Module 2 Competency 2: Cost and Economic Analysis Flashcards

1
Q

The Defense Acquisition is the management process that guides DoD acquisition programs and is basically the process by which programmatic risk is managed. What are the three programmatic risks that must be successfully managed?

A

Cost, Schedule, and Performance Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the appropriations that may be used to fund an acquisition program?

A

RDT&E, Procurement, O&M, MILCON, and MILPERS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the acquisition approach that delivers capability to the warfighter in set of increments spread over time - with a known desired end-state capability - rather than in a single effort, because technology is not yet available to provide that end-state capability?

A

Evolutionary acquisition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the term used to describe dollars shown in the life-cycle cost estimate wherein the effects of inflation are not considered?

A

Base Year Dollar or Constant Year Dollars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the term used to describe dollars used for programming and budgeting purposes wherein the effects of inflation are considered?

A

Then-year dollars or current year dollars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What cost structure does MIL-STD-881C represent?

A

Work Breakdown Structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What concept is based on the axiom that the best time to reduce cost is early in the process?

A

Cost As an Independent Variable (CAIV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which cost estimating method is based on direct comparison with historical information of one similar system?

A

Analogy Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which cost estimating method is known as a statistical method or top-down method?

A

Parametric Approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which cost estimating method requires extensive knowledge of the product or process?

A

Engineering Approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the methods/steps in conducting the Delphi Technique?

A

1) Query expert opinion
2) Seek supporting rational or information from each expert
3) Summarize Results
4) Gather second opinion
5) Continue iteration until consensus or near-consensus is reached

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the theory that as the quantity of output doubles, the man-hours required to produce the quantity decreases at a fixed rate?

A

Learning Curve Theroy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the name of the integrated management tool intended to relate contractor actual performance on a contract to the contractor’s planned cost and schedule, that measure the work in progress in objective terms, and that states the value of the work completed in dollars?

A

Earned Value Management System (EVMS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the EVM-related term when there is a difference between budgeted cost of work performed (BCWP) and actual cost of work performed (ACWP) on a cost reimbursable contract?

A

Cost Variances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost savings, cost avoidance, and Productivity Improvements are examples of what type of cost benefits?

A

Quantifiable Benefits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In regards to measures of central tendency, what is a mean? A Mode? A Median?

A

Mean is arithmetic average
Mode is the most frequent score in a distribution of scores
Median is the middle of arrayed values

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What does correlation measure?

A

Measure the degree of relationship between two or more variables`

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

For a perfect correlation to exist, what would be the coefficient?

A

1.0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When evaluating a proposed investment or project with costs and benefits occurring not only in the current year but also future years, it is necessary to “bring back today’s dollars” all those costs and benefits. What is the process determining?

A

Net Present Value of the proposed investment or project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is used to craft the plans and programs that satisfy the demands of the National Security Strategy within resource constraints, to develop budgets to be submitted to the Congress and manage the execution of those resources?

A

Planning, Programming, Budgeting, and Execution Process (PPB&E)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is a systematic method established by the Joint Chiefs of Staff for assessing gaps in military joint warfighting capabilities and recommendation solutions to resolve these gaps?

A

Joint Capabilities Integration and Development System (JCIDS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the management process that guides all DoD acquisition programs?

A

Defense Acquisition System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Which DoD Directive is the Defense Acquisition System?

A

5000.01

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What establishes the management framework that implements the Defense Acquisition Program; it emphasizes innovation and flexibility in the acquisition process and focuses on required outcomes and statutory requirements?

