Lecture 5b - South Kensington Campus Energy Strategy Flashcards

1
Q

What analysis was undertaken?

A
  • Using recent energy data, modelled some alternative future scenarios for energy use on campus
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What methodology was used to model future demand scenarios?

A
  • Future energy use in buildings
  • Position of data centre - large user of electricity
  • Density of energy use on sire - for positioning centralised system so that heat and pumping losses are kept to a minimum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What were the four scenarios?

A
  1. BAU - electricity demand down 5%, heat demand up 10%
  2. Data center removed - electricity demand down 20%, heat demand up 30%
  3. Larger data centre and large heat savings - electricity demand up 5%, heat demand down 20%
  4. Larger data centre and more wet labs - electricity demand up 5%, heat demand up 30%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What were the supply options?

A
  • Biomass - but too many deliveries and emissions too high so ruled out
  • PV cells - too many required and not enough land so ruled out
  • Local boilers - modelled
  • Gas turbine CHP - smallest available too big so ruled out
  • Smaller engine CHP - modelled
  • Same sized engine CHP - modelled
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the main heat distribution technologies?

A
  • Steam - compact, efficient use of CHP energy but some of the existing pipes too small.
  • MTHW - bulky and some of the existing pipes too small
  • LTHW - compact, efficient use of CHP energy if used with seam, necessary to maximise plant efficiency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What was the recommendation

A
  • Replace CHP and install larger steam network
  • Up to 3xCHP units producing 6.5MW electricity in total -> smaller size allows for more flexibility and resilience, and minimises heat rejection into the atmosphere.
  • Modular solution that can adapt to demands
  • Heat required not produced by CHP plant produced by steam boilers as it is currently.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What actually happened?

A
  • Upgrade steam pipes and heat exchanger - conversion of MTHW to LTHW
  • Re-procure existing operation and maintenance contract to get better value
  • Moved steam system onto MTHW system
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What were the key conclusions?

A
  • Removal of existing CHP engines and replace with smaller ones - best economic outcome based on cost, flexibility, CO2 reduction and space
  • Heat distribution system needed to be reconfigured t take full advantage of saving from CHP
  • Robustness of solution meant it did not change depending on master plan scenario
How well did you know this?
1
Not at all
2
3
4
5
Perfectly