Level 3 Flashcards
Why did you use a IC for HWS?
As the works had a named subcontractor and it was important that relevent events were defined.
What is a Nominated Subcontractor
Nominated subcontractors are stated within a contract are the principal contractor has no option but to use them. It is usual that the Employer will take responsibility for nominated subcontractors and a collateral warranty will be put into place.
What is a Named Subcontractor?
Named subcontractors are domestic, which means the principal contractor has freedom of choice to employ which subcontractor they wish and the terms on which they are employed.
Do JCT contracts no longer have provisions for nominated sub contractors?
SBC form no longer makes provision for nomination of subcontractors or suppliers, the Intermediate forms retain a method for appointing a ‘Named Sub-Contractor’. Responsibility for the named subcontractor remains with the contractor. The Minor Works forms do not provide for naming specialists or nomination of subcontractors.
What is a critical path?
A sequence of stages determining the minimum time needed from start to finish of a project.
What is Critical Path Analysis?
The primary purpose of critical path analysis is to show which activities on a programme of works are critical to completion and which are non-critical.
What is a critical path item?
The items on the critical path are important to achieve completion. Any delay in the critical path delays the project finish date.
What is the critical path method?
Calculates the minimum time needed to complete a construction project alongside the possible start and end times for the different activities.
What is an extension of time?
An additional period added on to the duration of the works.
What is an extension of time procedure needed in a construction contract?
1) Contractor must give notice to the CA.
2) Inform about the relevant event and the time predicted to be extended.
3) CA review and provide cert.
What are relevant events?
Events that are listed within the contract that allow the contractor to claim an extension of time. Reasons that are not the contractors fault.
What’s the difference between a relevant event and a relevant matter?
Relevant events allow an extension of time and is beyond the contractors control,
Relevant matter is the employers fault= will allow a claim for loss and expense
Event : justifies additional time
Matter : Justifies additional payment
List some relevant events (13)
Variations. Any impediment by the employer Force majure Exceptionally adverse weather conditions works by statutory undertakers
List relevant matter (11)
1) Failure to give the contractor possession of the site.
2) Delays in providing instructions.
3) Discrepancies in the contract documents.
4) Disruption caused by works being carried out by the client.
5) Instructions relating to variations and expenditure of provisional sums
6) Opening Up Works
What can a contractor claim with regards to the above.
Either:
Extension of Time
Loss & Expense
Dependent on relevant event/matter.