Mayor's Gala (new Surrey City Hall) Flashcards

1
Q

How did the new Surrey City Hall get built (contractually)?

A
  • PCL originally planned to sign $70 million contract in 2011 for complete the city hall
  • Surrey changed the plan and instead a smaller contract was signed for PCL to complete a parkade and geo-exchange facility
  • Surrey got PCL to complete the rest of the project using change orders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why did PCL file claims at the end of the project?

A
  • PCL claimed Surrey was liable for millions made in claims against PCL by subs
  • PCL completed over 360k in unpaid gala prep work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What did Surrey say in its counter-claim against PCL?

A
  • PCL did negligent work and failed to meet milestone events in schedule
  • Any loss or damage subs suffered was due solely to failures of PCL or themselves
  • PCL owed city in damages for constructing deficient and incomplete geo-exchange system
  • PCL deprived Surrey from being able to mitigate gala costs since it repsented to city on several occasions that the gala need not to be rescheduled
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What was the end result (at the end of the news article)?

A

Surrey and PCL were trying to reach an out-of-court settlement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What could have been done better to prevent this fiasco?

A

your answer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly