ME352 - Exam Questions Flashcards

1
Q

Types of system models

A

Physical
Analytical
Simulation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Adv and disadvantages of simulation

A

Good for complicated systems
But only statistical estimates with uncertainty and noise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Static vs dynamic simulation

A

Passage of time plays no active or meaningful role in model execution; can often be done in
spreadsheets

Passage of time is essential and explicit in model execution; can almost never be done in
spreadsheets except for very simple models

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Continuous-change vs discrete-change for dynamic models

A

Continuous-change: State variables can change continuously over time, at any point in
continuous time

Discrete-change: State variables can change only at instantaneous, separated, discrete
points in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Deterministic vs. stochastic

A

Deterministic: All input values are fixed, non-random constants

Stochastic: Some inputs are random draws (or samples or realizations) from probability
distributions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Simulation methods

A
  1. Monte Carlo Method – use paper, calculator, dice, etc.
  2. Computer generated graphics using a simulation engine, Creo, etc.
  3. Computer generated tables of random numbers – spreadsheets
  4. Java applets, Visual Basic routines, etc.
  5. Computer methods using a simulation language, e.g. SIMAN in
    Arena, Simio ,…
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Explain how variant machining process planning works; what are the drawbacks of this approach

A

There are four steps in variant machning process planning:
* define the coding scheme;
* group the parts into part families;
* develop a standard process plan; and
* given a part to be made, retrieve and modify the standard plan to arrive at the final process
plan.

drawbacks of this approach:
* The components to be planned are limited to the similar components previously planned;
* Experienced process planners are still required to modify the standard plan for a specific
component;
* The approach cannot be used in an entirely automated manufacturing system, without
additional process planning and human intervention.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Root causes of the bullwhipe effect

A

Order Batching
Price fluctuations
Lack of communication
Free return policies
Demand information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Order of importance of taylor equation

A

v&raquo_space; v_f&raquo_space; a_p

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Scope of planning

A

Long-term
Capacity Planning
1. Facility Size
2. Equipment Procurement

Intermediate-term
Aggregate Planning
1. Facility Utilisation
2. Personnel needs
3. Subcontracting

Medium-term
Master Schedule
1. MRP
2. Dis-aggregation of master plan

Short-term
Short-term Scheduling
1. Work centre loading
2. Job sequencing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Input and Outputs of aggregate plan

A

Input: Demand forecast
Output:
 production rate (units completed per unit of time)
 workforce level (number of workers)
 inventory level (from previous period)
The projected costs if the production plan was implemented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Aggregate planning approaches

A

Reactive approach
 Allow volume forecasts based on Marketing plan to drive production planning
Proactive approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Production Planning strategies

A

Chase strategy
 Match the production rate to meet the demand rate by adjusting the
workforce level (hiring/firing) as the demand rate changes. Minimize finished
good inventories by matching demand fluctuations.
Level strategy
 Use a stable workforce working at a constant production rate. Use
inventories and backorders to absorb demand peaks and valleys.
Hybrid strategy
Combine elements of the chase/level strategies with other
options:
 Stable workforce but variable work rate (overtime/undertime).
 Subcontract production or hire part-time or temporary workers
to cover short-term peaks.
 Varying work force size by hiring or layoffs
 Influencing demand
 Complementary product lines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Aggregate plan must balance

A

 Costs are important but so are:
 Customer service
 Operational effectiveness
 Workforce morale

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Master Production Schedule (MPS)

A

A time-phased plan specifying how many and when the firm plans to
build each end item

To avoid overloading or underloading the production facility so that
production capacity is efficiently utilised and low production costs
result.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Inputs and outputs of master scheduling process

A

Inputs:
Beginning inventory
Forecast
Customer orders

Outputs:
Projected inventory
Master production schedule
Uncommitted inventory

17
Q

Material Requirements Planning

A

 Material requirements planning (MRP) is a means for determining the
number of parts, components, and materials needed to produce a
product (end item)
 MRP provides time scheduling information specifying when each of
the materials, parts, ordered or produced and components should be
 What, when, how many?
 MRP is an information system

18
Q

An MRP system is intended to simultaneously meet three objectives:

A

 Ensure materials and products are available for production and delivery to
customers.
 Maintain the lowest possible level of inventory.
 Plan manufacturing activities, delivery schedules and purchasing activities.
What, when, how many?

19
Q

Material Requirements Planning input and data requirements and outputs:

A

Critical input and data requirements:
 Master Production Schedule (MPS)
 Bill of Materials (BOM)
 Inventory database

Many outputs – but primary ones are:
 Planned orders to be released at a future time.
 Order release notices to execute the planned orders.
 Changes in due dates of open orders due to rescheduling.
 Cancellations or suspensions of open orders due to cancellation or
suspension of orders on the master production schedule.
 Inventory status data. Planned order releases

20
Q

Mass Production Systems

A

 Low product variety
 High production volumes
 Specialized labor
 Dedicated equipment
 High reconfiguration costs
 Make-to-stock production

21
Q

Batch Production Systems

A

 Medium product variety
 Products are made in larger lots
 products are made to stock
 Significant setup costs
 Programmable/reconfigurable
equipment

22
Q

Job Shops

A

 High product variety
 Products are made in small
lots
 Products are made to order
 Flexible equipment and
labor
 Small setups

23
Q

Breakdown Maintenance vs Preventive maintenance

A

 Breakdown Maintenance: Waiting until equipment fails before
repairing or servicing it
 Preventive Maintenance (PM): cleaning, or replacing parts to prevent sudden failure

24
Q

Types of inspection for determining maintenance times

A

Infrared cameras
Detecting overheating cabling
Borescopes
Vibration monitoring

25
Q

Availability vs reliability

A

Availability is a measure of the % of time our equipment is in an
operable state. Availability = System up-time / (System up-time + System
down-time)
Whereas reliability is a measure of how long our equipment performs its intended function.

26
Q

2 types of availability

A

Inherent
Inherent availability is the steady state availability when considering
only the corrective maintenance (CM) downtime of the system.

Operational
Operational availability is a measure of the “real” average
availability over a period of time and includes all experienced
sources of downtime, such as administrative downtime, logistic
downtime, etc.

27
Q

6 M’s of Production

A

Manpower
Method
Machine
Material
Milieu
Measurement

28
Q

Principal queue parameters

A

Calling population (infinite vs finite, homogeneous (one type of customer/job, heterogeneous (several different kinds of customers/jobs))
Arrival process (pattern of arrival) - assume poisson arrival process (with interarrival times that follow exponential distribution)
Queue discipline (multiple vs single, differentiate who can join what, how jobs are selected - FCFS)
Number of servers
Service process (how do they get fulfilled, fixed time to complete or not) - exponential service times often assumed

29
Q

M/M/1 - M meaning

A

Markovian

30
Q

Characteristics of good facility layout

A

■Minimisedmaterials-handling costs.
■Maximised and efficientuse of space.
■Ease of accessibilityby support services
e.g. maintenance.
■Few, or no, bottlenecksin moving material or people.
■Flexibility.
■Facilitated communicationbetween all those involved.
■Reduced manufacturing cycle time or
customer servicetime.
■Eliminated or reduced waste.
■Compliance with health and safety standards.

31
Q

Supply chain order

A

Customer
Retailer
Wholesaler
Distributor
Factory