A

DoDI 5000.03: Operation of the Defense Acquisition System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
The Defense Acquisition system has how many milestones, phases, and acquisition activites?
3;5;3
26
What document details the broad, time-phased, operational goals, and a description of the required capabilities to address a specific gap?
Initial Capabilities Document
27
If a material solution is considered the most appropriated method to resolve an identified gap, what is the next step?
Start Action on an acquisition program as that material solution
28
What are the three major activities in the Acquisition Management System?
Pre-Systems Acquisition, Systems Acquisition, and Sustainment
29
What are the five phases of the Acquisition Management System?
1) Materiel Solutions Analysis 2) Technology Development 3) Engineering and Manufacturing Development (EMD) 4) Production and Deployment 5) Operations and Support
30
What type of appropriation funds can be used for the Materiel Solutions analysis phase?
RDT&E and O&M
31
What type of appropriation funds can be used for the Technology Development phase?
RDT&E
32
What type of appropriation funds can be used for the Engineering and Manufacturing Development phase?
RDT&E
33
What type of appropriation funds can be used for the Production and Deployment phase?
Procurement for the end item system and MILCON for the acquisition of necessary facilities unique to or required for the system involved
34
Who evaluates the milestones in the Defense Acquisition Management system?
Joint Requirements Oversight Council (JROC) and the Milestone Decision Authority (MDA)
35
Which milestone of the DoD Acquisition Management System is usually the point at which program initiation occurs?
Milestone B
36
In which milestone of the DoD Acquisition Management System do you examine alternative concepts to meet a stated mission need?
Milestone A
37
In which milestone of the DoD Acquisition Management System does a decision authorize the program manager to commence low rate initial production (LRIP) or initial deployment?
Milestone C
38
What are the five overarching policies that govern all DoD acquisition programs?
1) Flexibility 2) Responsiveness 3) Innovation 4) Discipline 5) Streamlined and Effective Management
39
True or False: When Milestone B occurs, the MILDEP or agency is required to have adequate funds in the FYDP to finance the acquisition of the program during this period.
True
40
What is the preferred DoD strategy for rapid acquisition of mature technology for the user?
Evolutionary Acquisiton
41
Using which process is Evolutionary Acquisition achieved?
Incremental Development Process
42
Evolutionary Acquisition requires the collaboration of whom?
1) Warfighter 2) Tester 3) Developer
43
What is established to determine the level of management review, decision authority, and applicable reporting requirements for a program?
Acquisition Categories (ACAT)
44
Which ACAT category is used for Major Defense Acquisition Programs (MDAP)?
ACAT I
45
Estimated by USD (AT&L), the required total expenditures for an ACAT I program is?
RDT&E of more than $365M or Procurement of more than $2.19B
46
What does ACAT ID and ACAT IC indiciate?
MDA is at Defense level for ID and known as Defense Acquisition Executive (DAE) MDA is at Component level for IC and known as Component Acquisition Executive (CAE)
47
What ACAT category is used for Major Automated Information System (MAIS)?
ACAT IA
48
Estimated by USD (AT&L), the required total expenditures for an ACAT IA program is?
Total cost in any single year in excess of $32M Total program cost in excess of $126M or Total life-cycle cost in excess of $378M
49
To comply with legal requirements, DoDI 5000.02 requires that every acquisition program establish an _________ to document the cost, schedule, and performance objectives and thresholds of that program beginning at program initiation.
Acquisition Program Baseline
50
the APB should contain only what?
the most important cost, schedule, and performance parameters
51
Programs goals for an APB consist of what two types of values?
"Objective" Values and "Threshold" Values
52
In considering program goals, which goals represent specific parameters that the warfighter user desires from the acquisition program?
Objective
53
In considering program goals, which goals represent the minimum parameters that the warfighter user is willing to accept from the acquisition program?
Threshold
54
What includes all of the elements of the system from cradle to grave?
Total Systems Approach
55
What are all of the elements of the Total Systems Approach?
``` Weapon System (hardware and software) Operators and Maintainers Operational Effectiveness and Suitability Deployment/Fielding Interoperability Training and Training Devices Environmental Impact ```
56
If a material solution is considered the best approach to provide the required capability, the next step in the acquisition process is what?
Analysis of Alternatives (AoA)
57
What is an analytical comparison of the operational effectiveness, suitability, and life cycle costs of alternatives that satisfy established capability needs stated in the approved ICD?
Analysis of Alternatives (AoA)
58
A sufficient AoA ensure what?
the best, most affordable alternative materiel solution is selected from among the potential solutions.
