To deenergise low voltage electrical current supply to buildings by removing the service fuses from overhead power lines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Construction #1

A

Pole
- high density fibreglass laminate
- between 5-7 telescopic sections
- sections raise one at a time, from 1.5-10.5m
- sections are engaged with spring loaded pins that lock in place as it reaches its travel limit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Construction # 2

A

Head
- fixed at top of pole
- universal fitting for different adapters
- male threaded pig tail adapter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Safety (4)

A
  • PPE gloves and helmet
  • don’t reach HV lines
  • falling parts / porcelain / fuses
  • don’t use it if it’s wet
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Operation 1. prepare link stick

A
  • PPE
  • identify fuse
  • ensure pigtail secure
  • check service dates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Operation 2. Extend link stick

A
  • hold in front
  • extend up, 1 section at a time, engaging locking pins
  • stop 1 metre below fuse
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Operation 3 Connect and extract fuse

A
  • Engage the pigtail head with the base of fuse
  • rotate clockwise
  • pull 300mm down
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Operation 4. Rehouse link stick

A
  • engage locking pins 1 at a time
  • remove fuse from pigtsil
  • place at base of pole
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Testing

A

Visual , into service, monthly , after use
- extend fully
- pole and threads are in good condition
- check test label in date

+ 6 monthly electrical authority test conducted