Inform and advise road users of directions, distances, routes, the location of services for road users and point of interest
Guide signs
To level a floor or layer of concrete with a straight edge using back and forth motion while moving across surface
Screeding
Process of proportioning , cement, water, aggregates, and additives prior to mixing called
Batching
Device mounted on a fixed support or portable support whereby a specific message is conveyed by means of work or symbols for the purpose of regulating, warning, or guiding traffic
Roadwork signs
Cement, Aggregates, and water
Bulk composition
Written instruction detailing how the facility is to be constructed
Specifications
Wave generated in deep water, when reaching shoaling waters, charges not only its height but also in its length but the period will
decrease
Maximum wave height and wave period of the maximum wave height in wave train
Significant wave
When directly affected and generated by local winds, a wind wave is
wind sea
Failure of the stability of slopes, generally occurs along
a curved surface
Measures of congestion highway capacity, what will happen as density continues to increase
speed declines
Ways to avoiding traffic conflicts
Grade separation
Time sharing
Space sharing
The difference between the actual travel time of a given segment of a transportation system and some ideal travel time
delay
cracks approximately at right angles to the pavement
Transverse crack
Provision of safety sight distance
Road: geometry, surface, topography, and illumination
Provision of safety sight distance
Friciton
Eye-height
2.5 days (tides)
Age of tides
Usually a result of insufficient asphalt binder in the mix or stripping of asphalt from particles of aggregate
Raveling
The most important process to prepare concrete
Batching
A test to determine the relative consistency of concrete
Slump test
Circumstances or deviation from standard condition which could permit an occurrence or incident
hazard
The single most important environmental factor in the broad field of coastal engineering
Wave
Combination of the likelihood of an occurrence of a hazardous event and severity of injury or damage of health of the people, property and environment
Risk
Worst condition which should be considered in relation to the design of coastal defence
combination of usually high sea level with severe wave action
Which is more accurate parameter of traffic capacity
Density: Function of cars
Concept of safe design for construction
Design
Equipment
On-site facilities
manpower
Occurs as concrete hardens, being greater in wet mixes
Shrinkage
Single initial application of bituminous material
Prime coat
ideal capacity of road in vehicles per hour
2000 veh/hr
Satisfy the requirement for estimating expected activity times in a PERT network
Makes use of three estimates
Puts the greatest weight on the most likely time
Motivated by BETA distribution
Stimuli fall into four categories
Mechanical
Thermal
Conductivity
Chemical
Standard practice of measuring vertical or zenith angles
Instrument is level
Sight exactly on the target
Slight direct and reverse
Calculation of the probability that the critical path will be completed
Requires knowledge of the standard deviation
Probability of a mechanism that will function satisfactorily
Reliability