Managing project cash flow Flashcards
1
Q
What is cash flow?
A
The transfer or flow of cash in and out of a project / company.
2
Q
What are 3 key issues with cash flow?
A
- Timing
- Time lags between having a payment certified and the money coming through.
- Credit arrangements
3
Q
Explain the S curve analysis.
A
- During the first 1/3 of the project, 1/4 of the money is spent.
- During the second 1/3 of the project, 1/2 the money is spent.
- During the final 1/3 of the project 1/4 of the money is spent.
4
Q
Why should cash flow be monitored?
A
- Client does it to inform themselves on payments for the contractor.
- Needed to show banks the situation when applying for loans or being monitored by the bank.
- Used to show stakeholders their liability should the contractor default.
5
Q
Why should cash flow be forecasted?
A
- Gives an early warning to insolvency. Work schedules could be altered to ensure money stays in the bank.
- Could inform the contractor on whether they are financially able to take on another project or not.
- Negotiations could be held to extend credit with client
- Suppliers often offer discounts for early payments - these can be forfeited if cash is needed elsewhere.
6
Q
What is capital lock up?
A
- Negative cashflow at the start of a project.
- Dealt with using loans (interest is gained) or company cash reserves (lost interest that would otherwise be gained on the cash is charged to the project).
7
Q
What are the influencing factors of capital lock up?
A
- The larger the margin, the less lock up there is.
- Margin at tender stage is usually large but it reduces due to retention, inflation of material costs.
- Claims don’t improve cash flow because they take a while to settle and for the cash to come through.
- Front / bad end loading (over measurement at the start / end also has the same effect).
- Delay in receiving payments from client.
- Delaying payment to suppliers/ subbies.
8
Q
What are the 12 Cash Flow Rows?
A
- cost
- cum cost
- cum cash out (cum cost delayed a month)
- cum profit
- cum value (cum cost + cum profit)
- cum value - retention
- cum certification (delayed a month)
- retention released
- cum retention released
- cum payments (cum cert + cum retention)
- cum cash flow (cum payments - cum cash out)