Mayor's Gala (new Surrey City Hall) Flashcards
1
Q
How did the new Surrey City Hall get built (contractually)?
A
- PCL originally planned to sign $70 million contract in 2011 for complete the city hall
- Surrey changed the plan and instead a smaller contract was signed for PCL to complete a parkade and geo-exchange facility
- Surrey got PCL to complete the rest of the project using change orders
2
Q
Why did PCL file claims at the end of the project?
A
- PCL claimed Surrey was liable for millions made in claims against PCL by subs
- PCL completed over 360k in unpaid gala prep work
3
Q
What did Surrey say in its counter-claim against PCL?
A
- PCL did negligent work and failed to meet milestone events in schedule
- Any loss or damage subs suffered was due solely to failures of PCL or themselves
- PCL owed city in damages for constructing deficient and incomplete geo-exchange system
- PCL deprived Surrey from being able to mitigate gala costs since it repsented to city on several occasions that the gala need not to be rescheduled
4
Q
What was the end result (at the end of the news article)?
A
Surrey and PCL were trying to reach an out-of-court settlement
5
Q
What could have been done better to prevent this fiasco?
A
your answer