Body Of Knowledge Flashcards
According to OSHA a “protective system” is defined as
A. Method of protecting employees by using a shield
B. Method of protecting employees from cave ins
C. A system that assures employees are safe from all hazards
D. A system that assures employees are safe from expected hazards
B. 29 CFR1926.650
Design and development inputs shall be identified and reviewed for?
A. Punctuation, completeness, and lack of conflict
B. Inspection test plans, completeness, and lack of time table
C. Accuracy, completeness and lack of conflict
D. Proximity to underground services as a primary factor in development
C. Q1 5.4.2
The excavator calls the One Call Center prior to excavation at least:
A. Two working days and no more than ten working days prior to
Beginning excavation
B.One working day and no more than seven working days prior to
Beginning excavation
C. Five working days and no more than ten working days prior to
Beginning excavation
D. Within three working days
A. CGA 5-1
Encroachment area is the area where the ground disturbance occurs within:
A. 10 feet of the centerline of the existing facility or other easement
B. 25 feet from the edge of the existing facility or other easement
C.50 feet of the centerline of the existing facility or other easement
D. 50 from the edge of the existing facility or other easement
C. INGAA NG SECT II
The pressure recorders and deadweight gauge shall be located at a safe distance at least: A. 100 ft from the facility being tested B. 150 ft from the facility being tested C. 75 ft from the facility being tested D. 200 ft from the facility being tested
A. INGAA CS-S-9 4.8.9
In compliance with the Uniform color code the route and or areas to be excavated shall be identified by: A. Pink B.Blue C.White D. Black on white
C. CGA APPB
Markings may include one or any combination of the following: paint, chalk, flags, stakes, brushes, or offsets. Matching markings to existing and expected surface conditions is the responsibility of: A. Locators B. Excavators C. Project Owner D. Facility Owner
A. CGA 4-8
Sub part G of 49CFR192 prescribes minimum requirements for:
A. Design of transmission pipelines and mains
B. Construction of transmission pipelines and mains
C. Design and fabrication of transmission pipelines and mains
D.Design and quality assurance for transmission pipelines and mains
B. 49CFR192.301
If a newspaper was seeking information about the project, are inspection personnel allowed to interact with them to answer their questions?
A. Yes
B. No
C. Only if expressly allowed
D. Only if the chief inspector is present
C. 1169 4.10
Before placing new gas pipeline in service all piping and components must be subjected to:
A. Pressure test of 133W% of MOP for 4 hours
B. Pressure test of 125W% of MOP for 4 hours
C. Pressure test of 110% of MOP for 8 hours
D. Pressure test of 125% of MOP for 8 hours
B. 49CFR195.304
A detailed design developed from operating requirements and conforming to code requirements, including all necessary drawings and specification, governing a liquid petroleum pipeline installation is also know as? A. Project Plan B. Project summary C. Engineering design D. Architectural design
C. B31.4 400.2
Planned, systematic, and preventative actions that are required to ensure that materials, products, and services will meet specified requirements is called? A. Inspection and test plan B. Inspection procedures C. Quality assurance system D. Quality control system
D. B31.8 806
Any physical objects detected by an in-line inspection device that may be anomalies, components, nearby metallic objects, or some other item are also known as? A. Themes B. Captures C. Features D. Reports
C. 1110 3.1.12
What describes “rework” the best?
A. Filing the toes of the weld to create the correct profile
B. Any grinding or welding on a completed weld to correct an individual defect that was rejected by examination
C. The removal of an imperfection that requires grinding and/or welding that is performed prior to visual or NDT examination
D. Any grinding or welding on a completed weld to correct potentially reject able indications
C. 1104 3.1.25
General basic requirements for chief inspector qualification are? A. Environmental and pollution control B. NDT level II and III experience C. CWI and welding D. Personnel hiring
A. 1169 ANNEX A
What type of hazard is a waterway crossing? A. Environmental B. Job site C. Site-specific D. Climatic
C. 1169 5.2.2
What would a continuous run of pipe between adjacent blocks valves be called? A. A pipeline B. An isolation area C. An isolation blocked section D. A pipeline section
D. B31.4 400.2
Does a section of pipe removed and scheduled for reuse, but then reinstalled in the same location need to be retested? A. Hydrostatic testing required B. Pneumatic testing required C. Helium leak testing required D. No testing required
D. B31.8 817.1.1
In international codes and standards, this is often referred to as the maximum steady state operating pressure or maximum allowable operating pressure. A. Operating pressure limit B. Operating max pressure C. MOP D. MOAP
A. 1110 3.1.22
The letter “I” identifies shipping names appropriate for:
A. Describing materials in intrastate transportation by rail
B. Describing materials in interstate transportation by rail
C. Describing materials in transportation between NAFTA members
D. Describing materials in international transportation
D. SUBPART B 49CFR172.101
Who is responsible for all safety on the job site? A. Contractor B. Owner operator C. Chief inspector D. 1169 inspector
A. 1169 5.2.3
What identifies hazards that necessitate the use of PPE? A. Contract B. Inspection plan C. JSA D. Work permit
C. 1169 5.3.1
Which is an example of a sustained load?
