Level 3 - Dev Row PQQ & Tendering Flashcards

1
Q

On Devonshire Row, how did you go about recommending contractors to invite to tender?

A

Prequalifying a long list of Contractors

I identified a short list to ITT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

As part of the PQQ what did you look for in the potential tenders?

A

Capacity - Review contractors staff resource levels and current / forecast workload and projects

Experience - checked for relevant project experience on similar projects

Finances - checked that they was capable to carry out a project of this size by reviewing turn over etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

You advised on an appropriate tender period? how did you assess this?

A

Following the guidance in the JCT Tendering practice note 2017 it was decided that a 4 week period was suitable given the nature and complexity of the works as well as the overall programme.

Also factored in that the design had been developed to stage 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How did you advise on an appropriate nr of tenderers to ITT?

A

Following the guidance in the JCT Tendering practice note 2017

4 were invited to tender

(3 - 6 Nr tenderers generally)
(Max 4 Nr D&B project)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you deal with any Tenders that weren’t compliant with the ER’s?

A

No compliant tenders shouldnt be accepted and I would state this in the Instructions to tenderers

I would discuss with the tenderer if they submitted a non compliant tender and give them the oppotunity to amend of withdraw

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How did you ensure tenders where compare on a like for like basis? How would you normalize a tender?

A

Anomalies identified and normalize using:

Average rate
PTE rate
Highest rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you talk through the PQQ process for Devonshire Row?

A
  • A long list of Contractors was collated based on recommended contractors (via colleagues and the design team)
  • Contractors were contacted and interested contractors were sent a PQQ
  • When PQQs were returned by the contractors
  • PQQs were ranked based on a scoring matrix
  • The top 4 contractors were invited to tender
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What Information was included in the PQQ?

A
Section 1 – Introduction & Overview 
o	Project Details 
o	Client / Project team details 
o	Tender Dates 
o	PQQ Scoring Matrix
Section 2 – PQQ (for contractors to fill out)
o	Contractors details (registration number, VAT, Parent companies)
o	Financial information (3 years)
	Turnover
	Pre tax profit 
	Cash & Credit Position
o	Insurances 
	Employers Liability 
	Public Liability 
	Contractors All Risk 
	Professional Indemnity 
o	Health & Safety Records 
o	Relevant project experience 
o	Proposed Team (Cvs)
o	Current Workload 
	Projects Secured 
	Projects bidding 
	Projects Monitoring / likely to bid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Did you ask the contractors to comment on the current market during the PQQ?

A

There was a section for contractors to identify potential supply chain risks associated with Brexit
There was also a section asking how they managed covid and if there were experiencing any issues with the supply chain due to covid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you ensure the tender process was fair?

A

Made them sign a declaration of non-collusion

Carried out tender normalisation and ensured the tenders were base on the same scope

Circulated tender queries to all tenderers

Prepared a tender report which documented and explained my advice given to the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was your advice in recommending a contractor to the client based on?

A
  • Design Team input / recommendation
  • Cost / Value (Most commercially competitive)
  • Shortest Programme
  • Performance during the tender period
  • Most pro-active during the tender period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What was included in your tender report?

A
Executive Summary 
Tender information received 
Post Tender Adjustments 
Cost options / Value engineering 
Conclusions and recommendation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly