Module 6: Cost Management (ch5) Flashcards

1
Q

Estimating Individual activities and summing them to get a project total is called ——

a - Analogous estimating.
b - Parametric estimating.
c - Simple Cost estimating.
d - Bottom-up estimating.

A

d - Bottom-up estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Instead of using a range of numbers for estimates, agile projects use —–

a - Top-down
b - Analagous
c - Relative
d - Timeboxing

A

c - Relative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

T-Shirt sizing is an agile estimating method.

True or False

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A cost baseline is a time based budget that is used to measure and monitor cost performance throughout the project.

True or False

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Typicallly, the cost baseline can be changed by any key stakeholder.

True or False

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly