What are the steps in the migration stage?
consultative sales engagement added to SOW
migration planning
peer SA review and approval
handover of plan to IS
What are the four parts of the Migration Process?
Environment
Planning
Execution
Cutover
What are the steps in block migration?
Preconfigure
Set up import
start import
cutover import
What is the preconfigure phase in block migration?
setting up network connectivity
What is the set up import phase in block migration?
install/upgrade required host plugin that accesses storage to be imported
add source system to the new cluster
select one or more volumes/consistency groups to be imported
select to add hosts that access storage to be imported - host builds inactive IO paths to the destination volumes
set import schedule/policies
What is the start import phase in block migration?
destination volume created for each source volume
volume group automatically created for each consistency group selected for import
active IO and inactive IO paths from host switched to redirect the IO paths to new cluster
What is the cutover import phase in block migration?
can only be performed when import processing state is “Read for Cutover”
What are the steps in file migration?
prepare the source for an import
add the remote system to establish import connection
create a file import session
start the file import session
cutover the import session
commit the import session
What is the prepare the source for an import stage in file migration?
create a source import network interface
What is add the remote system to establish import connection phase?
establish a file import interface connection to the source
What is the create a file import session phase?
specify all required options for the importW
What is the start the file import session phase?
during the session destination file mobility network, NAS server, and destination file systems created
configuration from the source is imported from the source into the destination NAS
What is the cutover the import session phase?
production interfaces disabled on the source side and enabled on destination side - incremental copy occurs from source to destination
What is the commit the import session phase?
protocol data connections to the source terminate and synchronize steps stop - destination import is deleted
What is the File System Migration Assistant (FSMA)?