Managing Time and Resources Flashcards

1
Q

Define Time Scheduling

A

Time scheduling is a collection of techniques used to develop and present schedules that show when work will be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Can you draw a precedence diagram method? What does a node look like in these?

A

A node looks like so
ES | D | EF
— description —
LS | F | LF

Where
ES = Earliest Start
D = Duration
EF = Earliest Finish
LS = Latest Start
F = Float
LF = Latest Finish
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define the “critical path” for a schedule

A

Sequence of activities in a project from start to finish, the sum of whose durations determines the overall project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can there be multiple critical paths? Y/N

A

Yes, there may be multiple parallel paths with the maximal time duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define a Milestone

A

Significant events in a project associated with the completion of a key deliverable.
They are useful for planning a schedule or displaying progress as they focus on what is being delivered, not how

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define Resource Scheduling

A

Resource scheduling is a collection of techniques used to calculate the resources required to deliver the work and when they will be required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define procurement

A

Process by which products and services are acquired from an external provider for incorporation into the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following statements about Critical Path Analysis (CPA) is true?

a. The critical path is the path with the longest duration in a network
b. The critical path is the path with the least risk in a network
c. Tasks with float will never become critical
d. The network will remain constant throughout the project

A

A

Rationale: The critical path is the chain of dependant activities that take the longest to complete. This is not affected by the level of associated risk. The critical path can change as the paths on the network do not remain constant: they can be affected by risk and changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Total float is:
a. The cost of all activities within a network diagram
b. The time by which an activity can be delayed or extended without affecting the next
activity
c. Also known as free float
d. The time by which an activity can be delayed or extended without affecting the project
end date

A

D

Rationale: Total float is calculated using the forward and backward pass on the network diagram. It shows the amount of additional time, shared along that path, that is available before the end date is impacted. This is over and above what has been estimated to complete the activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
The time by which an activity can be delayed or extended without affecting the
next activity's start date is called:
a. Total Float
b. Float
c. Free Float
d. Slack
A

C

Rationale: Total float, float and slack synonymous and relate to the impact on the projects end date. Free Float specifically refers to the amount of time an activity could be delayed before it impacts the next activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In the diagram below which is the critical path

a. ABCD
b. AEFG
c. ACDG
d. ABDG

A

B

Rationale: AEFG. This is the longest chain of activities in the network.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The total float of activity F in the diagram below is:

a. 2
b. 3
c. 0
d. 16

A

C

Rationale: 0. it is on the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Rearranging the schedule so that the number of resources used does not
exceed a certain level at any point is called:
a. Resource smoothing
b. Resource levelling
c. Critical path analysis
d. Total float

A

B

Rationale: Resource levelling is also known as resource limited scheduling. The schedule is arranged to ensure predetermined resource levels are applied.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

People, materials, equipment, knowledge and time are examples of what?

a. Project resources
b. Success factors
c. Success criteria
d. Project requirements

A

A

Rationale: Resources are the different elements that are required to deliver a project: we need time, money and people for example.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

One of the key objectives of procurement is to:

a. Ensure the users are satisfied with the choice of supplier
b. Offload as much risk as possible
c. Get the cheapest price
d. Obtain a fair and reasonable price

A

D

Rationale: The best strategy for success is to ensure that all parties have a fair and
equitable deal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Procurement includes:

a. Definition of technical requirements
b. Development and maintenance of contract documentation
c. Material purchasing only
d. Milestone planning

A

B

Rationale: The procurement process is concerned with the activities required to obtain goods and services from outside the project. Whether internal, using a service level agreement, or external contracts are key.

17
Q

A contract is:

a. Always drawn up by solicitors
b. Always has to be written
c. Always a legally binding agreement between two or more parties
d. Always concluded with a red wax seal

A

C

Rationale: A contract only requires an offer and a consideration, together with acceptance that a contract is in place, in order to be legally binding.