Lecture 6 Project Scheduling Key terms Flashcards
Project Network Diagram
Any schematic display of the logical relationships of project activities
Path
A sequence of activities defined by the project network logic
Event
A point when an activity is either started or completed
Node
One of the defining points of a netowork; a junction point joined to some or all the other dependency lines (paths)
Predecessors
Those activities that must be completed prior to initiation of a layer activity in the network
Successors
Activities that cannot be started until previous activities have been completed. These activities follow predecessor tasks
Early start date (ES)
The earliest possible date the uncompleted portions of an activity can start
Late start date (LS)
The latest possible date that an activity may begin without delaying a specific milestone
Project Scheduling
An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources
Project Planning
The identification of the project objectives and the ordered activity necessary to complete the project