Level 1 Flashcards

1
Q

Is there any guidance you can refer to when undertaking Contract Administrative service

A

RICS Guidance note: Contract Administration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What edition is the CA Guidance Note?

A

1st Edition- although aware this has been withdrawn (out of date).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key tasks of a CA

A
  • Inviting and processing tenders.
  • Preparing contract documents for execution.
  • Chairing construction progress meetings &*Preparing and issuing construction progress reports (Meeting Minutes)
  • Issuing instructions such as variations, or relating to prime cost sums or making good defects.
  • Issuing certificates of practical completion, interim certificates, certificate of making good

Defects
Defects and Final certificate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What JCT Contracts are you aware of

A
Minor Works Building Contract
Intermediate Building Contract
Standard Building Contract
Design & Build
Management contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When would you use JCT MW

A

Works simple in nature Simple (No Bills of Quantity)

No need for provisions set out in different contract types

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When would you use JCT IM

A

More complex works (complex and detailed procedures)

Sectional completion is needed

Named sub contractors.

Not suitable for D&B Contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What can be used to assist with selecting contracts.

A

*JCT Decision Tree.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the difference between Minor Works and Intermediate contracts?

A
  • More detailed procedures
  • Relevant Events defined
  • Early possession
  • Sectional completion
  • When named sub-contractors are required
  • Collateral warranties for Sub contractor with design responsibility
  • Bill of quantities
  • Advance payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who is responsible for valuations under the intermediate contract used?

A
  • QS in the case of IC standard terms

* Can be undertaken by the CA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Other types of Contract

A

New Engineering Contract

Recommended in the Latham Report (constructing the team)

Intended/designed to accommodate both engineering and construction & promote cooperative working.

The NEC contracts are used for:

  • Stimulate good management.
  • Used internationally
  • Easy to understand

Interlocking
 Produce an interlocking suite of contracts written

Clear and Simple
 Be clear and simple, written in plain English, in the present tense and without legal terminology.

Variety
 Be useable in a wide variety of situations from minor works to major projects.

Options
There are a number of options from A-G such as Priced Contract with activities schedule or Target Contract with Bill of Quantities

Issues
Key issues surround payments, compensation events, Dispute resolution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What’s the difference between NEC and JCT?

A

JCT - No programme
NEC - Programme is the heart of the contract

JCT - lump sum contract with Provisional Sums
NEC - Based on target for D and C

JCT - 4 weekly interim payments
NEC - Can be set period related to programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is FIDIC?

A

International Federation of Consulting Engineers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How did you decide whether PC had been achieved?/ When can you certify practical completion?

A

1) works substantially completed
2) free of patent defects (other than those that are minor or trivial).
3) Complete health and safety file has been issued in draft.
4) The client ability to take possession and make beneficial use of the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the consequences of issuing the PC certificate?

A

1) Rectification period begins,
2) Retention reduces
3) Insurance (passes back to the client).
4) Final account is then prepared.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the timescales for final account?

A
  • contractor has 6 months after PC to prepare

* 3 months after that date CA to issue final account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is required to have a contract?

A
  • Offer
  • Acceptance
  • Consideration
  • Time
  • capacity
17
Q

What are the parts of the contract?

A

*Agreement
The ‘articles of agreement’ setting out the core obligations/details of the parties involved

*Recitals
Recitals contextualise the agreement, giving factual explanations for the basis of the contract. recitals describe what is required and the events that have taken place.

*Articles
Set out what is agreed between the parties.

*Contract Particulars
Sets out the aspects of the contract that are particular to the project to which the contract relates.

*Attestation
Act of signing &/or witnessing a legal document (Contract agreement / Execution) to formally execute the document

*Execution
Under hand - disputes must proceed to court within 6 years

As a deed - disputes must proceed to court within 12 years

18
Q

What makes up a building contract

A

a. The building contract - This is a legal document, usually in standard form. It sets out the roles, rights and responsibilities of the employer and the contractor.

b. The specification:
i. Prelims - Preliminaries are activities or costs that are not necessarily linked to the building work. They are costs associated with administration, setting up and Statutory Authorities regulations and fees.
ii. Preambles – Quality of materials and workmanship.
iii. Works - The technical requirement to complete, execute and/or perform every little task or material being incorporated in the construction project. It specifies common standards, deviations accepted, materials accepted and the required testing for all materials. Specific referencing to construction standards and codes.
iv. The drawings/plans – Drawings detailing the works to be undertaken referring to and to be read in conjunction with the specification to gain a full understanding of the works.

c. Priced schedule of work/bill of quants - Breakdown of all items being incorporated in the construction project. This is usually the base of the application for payment.
d. Pre Construction Information Pack – Details of all the health and safety, security, welfare, access considerations that need to be taken into account. The response to which should be the contractors construction phase health and safety plan.

19
Q

Difference between Preambles and prelims?

A

Prelims detail non construction related works that the contractor needs to cost

Preambles detail the quality requirements for materials and workmanship.

20
Q

What should you include in the premlins and M&W

A
  • Prelims - Does not form part of the main works package - Welfare, access, emergency services, statutory requirements, party wall.
  • M&W - provides details of the material and workmanship requirements for the project to ensure a high standard of workmanship.
21
Q

what happens when the rectification period ends?

A

1) Joint snagging inspection should be undertaken by the CA and Contractor. The contractor should rectify any defects
2) Second inspection should be undertaken to check.
3) Certificate of making good defects and a final payment certificate should be issued for the remaining retention.
4) The contractor will then issue this to the client with his final invoice.

22
Q

Can you give me some examples of how a construction contract could be terminated.

A

Actions by the contractor - Solvency, Corruption.
Actions by the employer - Solvency, Corruption.

Breach of contract.

Contractor - abandoning site.
Employer - failure to make payment etc

Both - force majure, specified peril.

23
Q

How should H&S issues be report on site.

A

RIDDOR - Reporting of Injuries, disease and dangerous occurrences regs.

24
Q

What is the base date?

A

Reference date
The conditions under which the tender was prepared are considered to have been known by the contractor (so are properly reflected in their price).

25
Q

How do you calculate if a employer is a Contractor for the purpose of CIS (Construction Industry Scheme)

A

1) You pay subcontractors for construction work
2) Your business doesn’t do construction work but you spend an average of more than £1 million a year on construction in any 3-year period

26
Q

what is the difference between 2011 and 2016 update

A

1) The Payment Terms (Common Valuation Date)
2) CDM 2015 regulations (are now fully integrated).
3) Insurance Provisions - JCT 2016 incorporates 3 options.

27
Q

How do you value materials that are held off site?

A

Vesting certificate may be required from the contractor (or sub-contractors or suppliers), certifying that ownership of the goods, plant or materials listed in a schedule will transfer from one party to the other upon payment and confirming that they will be will be properly identified, separately stored, insured and are free from encumbrances (such as retention of title).

Advance payment bond may be more appropriate.