Level 2 Flashcards
Describe the building (Langtry House)
- 2 Storey former wardens maisonette
* 1950’s building, cavity walls, plain tiled hipped roof
Describe the works (Langtry House) .
- Conversion to 2 flats (Ground Floor/First Floor)
Removal of staircase, two new flats with separate access and installation of new decking area.
Why were there supply issues with the laminate flooring?
The supplier stated that the laminate flooring would take longer than anticipated which would have jeopardised the project completion.
How did you deal with the design change?
Requested that the Contractor offer 3 similar products with an appropriate lead in time for discussion with the Client.
How long was the rectification period?
6 months
What Works insurance Option was selected (Langtry)
C
What was the Contract Sum
93815
What was included in the tender pack?
Invitiation to Tender Appendices such as Asbestos/drawings Designer Risk Assessment Prelims Specification (Material and Workmanship Clauses) Schedule of Works M&E Specification Pre-Construction Information
Was the project notifiable under CDM Regulations?
No it did not meet the criteria.
Name are some certificates that are issued under JCT Contracts?
Interim payment certificates
Practical completion certificate
Penultimate payment certificate
Certificate of making good defects
Final Certificate.
What about if there is a delay to the project? What certificates are issued under JCT then?
Certificate of non completion - Fault of Contractor
Extension of time certificate. - Fault of Client or his Team
What is a Contractors Variation Order?
Alteration to the scope of works in the contract.
Addition/Substitution/Omission
What are interim Payment Certificates?
Allow the client to make payments to the contractor before the work is completed.
What figures would you expect to be detailed on a payment certificate?
- Contract sum
- Gross valuation
- Less the retention
- Less the total amount previously certified
- Net amount for payment (in figures and words).
Did you or someone else in the firm sign the interim certificate?
All certificates were drafted by me, checked by a senior surveyor and then checked and signed by a by a Director.
Did you have a retention?
Yes 5% with 2.5% released at practical completion.
What insurance would a contractor require before commencing works on site?
"• Joint Names Policy for All Risks • Joint Names Policy for Specified Perils • Employers Liability • Public Liability • Professional Indemnity "
How many insurance options are there in the JCT?
3 - Options A-C
What is Option A insurance in the JCT contracts?
The CONTRACTOR takes out a joint names policy for all risks insurance with cover for the full reinstatement value.
What is Option B insurance in the JCT contracts?
The EMPLOYER takes out a joint names policy for all risks insurance with cover for the full reinstatement value.
What is Option C insurance in the JCT contracts?
The EMPLOYER takes out and maintains insurance in respect of the existing structures and their contents and a joint names policy for all risks insurance with cover for the full reinstatement value.
Public Liability Insurance?
Loss or damage resulting from a claim for damages by a third party arising from negligence on your part
Professional Indemnity Insurance ?
Cover for claims brought against the policyholder due to their professional negligence. This is mainly in relation to contractor design.
Employer’s Liability Insurance?
Imposed on an employer to pay damages to an employee injured by the employer’s negligence
Which options would you use for the refurbishment of an existing structure?
C- chosen for alterations or extensions to existing buildings.
What is a potential issue with Option C in respect to the Employer/Contractor?
Employer to take out/maintain a ‘joint names’ insurance policy in respect of the existing structures and contents. This includes the employer and contractor as composite insured = insurers have no right of recourse against either party as there is a waiver of the insurer’s subrogation rights.