Level 3 - Programming and Planning Flashcards

1
Q

N 1. What is PERT? (Method of programme creation)

A

Programme, Evaluation, and Review Technique

Three estimates for a project programme:

  • The most Optimistic (Shortest)
  • The most pessimistic (Longest)
  • The most likely (an average of the two)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

N 2. What is a Project Programme?

A

A sequence in which tasks must be carried out to ensure a project can be completed on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

N 3. What can be identified from the project programme?

A
  • Start Date.
  • Completion Date.
  • List of activities to complete the project
  • The start date for each activity.
  • The completion date of each activity.

From evaluation of the programme you can identify:

  • The amount of ‘Float’ each activity has.
  • The Critical Path.
  • Tasks which can only be carried out sequentially.
  • Tasks which can be carried out simultaneously.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

N 4. What should a programme help you do?

A
  • Plan Activities.
  • Monitor progress.
  • Manage Resources.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

N 5. What types of Programme are there?

A
  • Clients Overall Programme (Development Programme)
  • Design Programme (Pre-construction programme)
  • Information Release Schedule (IRS)
  • Contractors Master Programme (Construction Programme)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

N 6. What goes into the Clients Overall Programme?

A
  • Everything, from the appointment of the consultant, through to the completion of the project.
  • This will include work outside the scope of the Main Contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

N 7. What goes into the design Programme?

A

It describes the sequence of design tasks, i.e. from the process of design from inception through the Technical Design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

N 8. What goes into an information release schedule?

A

The dates by which information needs to be released by the design team, to avoid any delays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

N 9. What goes into the Contractors Master Programme?

A

The schedule and sequence of construction activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

N 10. Can you employ a consultant to produce a programme?

A

Yes, on large projects they can prepare the outline programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

N 11. What should you consider when preparing a programme?

A
  • Items with a long lead-in
  • Pre-contract works
  • Pre-fabrication elements
  • Phasing and Sectional Completion
  • CDM Planning Period
  • Works outside of the main contract
  • Relationships with other projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

N 12. What is the CDM planning period?

A

An amount of time given to the Contractor, allowing the Contractor to assess Health and Safety issues and plan their works before construction commences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

N 13. How long is the CDM planning period?

A

Not specified, it should be proportional to the size and complexity of the project and the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

N 14. What is a Flow diagram?

A

A Graphical representation of a process of steps/sequences is required to achieve an end goal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

N 15. What is the benefit of using a Flow Diagram?

A

It helps the team to understand the different processes and relationships between activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

N 16. What is an Activity Schedule?

A

A list of activities which outlines the works required to complete a project/package etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

N 17. When would you use an Activity Schedule?

A

A simple project with few activities.

18
Q

N 18. What type of contract uses an Activity Schedule?

A

New Engineering Contracts, Engineering and Construction Contract Options A and C.

19
Q

N 19. How is an activity schedule represented graphically on a programme?

A
  • Typically using a Gantt chart.

- Each activity gets a bar.

20
Q

N 20. What should a PM do when receiving a contractors programme?

A
  • Check that it is not front-loaded.

- Check the activity timescales are reasonable and realistic

21
Q

N 21. What is a Gantt chart?

A

A way of displaying a programme, through a combination of bars, each relating to an activity and having a specified duration.

22
Q

N 22. What does a Gantt chart programme show?

A

The:

  • Start Date.
  • Duration.
  • Completion date.
  • Of both activities and the project as a whole.
23
Q

N 23. What are the advantages of a Gantt chart?

A
  • It is suitable for construction as it offers a high level of detail
  • It shows the timescale
  • Easy to read and to understand
  • Not detailed enough for cost planning and estimates
24
Q

N 24. What is the critical path?

A
  • The shortest sequence in which a project can be completed.

- Also referred to as the bottleneck of the project.

25
Q

N 25. What is Critical Path Analysis?

A
  • A way of analysing the programme, to see if the critical path duration can be shortened; or
  • Activities altered in sequence.
26
Q

N 26. What do you aim to identify when undertaking a Critical Path Analysis?

A
  • Any items with slack that can be used to improve the programme’s critical path.
  • Identify risky items within the programme, i.e. items on the critical path that also have significantly long lead-in-times on materials etc.
27
Q

N 27. What is a Key Milestone?

A

Specific points along the programme are used to measure progress.

28
Q

N 28. What is the benefit of having Key Milestones?

A

Helps the project keep site of:

  • The key dates.
  • The key deadlines.
29
Q

N 29. What is Float?

A

• The amount of time an activity can be delayed, before it impacts on the completion of the works.

30
Q

N 30. Can tasks on the Critical Path have float?

A

• No, if they did you would identify them through Critical Path Analysis and amend the programme.

31
Q

N 31. What are the types of Float?

A
  • Total Float.

* Free Float.

32
Q

N 32. What is Total Float?

A

• The amount of time an activity can be delayed, before it impacts on the overall completion date.

33
Q

N 33. What is Free Float?

A

• The amount of time an activity can be delayed, before it impacts on the start date of another activity.

34
Q

N 34. What valuation method gives the most accurate cash flow forecast in terms of time and surety of value?

A

• Stage Payments.

35
Q

N 35. What are Stage Payments?

A

• Payment which are made in instalments, but do not necessarily reflect the value of work completed.

36
Q

N 37. How can you monitor progress on site?

A
  • Compare progress to programme.
  • Compare Valuations against cash flow forecast.
  • Use the ‘S’ curve principles.
  • Milestone Chart.
37
Q

N 47. What are the Three types of delay?

A
  • Contract Led.
  • Client Led.
  • Neutral.
38
Q

N 48. What is Concurrent delay?

A

• Where multiple delays for numerous causes overlap. The difficulty is in determining the root cause.

39
Q

N 49. What types of concurrent delay are there?

A
  • Parallel Fault.
  • Overlapping Events.
  • Truly Concurrent Events.
40
Q

N 50. How do you assess Concurrent Delay?

A

• You must determine the root cause, true concurrent delay is actually very rare.
• Once you determine the root cause, you should really discard any other delays.
• Use the Malmaison approach.
o This is where if it is considered that one of the delays is the clients risks, then the contractor should be entitled to a Extension of Time without loss and expense.
o It will have to claim for loss and expense separately.