Level 3 - Programming and Planning Flashcards
N 1. What is PERT? (Method of programme creation)
Programme, Evaluation, and Review Technique
Three estimates for a project programme:
- The most Optimistic (Shortest)
- The most pessimistic (Longest)
- The most likely (an average of the two)
N 2. What is a Project Programme?
A sequence in which tasks must be carried out to ensure a project can be completed on time.
N 3. What can be identified from the project programme?
- Start Date.
- Completion Date.
- List of activities to complete the project
- The start date for each activity.
- The completion date of each activity.
From evaluation of the programme you can identify:
- The amount of ‘Float’ each activity has.
- The Critical Path.
- Tasks which can only be carried out sequentially.
- Tasks which can be carried out simultaneously.
N 4. What should a programme help you do?
- Plan Activities.
- Monitor progress.
- Manage Resources.
N 5. What types of Programme are there?
- Clients Overall Programme (Development Programme)
- Design Programme (Pre-construction programme)
- Information Release Schedule (IRS)
- Contractors Master Programme (Construction Programme)
N 6. What goes into the Clients Overall Programme?
- Everything, from the appointment of the consultant, through to the completion of the project.
- This will include work outside the scope of the Main Contractor.
N 7. What goes into the design Programme?
It describes the sequence of design tasks, i.e. from the process of design from inception through the Technical Design.
N 8. What goes into an information release schedule?
The dates by which information needs to be released by the design team, to avoid any delays.
N 9. What goes into the Contractors Master Programme?
The schedule and sequence of construction activities.
N 10. Can you employ a consultant to produce a programme?
Yes, on large projects they can prepare the outline programme.
N 11. What should you consider when preparing a programme?
- Items with a long lead-in
- Pre-contract works
- Pre-fabrication elements
- Phasing and Sectional Completion
- CDM Planning Period
- Works outside of the main contract
- Relationships with other projects
N 12. What is the CDM planning period?
An amount of time given to the Contractor, allowing the Contractor to assess Health and Safety issues and plan their works before construction commences.
N 13. How long is the CDM planning period?
Not specified, it should be proportional to the size and complexity of the project and the risk.
N 14. What is a Flow diagram?
A Graphical representation of a process of steps/sequences is required to achieve an end goal.
N 15. What is the benefit of using a Flow Diagram?
It helps the team to understand the different processes and relationships between activities.
N 16. What is an Activity Schedule?
A list of activities which outlines the works required to complete a project/package etc.