Lifecycle Flashcards
Name the 5 steps in sys lifecyle
concept>sys dev>sys prod>util/support (upgrades)>Retirement
Name 3 factors that make a system development major
complexity, importance of user need, timescale, many interrelated tasks, many disciplines, multiple orgs, specific schedule/budget
What 2x things start a lifecycle
Needs pull or technology push
What are the steps broken down into?
Technical processes
What occurs at significant points in the lifecycle
Decision gates
What are the 4 technical processes in Concept?
Biz analysis > stakeholder needs / reqs def > system requirements def, Architecture def.
What are the 4 TPs in Sys Dev?
Design Def, implementation, integration, verification
what are the 2 TPs in sys production?
Validation, Transition
What are the 2 TPs in Util/support?
Operation, maintenance
What is the 1 TP in retirement?
Disposal
What is the TP that applies to all steps?
System Analysis
Draw the sys eng V
need>req>design>prod>validation>delivery