Legislative Context Flashcards

(15 cards)

1
Q

What other frameworks are available for managing a contract?

A

NZS 3902 - Residential Scale Projects
NZS 3915 - Similar to 3910. No engineer to contract. Client administers the contract.
NZS 3916 - Design and Construct

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Outline the roles of each party under a NZS 3910 contract.

A
  • It’s the industry standard conditions of contract for civil engineering works.
  • Principle is the client. They are the source of funds. appoints engineer to oversee the contract on their behalf.
  • Engineer to contract:
    • Expert advisor + representative of principle.
    • provides direction to contractor, certifies payments and acts independently and impartially under the contract.
  • Engineers representative can undertake most administrative duties expect for certifying payments, issuing variations or make formal decisions unless authorised.
  • MSQA - Management Surveillance and Quality Assurance.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How would you use a schedule of quantities throughout the lifespan of a project?

A
  • It helps to generate a budget and allows provisional sums and contingencies to be measured.
  • SoQ is a link between design and implementation. Sets out contractors understanding of project.
  • SoQ provides a preliminary estimate of project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you think the Treaty of Waitangi is relevant to Landscape Architecture?

A
  • The values of the treaty are aligned to NZILA charter and statement of philosophy.
  • Guides our thinking re: achieving a harmonious relationship between land and culture.
  • Empowers communities to have guardianship over the land.
  • Collaborate with Mana Whenua in a meaningful way.
  • RMA references Treaty.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is a Landscape Architect responsible for Health & Safety on site?

A

Always be vigilant on site and report any concerns to site manager. Site managers responsibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Tell us about a time you’ve engaged with iwi?

A

Viaduct Masterplan - Mei Hill + Graham Tipene. Overarching cultural narrative.
Graham is an example of a relaxed Mana Whenua engagement. He set us off on a path and we checked in at various point in time for feedback/direction. He was trusting of us to take the lead on landing that narrative in a meaningful way.

CMUA - Matapopere. Debbie Tikau.
This project is an example of a more closely knit working relationship with Mana Whenua. Nothing about us without us.
Navigational / celestial sculptural markers. Marrying functional requirements of the stadium in terms of lighting/way finding with a story presented by Matapopere.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Tell me about some of the challenges you faced during the overseeing of the project?

A

Te Mata Topaki_

  • Scope expansion during developed design. Integrate pontoon access. Poor communication from client.

Long Bay Village_

  • Tree placement
  • RLs to PC units
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What should be contained in a set of construction / contract documents in addition to drawings?

A
  • Illustrative drawings
  • Qualitative specification
  • Quantitative schedules
  • Tender documents
  • Design Material (illustrative)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you describe the process of taking a project from tender stage to completion under 3910?

A

..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can you describe the contract process between practical completion and close out?

A
  • Defects / liability
  • Maintenance
  • Final claim
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you go about determining costs for this project?

A

Te Mata Topaki_

  • Outsourced to QS
  • Assisted QS in estimates via 3d visuals/outline specification.

Long Bay_

  • Outsourced to QS.
  • Cost reviews at 100% Developed Design, 50% Detailed Design and 100% Detailed Design
  • Assisted QS with queries
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you describe your role in relation to the contract?

A

Te Mata Topaki_

  • MSQA role
  • design and technical advice to client/principle

Long Bay Village_

  • Engineers representative?

MHP_

  • Contract type? Design Build.
  • ## Sub consultant to Lead WAM.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What’s the purpose of a specification?

A
  • ## Provide details re: materials and workmanship required to achieve the design.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is practical completion?

A

Practical Completion means the time when the Contract Works are complete save for Minor Outstanding Works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Can you describe taking a project from tender stage through to completion under NZS 3910?

A
  1. Tender goes out (open/select/direct). Mahutonga deck was a selection of contractors based on consultant team’s past experiences/relationships.
  2. Tender queries received
  3. Tenders received and evaluated (cost/track record/experience/methodologies)
  4. Tender awarded (often with feedback).
  5. Contract finalised (awarded). Including contract documents
  6. Mobilised prestart
  7. Works commence
  8. Site visits/monthly payments.
  9. Practical completion
  10. Defects inspection
  11. PCC (Practical Completion Cert) issued.
  12. Site opens back to client. Payments released.
  13. Defects liability period commences.
  14. Final completion (defects remedied, full handover/release of payments).