EVM Flashcards

1
Q

Generic Project Control Process

A
  1. Set a Baseline Plan
  2. Measure Progress and Performance
  3. Compare Actual against Plan
  4. Take Action
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you measure project performance

A

Performance is Measured against Baselines

  • Schedule
  • Cost
  • Scope
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value Management (EVM)

A

Realistic Estimate of Performance against a time-phased budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Earned Value Management Criteria

A
  1. Define the Project Scope (WBS)
  2. Plan and schedule the project (CPM)
  3. Form cost account plans and budget them to specific functions
  4. Establish and maintain a performance measurement baseline (cost baseline)
  5. Monitor project performance and forecast the final results (earned value analysis)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Three Major Components of EVM

A

Planned Value (PV)

Earned Value (EV)

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Planned Value (PV)

A

Authorized cost for the scheduled work on the project or a project activity up to a given point on the timescale. Also called Budgeted Cost of Work Scheduled (BCWS)

Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Earned Value (EV)

A

The value of the actually performed work expressed in terms of the approved budget for a project or a project activity for a given time period. Also called Budgeted Cost of Work Performed (BCWP).

What the project really accomplished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Actual Cost (AC)

A

Total cost actually incurred until a specific point on the timescale in performing the work on a project. Actual Cost of Work Performed (ACWP).

What the project spent or burned to accomplish what it did

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost Variance

A

(CV) = EV - AC

Earned Value - Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Earned Value (EV)

A

EV = BAC * (work completed / total work required)

BAC = Budget at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Planned Value (PV)

A

PV = BAC * (time passed / total schedule time)

BAC = Budget at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Schedule Variance (SV)

A

SV = EV – PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly