Module 5: Project Schedule Management (Ch5) Flashcards
1
Q
Dependency Diagram
a - Start to Finish
b - Start to Start
c - Finish to Start
d - Finish to Finish
A
c - Finish to Start
2
Q
Dependency Diagram
a - Start to Finish
b - Start to Start
c - Finish to Start
d - Finish to Finish
A
b - Start to Start
3
Q
Dependency Diagram
a - Start to Finish
b - Start to Start
c - Finish to Start
d - Finish to Finish
A
d - Finish to Finish
4
Q
Dependency Diagram
a - Start to Finish
b - Start to Start
c - Finish to Start
d - Finish to Finish
A
a - Start to Finish