible for arranging and coordinating field tests.
When a contractor proposes a substitution of a material or method of construction that is specified in the contract documents, the architect’s responsibility in reviewing the substitution is
A. proving that the proposed substitution is equivalent to the original.
B. finding documentation that relates to the substitution.
C. forwarding the request to the owner.
D. Approving or disapproving the request.
D - any request for substitution by the contractor must be made in writing and must be accompanied by a complete description of the proposed substitution, including drawings, test data, and other information necessary for an evaluation. The burden of proof of the merit of the substitution falls upon the contractor. The architect is required to review the submission and either approve or disapprove it.
The specifications for a project require moisture tests to be performed on all concrete slabs on which resilient flooring will be installed. According to the requirements of AIA A201, General Conditions of the Contract for Construction, which party is responsible for the cost of performing these tests?
A. architect
B. owner
C. contractor
D. flooring subcontractor
C - AIA A201, Sec. 13.5, states that tests, inspections, and approvals of portions of the work required by the contract documents or by laws, ordinances, rules, regulations, or orders of public authorities shall be paid for by the contractor. The contractor must also make arrangements for the tests and notify the architect of when they will be conducted.
If testing becomes required after receipt of bids or after contract negotiations and is not part of the original contract documents, then the owner becomes responsible for paying for the testing. This provision applies to testing required by the architect, owner, or public authorities having jurisdiction. This situation might happen if the building field inspector requires a test that was not anticipated. In some situations, the owner may not be legally permitted to pass responsibility for the cost of tests to the contractor; in which case, the owner is responsible for the fees.
Which of the following parties are required to agree to a construction change directive?
A. architect and owner
B. architect and contractor
C. owner and contractor
D. architect, owner, and contractor
A - AIA A201, General Conditions of the Contract for Construction, Section 7.1.2, states that a construction change directive requires agreement by the owner and architect and may or may not be agreed to by the contractor. The construction change directive requires the contractor to proceed with the work. The contract is later modified by change order to reflect the compensation due to the contractor.
When the project is 90% complete, the code inspector requires installation of six exit signs in addition to those shown on the approved plans. Which of the following instruments should the architect use to make this change?
A. order for minor change
B. addendum
C. change order
D. construction change directive
C - Because the additional exit signs would necessitate an increase in construction cost and possibly an adjustment to the contract time, an order for minor change would not be appropriate. An addendum can only be used before the contract is signed. It is possible that the contractor and owner might disagree with the cost of the additional exit signs and a construction change directive would be used initially, but it is more likely that everyone would realize the need for the extra signs and agree on a price. Ultimately, a change order would be issued to adjust the contract sum.
Which of the following statements about submittals are correct? ( Choose the three that apply)
A. The architect must review submittals before the contractor approves them.
B. The contractor is ultimately responsible for the accuracy of the dimensions and quantities.
C. Submittals are not considered part of the contract documents.
D. The contractor can reject submittals and request resubmittals by his or her subcontractors.
E. The architect can make a change to the scope of work through the review notes on the submittal.
F. Substitutions may be presented to the architect for consideration at any time during the construction phase.
B, C, D - The submittals process allows the architect to verify that the materials the contractor will provide comply with the requirements outlines in the contract documents. The contractor must review submittals prior to giving them to the architect. If the contractor wishes to make a substitution, the contractor must follow the guidelines given in Division 1 of the specifications. Substitutions are often not accepted after the bid period, or the specifications may require substitutions to be submitted and approved before a specified date. When a substitution is requested, the architect should first verify that the specifications allow this at the current stage of the project. The architect may not add to the scope of work by noting the additional tasks on the submittal. If additional work is necessary, this change should be made through a change order or a construction change directive.
The contractor is responsible for dimensions and quantities of materials. The contractor may require subcontractors to prepare submittal information relative to their work; in this case, if the contractor determines that the submittal data is insufficient or incorrect, the contractor may reject it and require the subcontractor to correct it before it is passed to the architect. The submittals received from the contractor are not considered a part of the contract documents.
A contractor makes a claim for additional money for extra work caused by unforeseen circumstances. According to AIA A201, General Conditions of the Contract for Construction, the initial decision maker (IDM) must respond to this claim within ____ days. (Fill in the blank)
10 days - The IDM is a person designated to be the first interpreter of the contract documents when disputes arise during construction. The purpose of allowing a third party to make initial judgements on claims is to facilitate conflict resolution and minimize the number of claims that proceed to arbitration or mediation. Traditionally, the architect served in this capacity, and if an alternate IDM is not identified, these responsibilities become the architects.
The responsibilities of the IDM and an explanation of he claims process are given in AIA A201, Section 15.2.
This section specifically states that the IDM must respond within 10- days of notification of the claim by the contractor. The IDM may request supporting data to further document the claim.
During the punch list inspection, the architect notices several items that are note completed and that will make it impossible for the client to occupy the space. According to AIA A201, General Conditions of the Contract for Construction, which of the following actions must the architect take?
A. Notify the owner of the incomplete items.
B. Notify the contractor that there are unfinished items that must be finished before the project can be determined substantially complete.
C. Prepare a certificate of substantial completion with a list of incomplete items attached.
D. Revise the punch list and resubmit it to the contractor.
B - AIA A20, Section 9.8.3, requires the architect to complete an inspection of the project upon receipt of the contractor’s punch list. The architect must notify the contractor of unfinished items and work that is not in accordance with the contract documents. The contractor must then correct the items on the list so that the owner can occupy the work or the designated portion thereof for its intended use. This must happen before the architect can issue a certificate of substantial completion.