Module 10 Flashcards
What are some alternate names for Change Orders?
Project change requests; Change Management Requests
What does EVM stand for?
Earned Value Management
What are some of the key values of EVM?
planned value (PV), earned value (EV), actual cost (AC), budget at completion (BAC = total PV)
Describe 4 measures that can be taken from the EVM, and how to calculate them
Cost Variance (CV) = EV-AC
Schedule Variance (SV) = EV-PV
Cost Performance Index (CPI) = EV/AC
Schedule Performance Index (SPI) = EV/PV
For each of CV, SV, CPI, SPI, describe what is good and what is bad
Cost Variance (CV) = EV-AC positive is good
Schedule Variance (SV) = positive is good
Cost Performance Index (CPI) = over 1 is good
Schedule Performance Index (SPI) = over 1 is good
List 4 ways to calculate EAC
EAC = BAC / CPI EAC = AC + ETC (new estimate for remaining) EAC = BAC - CV = AC + (BAC - EV) EAC = EAC = AC + (BAC-EV) / (CPI*SPI)
What is EAC?
estimate at completion