59
Who is responsible for preparation of the AoA study guidance?
Director, Cost Assessment and Program Evaluation
60
The foundation of a sound and credible cost estimate is a well-defined program; it is essential to know the details of what is to constitute that acquisition program in order to prepare a valid estimate of its life cycle cost. The document used to capture that detailed information is known what?
Cost Analysis Requirements Description (CARD)
61
A CARD shall be prepared for which programs?
ACAT I and ACAT IA
62
What can be defined as the total cost to the Government of a program over its entire life, including costs for research and development, testing, production, facilities, operations, maintenance, personnel, environmental compliance, and disposal?
Life Cycle Costs
63
When preparing a cost estimate in which manner must you prepare the estimate and such means that costs are tied to a specific base fiscal year, usually the year the cost estimate was prepared?
Constant Year Dollars
64
Which costs estimate method is used for programming and budgeting purposes and represent the amounts required when actually used, they reflect the effects of inflation?
Then-Year or Current Year Dollars
65
What are the three major ways of grouping and viewing program life-cycle cost estimates?
Appropriation Category Work Breakdown Structure (WBS) Life Cycle Cost Categories
66
Which method of grouping life-cycle costs is the greatest interest to the business financial manager of the acquisition program?
Appropriation
67
Which method of grouping life-cycle costs is the greatest interest program manager and chief engineer of the acquisition program?
Work Breakdown Structure (WBS)
68
Which method of grouping life-cycle costs should define the total system to be developed or produced; display the total system as a product oriented family tree composed of hardware, software, services, data and facilities; and relate the elements of work to each other and to the end product?
Work Breakdown Structure (WBS)
69
Major acquisition programs shall tailor a program WBS in accordance with guidance in what?
MIL-STD-881C
70
Since MIL-STD-881C does not address AIS programs, managers of these programs should develop their own program-specific WBS in consultation with who?
Integrated Product Team (IPT) members
71
Which method of grouping life-cycle costs is the greatest interest to the cost analyst?
Life Cycle Cost Categories
72
What are the four different cost categories in the Life Cycle Cost Categories?
Research and Development Investment Operations and Support Disposal
73
What are the three basic types of cost estimates for ACAT I acquisition programs?
Program Cost Estimate Component Cost Estimate Independent Cost Estimate
74
For ACAT II, ACAT III, ACAT I programs what types of cost estimates normally done?
Program Cost Estimate | Component Cost Estimate
75
What is defined by 10 USC 2432 as the amount found by dividing the total cost for development and procurement of, and system-specific military construction for, the acquisition program by the number of fully configured end items to be produced for the acquisition program?
Program Acquisition Unit Cost (PAUC)
76
What is the amount found by dividing the total of funds programmed to be available for obligation for procurement by the number of fully-configured end items to be procured?
Average Procurement Unit Cost (APUC)
77
PUAC =
RDTE+ Procurement + MILCON / Procurement Quantity
78
APUC =
Total Procurement/Procurement Quantity
79
What is based on the principle that the best time to reduce LCC is early in the acquisition process?
Cost as an Independent Variable (CAIV)
80
Which cost estimating method is based on the direct comparison with historical information of one similar existing activity, system, or component?
Analogy
81
Which cost estimating method is based on physical attributes or performance characteristics and their relationships to highly aggregated component costs?
Parametric
82
The parametric approach is also known as what?
Statistical Method or Top Down Method
83
Which cost estimating method uses a databased of elements from multiple similar systems?
Parametric
84
How does the parametric method of cost estimating differ from the analogy method?
Makes statistical inferences about Cost Estimating Relationships (CER) between cost and system characteristics
85
Which cost estimating method is known as the "bottom up," requires extensive knowledge of system characteristics, and is the most detailed of all techniques and the most costly to implement?
Engineering Method
86
Which cost estimating method's strength is that it is very accurate in later stages of Engineering and Manufacturing Development? Also for equipment or systems in current production, it can provide very accurate cost projections?
Engineering Method
87
Which cost estimating method uses actual costs contracted for or actually incurred on the same system during an earlier period, which are then projected to future events in similar nature?
Actual Cost Method
88
When should you not use expert opinions when estimating costs?
1) When the time permits the preparation of a more thorough analysis 2) As a convenient substitute for more scientific methods when the use of more scientific methods is possible.
89
Expert opinions are helpful in which circumstance?
