Lecture 5b - South Kensington Campus Energy Strategy Flashcards
1
Q
What analysis was undertaken?
A
- Using recent energy data, modelled some alternative future scenarios for energy use on campus
2
Q
What methodology was used to model future demand scenarios?
A
- Future energy use in buildings
- Position of data centre - large user of electricity
- Density of energy use on sire - for positioning centralised system so that heat and pumping losses are kept to a minimum
3
Q
What were the four scenarios?
A
- BAU - electricity demand down 5%, heat demand up 10%
- Data center removed - electricity demand down 20%, heat demand up 30%
- Larger data centre and large heat savings - electricity demand up 5%, heat demand down 20%
- Larger data centre and more wet labs - electricity demand up 5%, heat demand up 30%
4
Q
What were the supply options?
A
- Biomass - but too many deliveries and emissions too high so ruled out
- PV cells - too many required and not enough land so ruled out
- Local boilers - modelled
- Gas turbine CHP - smallest available too big so ruled out
- Smaller engine CHP - modelled
- Same sized engine CHP - modelled
5
Q
What are the main heat distribution technologies?
A
- Steam - compact, efficient use of CHP energy but some of the existing pipes too small.
- MTHW - bulky and some of the existing pipes too small
- LTHW - compact, efficient use of CHP energy if used with seam, necessary to maximise plant efficiency
6
Q
What was the recommendation
A
- Replace CHP and install larger steam network
- Up to 3xCHP units producing 6.5MW electricity in total -> smaller size allows for more flexibility and resilience, and minimises heat rejection into the atmosphere.
- Modular solution that can adapt to demands
- Heat required not produced by CHP plant produced by steam boilers as it is currently.
7
Q
What actually happened?
A
- Upgrade steam pipes and heat exchanger - conversion of MTHW to LTHW
- Re-procure existing operation and maintenance contract to get better value
- Moved steam system onto MTHW system
8
Q
What were the key conclusions?
A
- Removal of existing CHP engines and replace with smaller ones - best economic outcome based on cost, flexibility, CO2 reduction and space
- Heat distribution system needed to be reconfigured t take full advantage of saving from CHP
- Robustness of solution meant it did not change depending on master plan scenario