Legal and Regulatory Compliance Flashcards

Level 1 - 3

1
Q

What are the main sections of the Party Wall etc Act 1996 ?

A

Section 1 applies where it is proposed to erect a new wall at a boundary that is not already built on.
Section 2 concerns existing party structures, which include party walls, floors and partitions (that separate buildings or parts of buildings), party fence walls (essentially a boundary wall between lands in separate ownership which is built astride a boundary) and, in some instances, a neighbour’s independent property.
Section 6 can apply to excavations up to 6 m away from a building or structure on neighbouring land, subject to depth criteria which the Act sets out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the three types of Notice under the Party Wall etc Act 1996

A

Section 1: Line of Junction Notice
Section 3 (for S2 works): Party Structure Notice
Section 6: Notice of Adjacent Excavation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is supersession ?

A

Supersession is an undefined legal concept which effectively means that a landlord should not claim for the remedy of a tenant’s breach, because the landlord is proposing to do something else to the building which would supersede the need for the tenant to remedy their breach.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Section 1 Notice / Line of Junction Notice ?

A

If you are planning to build a new wall either as a Party Wall or a Party fence wall (astride a boundary) subject to your neighbour’s consent, or up to the line of junction and wholly on your own land, a Section 1 Notice must be served.

If a proposed wall needs foundations to a lower depth than your neighbours foundations, a Section 6 notice could also be required.

One month notice must be given before the works commence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a Section 3 Notice / Party Structure Notice?

A

If you are planning to cut into a Party Wall to insert flashings or a damp proof course, cut away chimney breasts or projections, raise, rebuild repair, underpin, expose the Party Wall to the weather
or enclose upon a wall on or at the line of junction turning it into a Party Wall, in such cases a Section 3 Notice must be served.

Two months notice must be given for a section 3 Notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Section 6 Notice / Notice of Adjacent Excavation ?

A

If you are planning to excavate within 3m of neighbour’s foundations to a lower depth, or within 6m to a lower depth than a line struck at 45 degrees down from the underside of the neighbour’s foundations, then a section 6 notice must be served.

One month notice must be given before work commences and in addition, plans and sections of the proposed works must be provided with the notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Under planning what are the use classes ?

A

Class B2 - General Industrial
Class B8 - Storage and Distribution

Class C1 - Hotels
Class C2 - Residential Institutions
Class C2A - Secure Residential institution
Class C3 - Dwellinghouse
Class C4 Houses in multiple occupation
Class E - Commercial, Business and Service

Class F - Local Community and Learning

Sui Generis - (in a class of its own) anything not included in the other classes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a build over agreement ?

A

A Build Over Agreement is required where building work is to take place close to (within 3 metres of) or over the route of an existing public sewer or drain. Any work involving new foundations, underpinning, piling or basements requires approval of the Water Company prior to work commencing on site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a section 146 notice ?

A

A notice to forfeit the lease as a result of the tenants failing to meet a specific clause.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a section 18 notice ?

A

S18(1) of the Landlord and Tenant Act 1927 related to

Diminution of value
Supersession

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When do you need to comply with Building Regulations regarding upgrading works ?

A

Roof replacing more than 25% thermal upgrading required.

Thermal elements - More than 50% of the thermal elements (surf area) being replaced it should complies with L1A.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Are you aware of any new approved documents that will be implemented soon ?

A

Part O - Overheating

Part S - Electrical Car Charging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of The Town and Country Planning Act 1990?

A

Takes account of the policies at national and regional level insofar as they affect the physical and environmental planning of its area; and. Provides the framework for local plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the RICS Dilapidations document ?

A

The RICS Guidance note 7th Edition Sep 2016, provides practical guidance to dealing with dilapidations within England and Wales. Subjects include taking instruction, documentation, inspection , schedules, diminution valuations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Section 18 of the Landlord and Tenant Act 1927 ?

A

I) A diminution valuation is required, and damages are usually capped by reference to the diminution in the value of the landlord’s reversion. Two valuations are prepared by a specialist valuation surveyor, one of the property in its current state and another if the tenant kept up with all of their obligations. The difference between the two valuations places a cap on the repair obligations only, not reinstatement and decoration.
II) No costs can be recovered by the landlord if at or shortly after termination of the lease, the building will be structurally altered in a way that would render the repairs valueless or the building is to be pulled down

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is NPPF?