A. The total length of the pipeline including components, fluids, and slurries
B. The total volume of the pipeline including components, fluids, and slurries
C. The total flow and volume of the pipe line including components, fluids and slurries
D. The weight of the pipeline including components, fluids, and slurries
D. B31.4 401.1.2
What is the standard of acceptance for welds of piping systems operating at hoop stress levels 50% of the SMYS? A. ASME B31.4 B. ASME B31.8 C. API 1110 D. API 1169
B.
What is a near miss?
D. Occurrences that have happened, but did not lead to injury or damage
In regards to road and highway use, what should the inspector be aware of?
A. Size and weight restrictions for heavy equipment
B. Size and weight of the equipment required
C. Size and capacity of the equipment
D. Size, weight, and capacity of the equipment
A. 1169 5.7.2
It is not necessary to vary the design stress for metal temperatures between what range? A. -20F and 250F B. -20F and 150F C. -50F and 250F D. -50F and 150F
A. B31.4. 401.2.3.7
Which pressure test is designed to establish the operating pressure limit of a pipeline? A. Strength pressure test B. Hydrostatic pressure test C. Spike pressure test D. Leak pressure test
A. 1110 3.1.35
What is LOTO?
A. A practice to ensure exposure to electrical hazards
B. A practice to prevent exposure to electrical hazards
C. A practice to ensure all welders are on site and working
D. A practice to prevent exposure to all hazards
B OR D. 1169 5.9.2 5.9.3
Where shall the requirements for verifying conformance with applicable product quality plans be included during production? A. Engineering design B. Right to know area C. Shop routers or travelers D. Documented procedures
C. Q1 5.7.1.3
What would be considered a mechanical property of a finished weld? A. Soundness B. Ductility C. Strength D. Notch toughness
B. 1104 5.1
There are three key pieces of joint design information that need to be included on a qualified WPS they are ?
A. Angle of bevel, size of the root face, and root opening dimension
B. Angle width, size of the root face, and root opening dimension
C. Angle of bevel, angle of root face, and root opening dimension
D. Angle of the bevel, size of root face, and root opening angle dimension
A. 1104 5.3.2.4
How is the test pressure ratio derived?
A. Maximum pressure divided by operating pressure limit
B. Test pressure divided by operating pressure limit
C. Operating pressure divided by test pressure
D. Operating pressure multiplied by test pressure
B. 1110 3.1.39
A uniform color code marking system is employed to identify underground facilities and marking construction ROWS. The color code is adopted: A. Worldwide B. US and Canada C. States D. Nationwide
D. CGA APXB
When steel butt welded fittings are used, they shall conform to? A. ASME B16.11 B. ASME B16.9 C. MSS-SP-55 D. ASME B16.49
B. B31.4 404.1.1
All excavations made in type B soil 20ft or less in depth, which have vertically sided lower portions shall be?
A. Approved for entry with no additional support or sheliding
B. Required to have the lower portion be shielded or supported to a height at least 18inches above the top of the vertical side
C. Required to have the lower portion and half the upper portion be shielded or supported entirely
D. Required to have the lower portion be shielded or supported to a height equal to the top of the vertical side
B 1169 5.10.3
A confined space is?
D. 1169 5.11.1. A space that can be entered bodily by an individual but is not designed for continuous occupancy and has limited and restricted means of entry and exit
What information concerning position should be noted on the qualified WPS? A. Horizontal position B. Vertical position C. Roll or position welding D. Heat input and position
C 1169. 5.3.2.8
Pipelines are pressure tested to demonstrate?
A. Their total capacity
B. Their fitness for service
C. Their maximum allowable operating pressure
D. Their maximum operating pressure
B. 1110
According to OSHA structural ramps for employee access or egress shall be
A. Fabricated from structural steel products
B. Designed in accordance with AWS D1.1
C. Fabricated in accordance with AWS D1.1
D. Designed by a competent person
D. CFR1926.651