What are some of the risks with market testing?

A
  • Budget cost advice only so suppliers cannot be held to the rates provided
  • May be overly competitive to get their foot in the door
  • Based on limited design / time frame
  • They may not fully understand the scope or the project abnormal
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What Pricing Documents are you aware of?

A

Schedule of works – doesn’t have quantities (contractors responsible for quantifying)

Schedule of rates – list of rates the contractor will use for pricing cost reimbursable dayworks

CSA – D&B contracts split elementally

BoQ – Used in traditional works generally prepared by client QS with a detailed break down all items of works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What risk allowances were included in your PTE?

A

Design Development
Construction
Included as a line item at 10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a PTE?

A

QS last estimate using design info that the contractors will use to give the client an indication of what the cost of the works will be

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What bespoke items did you market test?

A

Feature ‘rock effect’