Lecture 6 Project Scheduling Key terms Flashcards

1
Q

Project Network Diagram

A

Any schematic display of the logical relationships of project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Path

A

A sequence of activities defined by the project network logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Event

A

A point when an activity is either started or completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Node

A

One of the defining points of a netowork; a junction point joined to some or all the other dependency lines (paths)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Predecessors

A

Those activities that must be completed prior to initiation of a layer activity in the network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Successors

A

Activities that cannot be started until previous activities have been completed. These activities follow predecessor tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Early start date (ES)

A

The earliest possible date the uncompleted portions of an activity can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Late start date (LS)

A

The latest possible date that an activity may begin without delaying a specific milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project Scheduling

A

An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project Planning

A

The identification of the project objectives and the ordered activity necessary to complete the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly