Level 1 Flashcards
Is there any guidance you can refer to when undertaking Contract Administrative service
RICS Guidance note: Contract Administration
What edition is the CA Guidance Note?
1st Edition- although aware this has been withdrawn (out of date).
What are the key tasks of a CA
- Inviting and processing tenders.
- Preparing contract documents for execution.
- Chairing construction progress meetings &*Preparing and issuing construction progress reports (Meeting Minutes)
- Issuing instructions such as variations, or relating to prime cost sums or making good defects.
- Issuing certificates of practical completion, interim certificates, certificate of making good
Defects
Defects and Final certificate
What JCT Contracts are you aware of
Minor Works Building Contract Intermediate Building Contract Standard Building Contract Design & Build Management contract
When would you use JCT MW
Works simple in nature Simple (No Bills of Quantity)
No need for provisions set out in different contract types
When would you use JCT IM
More complex works (complex and detailed procedures)
Sectional completion is needed
Named sub contractors.
Not suitable for D&B Contracts.
What can be used to assist with selecting contracts.
*JCT Decision Tree.
What are the difference between Minor Works and Intermediate contracts?
- More detailed procedures
- Relevant Events defined
- Early possession
- Sectional completion
- When named sub-contractors are required
- Collateral warranties for Sub contractor with design responsibility
- Bill of quantities
- Advance payment
Who is responsible for valuations under the intermediate contract used?
- QS in the case of IC standard terms
* Can be undertaken by the CA
Other types of Contract
New Engineering Contract
Recommended in the Latham Report (constructing the team)
Intended/designed to accommodate both engineering and construction & promote cooperative working.
The NEC contracts are used for:
- Stimulate good management.
- Used internationally
- Easy to understand
Interlocking
Produce an interlocking suite of contracts written
Clear and Simple
Be clear and simple, written in plain English, in the present tense and without legal terminology.
Variety
Be useable in a wide variety of situations from minor works to major projects.
Options
There are a number of options from A-G such as Priced Contract with activities schedule or Target Contract with Bill of Quantities
Issues
Key issues surround payments, compensation events, Dispute resolution.
What’s the difference between NEC and JCT?
JCT - No programme
NEC - Programme is the heart of the contract
JCT - lump sum contract with Provisional Sums
NEC - Based on target for D and C
JCT - 4 weekly interim payments
NEC - Can be set period related to programme
What is FIDIC?
International Federation of Consulting Engineers
How did you decide whether PC had been achieved?/ When can you certify practical completion?
1) works substantially completed
2) free of patent defects (other than those that are minor or trivial).
3) Complete health and safety file has been issued in draft.
4) The client ability to take possession and make beneficial use of the building.
What are the consequences of issuing the PC certificate?
1) Rectification period begins,
2) Retention reduces
3) Insurance (passes back to the client).
4) Final account is then prepared.
What are the timescales for final account?
- contractor has 6 months after PC to prepare
* 3 months after that date CA to issue final account