A

National Planning Policy Framework - Sets out government planning policies for England and how they should be applied. Published on 27th March 2012. Implemented to make the planning system less complex and more accessible and protect the environment. NPPF updated in 2018 with minor amendments in 2019.

16
Q

What is required for a client under CDM?

A

PCI package.

17
Q

When is HSE notifiable?

A

A construction project is notifiable if: It’s scheduled to last longer than 30 working days AND has more than 20 workers working simultaneously; OR. The project exceeds 500 person days.

18
Q

Which of the following is a primary duty of the client under CDM 2015?

A

To appoint a principal contractor and principal designer

19
Q

How do you ensure your projects comply with the most up-to-date statutory regulations?

A

I regularly refer to current legislation and Approved Documents, attend CPD events, and subscribe to updates from regulatory bodies like RICS and local authorities. I apply this knowledge during the design, specification, and application stages of my projects.

20
Q

Can you explain your process for researching and applying building regulations during the design stage?

A

I review the relevant Approved Documents based on the project scope, ensure key compliance areas like fire safety, accessibility, and structure are considered, and integrate these into the technical design and specifications from the outset.

21
Q

How do you stay current with changes in legislation relevant to your role?

A

Through structured CPD, attending RICS seminars, reviewing industry publications, and discussing updates with colleagues and consultants. I also keep notes from significant CPD sessions for future reference.

22
Q

What are the different types of party wall notices, and when are they used?

A

There are three: Section 1 (line of junction), Section 3 (party structure), and Section 6 (adjacent excavation). Each is served based on the nature of proposed works impacting a party wall or neighbouring property.

23
Q

Describe the process you followed in preparing a party wall award for the Mansfield development.

A

I identified affected properties, served the appropriate notices, communicated with adjoining owners, and upon agreement, drafted a Party Wall Award outlining the works, working hours, and protection measures.

24
What are the key legal implications for a building owner when serving a party wall notice?
They must serve notices within the required timeframe, secure consent or resolve disputes via a surveyor, and cannot proceed with notifiable works without an award or agreement in place.
25
What are the main duties of a Principal Designer under the CDM Regulations 2015?
To plan, manage, and monitor the pre-construction phase, ensure health and safety risks are mitigated, coordinate between designers, and ensure all information is provided to other duty holders.
26
Can you explain the key requirements of The Control of Asbestos Regulations 2012 for duty holders?
Duty holders must identify asbestos, assess risk, manage or remove it accordingly, and ensure licensed professionals handle higher-risk asbestos works. Record-keeping and communication are also required.
27
How do you approach regulatory compliance when working on a property that has both commercial and residential elements?
I begin by identifying the classification of each use under Building Regulations and assess fire separation, access, and service requirements. I review both Parts B (fire safety), M (access), and L (energy efficiency) in particular, as they can differ significantly between residential and commercial spaces
28
How do you ensure that the contractors you engage are compliant with fire safety and building regulation requirements?
I provide them with detailed construction drawings and specifications based on current regulations. I also review their competency, request proof of accreditation (e.g., FIRAS), and maintain regular site inspections to ensure works align with design and compliance intent.
29
What challenges have you faced when dealing with listed buildings, and how did you overcome them?
One challenge was obtaining LBC for works with limited historical documentation. I overcame this by conducting thorough research, including speaking with local historians, and presenting a balanced proposal that preserved heritage while enabling necessary works, which reassured the Conservation Officer.
30
One challenge was obtaining LBC for works with limited historical documentation. I overcame this by conducting thorough research, including speaking with local historians, and presenting a balanced proposal that preserved heritage while enabling necessary works, which reassured the Conservation Officer.
I assess project complexity and whether the client needs design certainty up front. For simple refurbishments with minimal structural change, a Building Notice is quicker. However, if detailed approval is needed beforehand (e.g., for funding or insurance), I recommend a Full Plans application
31