to get a rough order of magnitude (ROM) that can be used as a "sanity check" for an estimate computed by another approach. `
90
What is a method of narrowing range of expert opinion to achieve consensus and involves querying the expert opinions from a group?
The Delphi Technique
91
What is a scientific way of determining (predicting) how much learning should occur and applying it to a production estimate?
Learning Curve Theory
92
Every time the production quantity of a particular tactical missile doubles (for example, from unit number 8 to 16), unit labor-hour cost is reduced how much?
85% to 92% of the previous unit's labor-hour cost.
93
Given that the time required to produce unit number 2 is 300 hours and a learning curve rate, determine the labor time (or cost) to produce the "doubled" production unit from the previously given production unit
270 hours for 4 units | 243 hours 8 units
94
Type one of the learning curve application is useful when?
Estimating cost of a production lot of a specific quantity of items planned for a future contract, which is then used for programming and budgeting. It is later used when negotiating the actual contract
95
Type two of the learning curve application is useful when?
When determining the learning curve rate used by potential contractors and evaluating their price proposals for production contracts.
96
A contract is valid when there is what?
1) Has been an offer 2) has been an acceptance of that specific offer 3) has been an intent between two or more parties to create a legal relationship 4) the agreement is supported by value consideration
97
The contracting process is governed by which regulations?
1) Federal Acquisition Regulations (FAR) | 2) Defense FAR
98
What are the two different categories of a contract?
1) Fixed-Price | 2) Cost-Reimbursement Contracts
99
In which category of a contract does the contractor bear the majority of the risk?
Fixed-Price
100
In which category of a contract does the government bear the majority of the risk?
Cost-Reimbursement Contract
101
Why does the government bear the risk in a cost-reimbursement contract?
Because if the work turns out to need more money than estimated, the government must pay those allowable, allocable, and reasonable costs
102
What is an integrated tool that relates technical performance to its associated cost and schedule, measures the work progress in objective terms, and states the value of the work completed in dollars? It is also used to measure contractor performance
Earned Value Management (EVM)
103
Each work package for Earned Value Management consists of what?
Scope of work and its related budget
104
The result of the Earned Value Management is known as what?
Budgeted Cost of Work Scheduled (BCWS) also called Performance Measurement Baseline (PMB)
105
Cost Variance =
Budgeted Cost Work Performed - Actual Cost
106
A cost variance is favorable when?
Actual costs incurred are less than budgeted costs for the work completed.
107
Schedule Variance =
Budgeted Cost of Work Performed - Budgeted Cost of Work Scheduled
108
A schedule variance is favorable when?
Budget for the work performed is greater than the budget for work scheduled
109
What is a method to analyze the multiple tasks or activities required to complete a given project or contracted work effort?
Program Evaluation and Review Technique (PERT)
110
PERT analyzes what?
The time required to complete each task and to identify the minimum time needed to complete the total project.
111
What is the longest possible continuous path from the start event to the terminal event?
Critical Path
112
What does the Critical Path in the PERT chart indicate?
the total calendar time required to complete all activities of the project.
113
Which type of chart for useful planning and project scheduling lays out the project in the order in which the tasks need to be completed allows the manager to assess how long a project should take, to manage the dependencies between the activities and to determine the needed resources?
Gantt Chart
114
True or False: | PERT Chart is better at displaying the schedule and resources used in a project than the Gantt Chart?
False
115
What is a systematic approach to the problem of choosing the best method of allocating scarce resources to achieve a given objective?
Economic Analysis
116
In economic analysis all costs and benefits are adjusted to what?
Present Value
117
What provides the basis for financial planning and decision-making in the Defense Acquisition System, as well as, the expected cost input to the PPBE process?
Cost and Economic Analysis
118
True or False: | There are no mandated thresholds for using economic analysis for DoD Applications?
True
119
A threshold of how much applies to construction and thus may be a reasonable threshold to require an economic analysis?
$1 Million
120
An economic analysis is prepared using ___________ basis in compliance with applicable DoD or component guidance, as well as function program guidance.
Net Present Value
121
What are benefits that can be assigned a numeric value, such as dollars, physical count of tangible items, or percentage of change?
Quantifiable Benefits
122
Which type of quantifiable benefits result in the actual reduction of an approved program if the benefit occurs during the POM period?
Cost Savings
123
