MANUAL REVIEWER 7 Flashcards
What is the purpose of curing concrete?
A. To promote cement hydration
B. To promote specifications
C. To maximize aesthetics
D. No important purpose
A
What is the mixing time for concrete when mixed in a central mixing plant?
A. Less than 50s nor more than 90s
B. Less than 40s nor more than 90s
C. Less than 50s nor more than 80s
D. Less than 40s nor more than 80s
A
When transporting mixed concrete. the time elapsed from the time water added to the mix until the concrete is deposited in place shall not exceed?
A. 60 min by non-agitating trucks
B. 45 min by agitating trucks
C. 45 min by non-agitating trucks
D. 90 min by non-agitating trucks
C
When hauled by Agitating Trucks, time elapsed from the time water added to the mix until the concrete is deposited in place shall not exceed?
A. 60 min
B. 45 min
C. 75 min
D. 90 min
D
When hauled by non-agitating trucks, time elapsed from the time water added to the mix until the concrete is deposited in place shall not exceed?
A. 60 min
B. 45 min
C. 75 min
D. 90 min
B
What is the frequency of core sampling on a completed bituminous pavement?
A. To create bond between asphalt and aggregates
B. To make water and asphalt combine
C. To improve asphalt properties
D. To apply specification requirements
A
The workability of the bituminous mixture is very dependent on its ___
A. Compaction effort
B. Temperature of the mixture
C. Shape and size of aggregates
D. Asphalt content
B
What is the frequency of core sampling on a completed bituminous pavement?
A. Every 100m
B. Every 200m
C. Every 500m
D. Every 1,000m
B
What is the minimum time the contractor should submit the asphalt mix design prior to asphalting works?
A. 4 weeks
B. 3 weeks
C. 2 weeks
D. 5 days
B
Fibers used in the manufacture of geotextiles and the threads used in joining geotextiles and the threads used in joining geotextiles by sewing shall consist of long-chain synthetic polymers composed of at least ___ percent by mass polyolefins, polyesters, or polyamides
A. 50%
B. 75%
C. 85%
D. 90%
C
What is the corrugation produced by brooming the newly paved PCCP?
A. 2.0mm
B. 1.0mm
C. 1.5mm
D. 2.5mm
C
What is the sampling frequency for compressive strength of shotcrete?
A. 1 set per 25 cu.m but not less than 1 day
B. 1 set per 50 cu.m but not less than 1 day
C. 1 set per 75 cu.m but not less than 1 day
D. 1 set per 20 cu.m but not less than 1 day
A
What is the grading requirements of aggregate sub-base course, grading A as to passing sieve no. 200?
A. 0 - 12%
B. 2 - 14%
C. 0 - 25%
D. 11 - 35%
A
What is the grading requirements of aggregate base course, grading A as to passing sieve no. 200?
A. 0 - 12%
B. 2 - 14%
C. 0 - 25%
D. 11 - 35%
A
What is the grading requirements of crushed aggregate sub-base course, grading A as to passing sieve no. 200?
A. 0 - 12%
B. 2 - 14%
C. 0 - 25%
D. 11 - 35%
B
Conducting California Bearing Ratio (CBR) is forcing the plunger into the sample to a depth of ___
A. 2.0mm
B. 1.0mm
C. 1.5mm
D. 2.5mm
D
What is the no. of layer of AASHTO T-180 (Modified Proctor Test)?
A. 3
B. 4
C. 5
D. 6
C
What is the height of drop of AASHTO T-99 (Standard Proctor Test)?
A. 12”
B. 14”
C. 16”
D. 18”
A
What is the height of drop of AASHTO T-180 (Modified Proctor Test)?
A. 12”
B. 14”
C. 16”
D. 18”
D
What is the ideal time elapsed to finish slump test?
A. Within 2 minutes
B. Within 2.5 minutes
C. Within 3 minutes
D. Within 3.5 minutes
B
Acceptable of item 740 Structural Concrete Injection and Crack Report is when the epoxy bonding has penetrated at least ____ of the crack volume within the core sample
A. 90%
B. 95%
C. 85%
D. 80%
A
What is the minimum index, oxygen volume requirement for geofoam
A. 23%
B. 24%
C. 25%
D. 26%
B
What is the minimum asphalt content which the sample of Porous Asphalt Mixture can retain its shape under the condition after compaction
A. Deflection Point
B. Yield Point
C. Inflection Point
D. Tensile Point
C
This is the amount of air voids for Type-2 Gap Graded Porous Asphalt Mixture at 75 blows compaction
A. 4.0-5.5%
B. 2-14%
C. 15-25%
D. 18-25%
B