Level 1 - Quantifying Construction Elements Flashcards
How are Construction elements broken down in NRM 1?
0 Facilitating Works 1 Substructure 2 Superstructure 3 Internal Finishes 4 FF&E 5 Services 6 Prefabricated buildings and building units 7 Works to existing buildings 8 External Works 9 Main Contractor Preliminaries 10 Main Contractor OH&P 11 Project / Design team Fees 12 Other Development / Project Costs 13 Risks 14 Inflation
How would you measure Shallow foundations using NRM1?
Excavation – (m³) Extra for disposal of contaminated materials
Strip – (m) stating details and depth
Pad – (nr) stating details, reinforcement etc
How would you measure piled foundations using NRM1?
- Piling mat – (m²)
- Plant details – (item)
- Moving pile rig into position – (nr)
- Piles – (nr) stating diameter and depth
- Pile casings – (nr)
- Disposal of excavated materials (m³)
- Extra for breaking through obstructions – (nr/m³)
- Cutting off tops of piles – (nr)
- Pile tests – (item)
- Pile caps (nr)
How would you measure Facades / External Walls using NRM 1?
Quantifying the design from the architect
• External walls – (m²)
• Measure Solid and Glazing separately (m²)
• E/O Plinths – (m)
• E/O forming windows –(nr)
How would you measure Structural Frames using NRM1?
Steel Beams & Columns – (t) E/O allowance for Intumescent paint
Concrete – (m) detailing nr of columns / beams, size (mm), concrete grade, reinforcement rate and type of formwork
Timber – (m²) incl details of the frame system and all components