Which type of quantifiable benefits result in a reduction or elimination of some future resource requirements? For example: (if the status quo requires the purchase of certain hardware, which has no be included in an approved program, but implementation of the preferred alternative does not require its purchase and does not degrade current capability)
Cost Avoidance
124
What type of quantifiable benefit result in a reduction in future personnel time and effort requirement associated with a function or assigned task that has been included in an approved program?
Productivity Improvements
125
What are some examples of non-quantifiable benefits?
Improved Morale, compatibility, improved quality and security, and improved readiness
126
Benefits that do not have quantitative measure and instead are addressed qualitatively in economic analysis are known as what?
Non-Quantifiable Benefits
127
What encompasses a large body of scientific theories and methods used to collect and analyze quantitative and qualitative facts to support decision-making and problem-solving processes/
Statistics
128
What are the two distinct disciplines of statistics?
Descriptive Statistics | Inferential Statistics
129
What type of statistics describe a collection of quantitative information in a way that is easy to understand and interpret?
Descriptive
130
What type of statistics tell us things about specific collection of data we have gathered?
Descriptive
131
What is the arithmetic average of a distribution and is useful for tracking trends in data?
Mean
132
What is the "middle value" in a list of numbers after sorting the list in increasing order?
Median
133
What is the most frequent occurring score in a distribution of scores?
Mode
134
What indicates how data is distributed as a whole?
Measures of Dispersion
135
Which measure of dispersion is often used to describe the limits of sample of data?
Range
136
How is a range calculated?
Subtract the smallest number from the largest number
137
What measure of dispersion is a measure of how a set of values is spread around the mean?
Standard Deviation
138
By laws of mathematics, what percentage of population when considering measures of dispersion falls within 1 standard deviation of each side?
68.27%
139
By laws of mathematics, what percentage of population when considering measures of dispersion falls within 2 standard deviations of each side?
95.45%
140
By laws of mathematics, what percentage of population when considering measures of dispersion falls within 3 standard deviations of each side?
99.74%
141
Which measure of dispersion includes methods used to examine a sample of a population and make inferences about the entire population based on analysis of the sample data?
Inferential Statistics
142
What is the formula for percentage change?
((New# - Old#) / Old#) x 100
143
What is a number between -1 and 1 which measure the degree to which two variables are linearly related?
Correlation Coefficient
144
If we have a perfect linear relationship (all data points on a straight line) we have a correlation coefficient of _____ for a positive correlation and of ______ for a negative correction and we have strong predictability
1;-1
145
A correlation coefficient of 0 means what?
There is not a linear relationship between the variables
146
To obtain the coefficient of correlation of data sets it would be necessary to calculate ______ which can be performed in ________
"Pearson's r;" Excel
147
What is the square of "r" or the square of the correlation coefficient, and tells us how reliably the data will fall directly on the "best fit" line?
Coefficient of Determination
148
When considering the coefficient of determination, the larger the value the _________________.
stronger the relationship
149
When considering the coefficient of determination values close to 1 indicate what?
Excellent Linear Reliability
150
What measure the amount of dispersion expressed as a decimal or a percentage? It helps explain how much variability exists between the variables.
Coefficient of Variation
151
When considering the coefficient of variation the smaller the value (variability) the ____________.
better the predictability
152
Estimates prepared in constant dollars _________ the changing spending power of the dollar over time because what?
Do not Show; because they must be adjusted for inflation
153
Who is responsible for developing inflation guidance by appropriation for government estimates?
OMB
154
What regulation contains inflation guidance and when is it distributed?
OMB Circular A-94; Every January
155
What is the formula for the present value factor?
PVF = 1/ (1+D)^t
156
In the PVF "d" represents what?
discount rate
157
In the PVF "t" represents what?
project year
158
Net Present Value =
Total PV of Benefits - Total PV of Costs
159
What is the point (e.g. number of years or fractional years) at which the cumulative costs (investment plus sustainment) of two alternatives equal?
Break-Even Point
160
Consider an opportunity for a new system that has a $500,000 cost and annual operating cost of $25,000. The proposed system will replace the current capability that has an annual operating cost of $150,000. How much savings will this proposed system generate and how many years will it take for the savings in operating costs to equal the investment cost of the proposed new system?
$500,000 / ($150,000 - $25,000) = 4 years