Lecture 4 - Intermittency, flexibility and energy storage Flashcards
Explain system margin
- To maintain reliability of supply, peak demand must not exceed production capacity at that moment.
- Historically, planners sought to ensure that installed generation capacity could meet forecast peak demand within a planning horizon.
- In liberalised markets, individual market participants are responsible only for ensuring adequate generation capacity is available to meet their own contracts to supply electricity.
- In either case, system margin can be measured as the amount by which the total installed capacity of all generating plants on the system exceeds the anticipated peak demand.
What are the two categories of impact associated with introducing more intermittent electricity into the grid?
- System balancing - relates to the relatively rapid short term adjustments needed to manage fluctuations over a time period from minutes to hours.
- Reliability impacts - relates to the extent to which we can be confident that sufficient generation will be available to meet peak demand.
Explain system balancing
Relates to the relatively rapid short term adjustments needed to manage fluctuations over a time period from minutes to hours.
Explain reliability impacts
Relates to the extent to which we can be confident that sufficient generation will be available to meet peak demand.
Explain frequency response
- Frequency of AC on the grid will drop in response to a sudden fall in generation or increase in demand.
- ‘Frequency response reserves’ are required to ensure frequency stays within acceptable limits (within 1% of 50Hz in the UK).
What are frequency response reserve required for?
To ensure frequency stays within acceptable limits (within 1% of 50Hz in the UK).
What is the acceptable limit for frequency response in the UK
Within 1% of 50Hz
Name and describe the three categories of frequency response reserves
- Enhanced frequency response (EFR) - must provide power (or reduce demand) within 1 second and provide power for a further 9 seconds.
- Primary frequency response (PFR) - must provide power (or reduce demand) within 10 seconds and provide power for a further 20 seconds.
- Secondary frequency response (SFR) - must provide power (or reduce demand) within 30 seconds and provide power for a further 30 mins.
What is enhanced frequency response (EFR)?
Must provide power (or reduce demand) within 1 second and provide power for a further 9 seconds.
What is primary frequency response (PFR)?
Must provide power (or reduce demand) within 10 seconds and provide power for a further 20 seconds.
What is secondary frequency response (SFR)?
Must provide power (or reduce demand) within 30 seconds and provide power for a further 30 mins.
What is Loss of Load Probability (LOLP)?
- Statistical measure of the risk of demand being unmet
- Measures the likelihood that any load (demand) is not met, and it is usually a requirement of electricity systems that LOLP is kept small.
- Variable generation increases LOLP
What is capacity credit?
- The possibility for a certain power plant to increase the reliability, measured as decreased LOLP, of the power system with a certain level.
- How much electricity can a technology provide at peak demand?
At what ratio is renewable energy currently backed up in the EU?
Total capacity:renewable capacity = 2:1
What are the main costs of intermittency?
- Aggregate costs of intermittency are made up of additional short-run balancing costs and the additional longer term costs associated with maintaining reliability via an adequate system margin.
- A 2017 review suggested that, at variable renewable penetration of 30% or less, intermittency costs in the UK are: £5/MWh from short-run balancing costs and £4-7/MWh from costs of maintaining a higher system margin.
- Be careful summing the numbers because risks double counting some costs (e.g. system reserves to meet short-term balancing requirements may also contribute to the capacity margin).
- Balancing in the UK is mainly through thermal plants.