Module 05 Flashcards

1
Q

Project Consists of Two Main Components. What components?

A

The project work that needs to be performed

The schedule to perform the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What makes up the the Project Work (Scope)

A

The Project Charter
The Scope Statement
Work Breakdown Structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What makes up the the Project Schedule

A

What activities need to be performed
Who will perform them
When will the activities be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Output of Activity Definition?

A

Activity List
Activity Attributes
Milestone List and Requested Changes to WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is an Activity List

A

All activities necessary and sufficient to produce the product deliverables

Defined in sufficient detail to promote understanding by project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do we identify activities?

A

Select systems development life cycle model (SLCM)

Map life cycle process activities to SLCM using available standards and guidelines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Activity Sequencing

A

Identifies the dependencies among the schedule activities and orders the activities accordingly

Tasks may have dependencies because they require the same resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Precedence Relationships?

A

Finish to Start
-Initiation of the successor activity depends upon completion of the predecessor activity

Finish to Finish
-The completion of the successor activity depends upon the completion of the predecessor activity

Start to start
-The initiation of the successor activity depends upon the initiation of the predecessor activity

Start to finish
-The completion of the successor activity depends upon the initiation of the predecessor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Three Types of Dependencies, what are they?

A

Mandatory Dependencies

Discretionary Dependencies

External Dependencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Mandatory Dependencies

A

Inherent to the schedule activities (e.g. software must be developed before it can be tested)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Discretionary Dependencies

A

Dependencies at the discretion of the project team (e.g. acceptance test with marketing before accounting)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

External Dependencies

A

Involves a relationship between a project activity and a non-project activity (e.g. Windows Vista Delivered)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Critical Path

A

The longest path (sequence of activities) in a project schedule network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Early Start

A

The earliest an activity can start. It is the largest early finish time of all its immediate predecessors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Early Finish

A

The earliest an activity can finish if all its preceding activities are finished by their early finish times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Late Start

A

The latest an activity can start and not delay a succeeding activity

17
Q

Late Finish

A

The latest an activity can finish and not delay a succeeding activity

18
Q

Float Time (Slack)

A

Time an activity can be delayed and not become critical

19
Q

Project Network Calculations

A
Early Start and Early Finish
-Forward Pass Through the Network
Late Start and Late Finish
-Backward Pass through the Network
Slack or Float
-Late Start – Early Start
20
Q

Critical Path Method? (Schedule Network Analysis)

A

Used to identify the schedule flexibility

The critical path is the longest path (sequence of activities) in a project schedule network diagram

Determines the length of the project

21
Q

Resource Leveling (Schedule Network Analysis)

A

Involves taking a part of the resources from one activity and assigning it to another

Change the durations and possible the critical path

22
Q

Crashing (Schedule Compression)

A

Used to decrease the project duration with minimal additional cost

A number of alternatives are considered, including adding additional resources

23
Q

Fast Tracking (Schedule Compression)

A

Decrease project duration by performing project phases or some schedule activities within a phase in parallel that would normally be performed in sequence

24
Q

Schedule Development Output

A

Project Schedule Network Diagram
Gantt Chart
Milestone Chart
Schedule Baseline

25
Q

How are project schedule represented?

A

The Gantt chart

26
Q

What is a Gantt chart

A

The Gantt chart shows tasks, dependencies and milestones using different shapes

27
Q

Schedule Development Concerns

A

Actual start date

Uncertainty on the availability of resources
Identification and preparation for activities on the critical path

Risks involved or “what if” scenarios

The hard start/finish dates for activities or for the project that came down the pipeline from important stakeholders