Crtical Path Key terms Flashcards

1
Q

Forward Pass

A

An additive move through the network from start to finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Backward Pass

A

A subtractive move through the network from finish to start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Critical Path

A

The longest path from end to end which determines the shortest project length

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Rules for forward pass

A

– ES + Duration = EF

– EF of predecessor = ES of successor

– Largest preceding EF at a merge point becomes EF for successor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Rules for backward pass

A
  • LF - Duration = LS
  • LS of successor = LF of predecessor
  • Smallest succeeding LS at a burst point LF for predecessor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Merge activity

A

An activity with two or more immediate predecessors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Burst activity

A

An activity with two or more immediate successors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Float

A

The amount of time an activity may be delayed from its early start without delaying the finish of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Critical Path

A

The path through project network with the longest duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Critical Path Method

A

A network analysis technique to determine the shortest project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Resource limited schedule

A

Start and finish dates reflect expected resource availability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Serial activities

A

Those that flow from one to the next, in sequence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Concurrent Activities

A

When the nature of work allows the completion of two or more activities at the same time, they are concurrent activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly