Module 3: Project Initiation (Ch3) Flashcards
One of the main activities NOT involved in project initiation is:
a - Create a change control process
b - Identify stakeholders
c - Create project charter
d - Hold a kick-off meeting
a - Create a change control process
For projects where requirements are not well defined, the best development approach might be:
a - waterfall
b - incremental
c - scrum
d - predictive
b - incremental
The document that provides justification for investing in a project is:
a - strategic plan
b - business case
c - project charter
d - net present value analysis
b - business case
What is the rhythm of activities conducted throughout the project?
a - Project Charter
b - Sprint
c - Relative Size
d - Cadence
e - Template
d - Cadence
Agile estimates are often done in terms of ——- ?
a - Project Charter
b - Sprint
c - Relative Size
d - Cadence
e - Template
c - Relative Size
What is a document that formally recognizes the existance of a project?
a - Project Charter
b - Sprint
c - Relative Size
d - Cadence
e - Template
a - Project Charter
A ——- is a short period of time (2-3 weeks) when the project team work to complete a certain amount of work.
a - Project Charter
b - Sprint
c - Relative Size
d - Cadence
e - Template
b - Sprint
A ——- is a file with a preset format used to create various documents.
a - Project Charter
b - Sprint
c - Relative Size
d - Cadence
e - Template
e - Template