Module 4 Stakeholder and Communication Management Flashcards
Inputs to the Plan Communications Management process include all of the following except:
A. Stakeholder register
B. Enterprise environmental factors
C. Project management plan
D. Budget forecasts
D. Budget forecasts
Stakeholders may include which of the following people?
A. team members and subject matter experts
B. all of these
C. external suppliers and competitors
D. clients and customers
B. all of these
A principal idea in agile is that the length of daily stand-up meetings should be ___________.
A. 45 minutes or less
B. 10 minutes or less
C. 15 minutes or less
D. 30 minutes or less
C. 15 minutes or less
Once the project is underway, the project manager and team need to manage communications by doing all of the following activities EXCEPT:
A. Communicate thoroughly, copying all stakeholders on all e-mails and team status reports.
B. Communicate promptly, providing information soon enough so that it is useful to recipients and facilitates timely decisions.
C. Communicate effectively, taking actions to ensure the receiver understands the communication and acts appropriately.
D. Communicate accurately, presenting information in a manner that people are likely to interpret correctly
A. Communicate thoroughly, copying all stakeholders on all e-mails and team status reports.
Meeting expectations, addressing issues, and fostering appropriate involvement should result from which PMBOK process?
A. Administer Procurements
B. Manage Stakeholder Engagement
C. Manage Communications
D. Plan Communications
B. Manage Stakeholder Engagement
By identifying stakeholders and their needs, project managers can be more effective in all the following ways EXCEPT:
A. develop a shared sense of risk.
B. derive the final budget
C. serve as good stewards of the organization’s resources.
D. prioritize among competing objectives.
B. derive the final budget
Which of the following activities is one of the best ways to build strong working relationships within the core project team and among stakeholders?
A. Encourage open communication
B. Regularly celebrate success
C. Use appropriate decision making techniques
D. All of these
D. All of these
________ is the process of the project team communicating and working with stakeholders to satisfy their needs (and additional desires, when possible), handle issues quickly and encourage active stakeholder participation throughout.
A. Identify Stakeholders
B. Plan Stakeholder Engagement
C. Manage Stakeholder Engagement
D. Analyze Stakeholders
C. Manage Stakeholder Engagement
A project communications plan generally includes all of the following information EXCEPT:
A. stakeholder register
B. communication purpose
C. communication methods
D. communication timing
A. stakeholder register
According to PMBOK, the fundamental attributes of effective communication activities and developing effective communication artifacts include all of these EXCEPT:
A. Monitoring and measuring effectiveness of communications
B. Challenging others communications styles to follow a single standard
C. Understanding as much as possible about the receiver of the communications
D. Clarity on purpose of the communication
B. Challenging others communications styles to follow a single standard
The “act” part of the PDCA cycle for project meetings is:
A. perform in-between meeting tasks
B. evaluate the meeting
C. conduct the meeting and write meeting minutes
D. prepare an advanced agenda to guide the meeting
A. perform in-between meeting tasks
A stakeholder analysis has shown that one of the project’s key stakeholders is currently neutral with respect to the project. However, it is desired that they be one of its leading supporters. How can the project manager identify proper actions and communications to fill this gap?
A. confrontation conflict style
B. using performance reporting
C. the communications management plan
D. using expert judgment
D. using expert judgment
The project team has identified a set of stakeholders and has a good idea as to which ones need to be most engaged with the project. What analytical technique can be used to help them assess any gaps in their engagement?
A. Power/Interest Grid
B. Stakeholders Engagement Assessment Matrix
C. Stakehholder management plan
D. Responsibility Assignment Matrix
B. Stakeholders Engagement Assessment Matrix
A project team is facing an important decision. For this decision, broad input is important, it is desirable to get as much buy-in as possible, and there is only a limited time before the decision must be made. Which decision method is most appropriate?
A. Consultative
B. Consensus
C. Autocratic
D. Delegating
A. Consultative
Project stakeholders can be prioritized based upon their level of power, legitimacy and urgency plus a number of additional criteria that might include:
A. personality
B. impact
C. fame
D. tenure
B. impact