Module 05 Flashcards
Project Consists of Two Main Components. What components?
The project work that needs to be performed
The schedule to perform the work
What makes up the the Project Work (Scope)
The Project Charter
The Scope Statement
Work Breakdown Structure (WBS)
What makes up the the Project Schedule
What activities need to be performed
Who will perform them
When will the activities be performed
Output of Activity Definition?
Activity List
Activity Attributes
Milestone List and Requested Changes to WBS
What is an Activity List
All activities necessary and sufficient to produce the product deliverables
Defined in sufficient detail to promote understanding by project team
How do we identify activities?
Select systems development life cycle model (SLCM)
Map life cycle process activities to SLCM using available standards and guidelines
What is Activity Sequencing
Identifies the dependencies among the schedule activities and orders the activities accordingly
Tasks may have dependencies because they require the same resource
Precedence Relationships?
Finish to Start
-Initiation of the successor activity depends upon completion of the predecessor activity
Finish to Finish
-The completion of the successor activity depends upon the completion of the predecessor activity
Start to start
-The initiation of the successor activity depends upon the initiation of the predecessor activity
Start to finish
-The completion of the successor activity depends upon the initiation of the predecessor activity
Three Types of Dependencies, what are they?
Mandatory Dependencies
Discretionary Dependencies
External Dependencies
Mandatory Dependencies
Inherent to the schedule activities (e.g. software must be developed before it can be tested)
Discretionary Dependencies
Dependencies at the discretion of the project team (e.g. acceptance test with marketing before accounting)
External Dependencies
Involves a relationship between a project activity and a non-project activity (e.g. Windows Vista Delivered)
Critical Path
The longest path (sequence of activities) in a project schedule network
Early Start
The earliest an activity can start. It is the largest early finish time of all its immediate predecessors.
Early Finish
The earliest an activity can finish if all its preceding activities are finished by their early finish times