MISC. STUFF Flashcards
1
Q
Inspectors during stringing activity should inspect for which of the following except for A. Scratches and gouges on pipe coating B. Pipe thickness and grade of pipe C. Tag ropes and pipe spacers D. Pipe tallies E. None of these
A
C
2
Q
During a pressure test, the pressure recorders and deadweight gauge shall be located at a safe distance least\_\_\_\_ from the facility being tested A. 150’ B. 500 ‘ C. None of these D. 100 meters E. 300’
A
C
3
Q
Per INGAA foundation guidelines, the crossing company will identify areas where blasting will be used along the route within \_\_ feet of the existing facilities to be crossed A. 250 B. None of these C. 300 D. 50
A
C
4
Q
Safety equipment and supplies should be readily available during a pressure test and should include at a minimum A. Mobile light plants B. Emergency spill kit C. Ladders D. Whip checks E. Fire extinguishers F. Fire trucks G. Warning signs and barricades
A
A,B,C,D,E,G
5
Q
Installation of uncased carrier pipe under railroad and highway crossings is___
A. Preferred
B. Not allowed
A
A
6
Q
Per Title 50 CFR 21, licensed vets must keep records for \_\_\_ of all migratory birds that die while in their care A. 3 years B. 7 years C. 10 years D. 5 years E. 1 year
A
D
7
Q
According to 33 CFR 321, any impoundment structures that completely spans a navigable water of the U.S and that may obstruct interstate waterborne commerce refers to\_\_\_\_ A. None of these B. Dikes, dams, and wires C. A pipeline route D. Dikes and dams E. A P/I
A
D
8
Q
Active excavation area is the area where the edge of the disturbance is within\_\_\_ feet of the centerline of existing facility A. 75 B. 25 C. 100 D. 50
A
B
9
Q
FBE is a type of \_\_ A. Protective clothing B. Coating C. Soil D. Blast media
A
B
10
Q
Continuous or broken slag lines or wagon tracks-are usually found at the fusion zone A. None of these B. Elongated slag inclusion C. Isolated slag inclusion D. Incomplete penetration E. Lack of fusion
A
B
11
Q
\_\_\_\_\_ are authorized to decide whether department of the army authorization for a dam or dike in an intrastate navigable water of the U.S. will be issued. A. Governors B. Environmental inspectors C. District engineers D. Secretary of the army advisors E. None of these
A
C
12
Q
Choose the correct diameter of a pipe rounded to the nearest inch. The pipe has a 157” circumference A. 57” B. 50” C. 48” D. 47”
A
B
13
Q
Piston gauge is also known as a \_\_\_ A. Pressure tee B. Pressure valve component C. None of these D. Dead-weight tester E. Pressure driver
A
D
14
Q
The pipeline safety division of the DOT’S PHMSA A. Ops B. None of these C. PHS D. OSHA
A
A
15
Q
Normally used to separate a test section into smaller test segments in order to identify leaks more readily or used to establish a test boundary A. Divider tee B. Separation gasket C. Freeze plug D. None of these E. Pig scraper
A
C
16
Q
An oscilloscope is ___
A
A precision device that’s uses a visual instrument to depict periodic changes in an electric quantity, such as voltage or current
17
Q
Name the standard that crude oil pipeline valves must be manufactured to per B31.8 A. ANSI B16.38 B. MSS SP-78 C. API6D D. API6A
A
C
18
Q
Soil classification has been determined as type A. The bottom floor of the excavation is measured as 8’ wide. The depth of the bell hole is 7’. How wide should the top of the bell hole be if employees are planning on entering that section of the bell hole using acceptable slope ratio? A. 18.5’ B. None of these C. 22’ D. 15.5’ E. 29’
A
A
19
Q
The application of the monogram can be applied only by the license at the \_\_\_ per API-SPEC-Q1A A. Licensed facility B. None of these C. Project lay down yard D. Train yard E. Right-of-way
A
A