Module 7 Flashcards

1
Q

What factors does the pm have to monitor and control

A

Deliverables, schedule and budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain what it means when deliverables varies in the project plan

A

What will be delivered and the quality.

Determined by the pm (if qualified or others)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What aspects of the schedule are monitored for variances

A

Critical tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Should you report variances for favourable outcomes?

A

Yes,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When should variances be identified in a project

A

In the planning phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the two different parts of variance reporting?

A

Internal - within project team

External - between team and stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Are internal or external reports more detailed

A

Internal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the types of reports a pm can use to report variances?

A

1) Gantt chart
2) line graph
3) Variance tables
4) deliverables schedule
5) work effort analysis schedule
6) overtime analysis schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Explain how a Gantt chart can be used to report variances

A

For each task on the y axis having planned and actual progress toward task completion bars on the x axis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How can a line graph report variances?

A

Useful visual aid for budget variances

Planned expenditures over time and actual expenditures over time can be plotted as two different lines on the same graph

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is one thing to note when reporting expenditures

A

The pm must understand that businesses typically do not pay their bills until they are required to be paid by suppliers and suppliers often provide payment in terms of 15 to 30 days of billing date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How can variance tables report variances

A

Have much more detail then line graphs or Gantt charts. (Both are often used in combination)

  • consider including a column to explain reasons for variances
  • columns include titles such as “task”, “budget” “actual or revised” “variance” “% variance” “explanation “
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do deliverables help report variances

A

Can be used for schedule of budget variances

-shows in columns: task, team member, target date, actual or revised, variance, % variance, and explanation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How does work effort analysis schedule report variances

A

For schedule variances

  • shows variance in hours worked
  • columns include: task, budget hours, actual to date, estimated hours to completion, total, variance, % variance, and explanation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How does an overtime analysis schedule help report variances

A

Shows the hours scheduled for each team member and the actual hours tracked

  • identifies team members that are over and under utilized
  • columns include: task, schedule hours, actual hours, variance, %variance, and explanation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the first step to judge the most appropriate response from a pm when a team member is overloaded

A

To understand the cause of the overload

17
Q

What is an executive summary

A

It briefly explains the overall progress for the project to date and

  • also identifies significant variances.
  • If decision have been made in response to variances they should also be explained
18
Q

What section of a progress report are many stakeholders only going to read?

A

Executive summary

19
Q

What should a progress report include (mostly)

A
  • executive summary
  • table of contents
  • thorough section on deliverables, schedule and budget
  • explanation of issues relevant to a particular project
20
Q

Where should graphs tables and charts be in a progress report?

A

In the explanation section

21
Q

Do project scopes change during the life of the project

A

Yes

22
Q

What are the two types of scope changes

A

Mandatory and optional

23
Q

What is a mandatory scope change?

A

One that must be completed to ensure that the deliverables produced are relevant

-without a scope change the projects original deliverables are are irrelevant and useless

24
Q

What is an optional scope change

A

Not required to meet original deliverables but was requested

25
Q

What is the first action a pm should take after there is a scope change

A

Investigate the impact of the change on the projects deliverables , schedule and budget

26
Q

What is one way to deal with mandatory scope changes

A

Contingency

27
Q

What is the difference between monitoring and controlling

A

Monitoring - variances are identified

Controlling - action taken to put project back on track

28
Q

When creating a work effort analysis schedule, what is compared against planned hours to identify variances

A

Estimated hours are compared against planned hours

29
Q

What chart is useful to illustrate the planned schedule against actual progress

A

Gantt

30
Q

Main use of overtime analysis schedule

A

To identify team members that have worked more or less hours then were planned so that work can be reorganized in a more balanced fashion

31
Q

Purpose of project progress report?

A

Give stakeholders the info they need to understand the progress project has taken over reporting period

-also highlight and explain variance

32
Q

Main concept controlling scope changes

A

Scope changes should not be made that would impact ability to achieve their own project responsibilities without involving appropriate stakeholders