Module 10 Flashcards

1
Q

What are some alternate names for Change Orders?

A

Project change requests; Change Management Requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does EVM stand for?

A

Earned Value Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are some of the key values of EVM?

A

planned value (PV), earned value (EV), actual cost (AC), budget at completion (BAC = total PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Describe 4 measures that can be taken from the EVM, and how to calculate them

A

Cost Variance (CV) = EV-AC
Schedule Variance (SV) = EV-PV
Cost Performance Index (CPI) = EV/AC
Schedule Performance Index (SPI) = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

For each of CV, SV, CPI, SPI, describe what is good and what is bad

A

Cost Variance (CV) = EV-AC positive is good
Schedule Variance (SV) = positive is good
Cost Performance Index (CPI) = over 1 is good
Schedule Performance Index (SPI) = over 1 is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

List 4 ways to calculate EAC

A
EAC = BAC / CPI
EAC = AC + ETC (new estimate for remaining)
EAC = BAC - CV = AC + (BAC - EV)
EAC = EAC = AC + (BAC-EV) / (CPI*SPI)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is EAC?

A

estimate at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly