Module 6: Cost Management (ch5) Flashcards
1
Q
Estimating Individual activities and summing them to get a project total is called ——
a - Analogous estimating.
b - Parametric estimating.
c - Simple Cost estimating.
d - Bottom-up estimating.
A
d - Bottom-up estimating.
2
Q
Instead of using a range of numbers for estimates, agile projects use —–
a - Top-down
b - Analagous
c - Relative
d - Timeboxing
A
c - Relative
3
Q
T-Shirt sizing is an agile estimating method.
True or False
A
True
4
Q
A cost baseline is a time based budget that is used to measure and monitor cost performance throughout the project.
True or False
A
True
5
Q
Typicallly, the cost baseline can be changed by any key stakeholder.
True or False
A
False