Lecture 3 - Time Planning Flashcards
Draw out the breakdown of the time planning years:
…
Define a ‘work package’:
A work package is a subset of a project that:
- Can be assigned to specific resources (people, machines etc).
- Produces a deliverable within the project.
What should work packages be?
Small enough:
- Require the same resources throughout.
- Keeping track of WPs give a good view of the project’s overall status.
Large enough:
- Lead to a verifiable outcome.
- Form independent units of work with distinct start times + resources.
Rule of thumb: typical WPs last several days to weeks.
There are three ways in which a process overview can be broken down; what are these?
- Activity breakdown.
- Physical breakdown.
- Functional breakdown.
The highest level in the each breakdown is the most different to all others.
In the activity breakdown, what are the tasks broken down into?
- Major activity groups (and activity sub-groups).
- Individual work packages.
The number of levels of the breakdown depends on the project complexity.
In the functional breakdown, what are the tasks broken down into?
- Major functional areas / departmental units (and activity sub-groups).
- Individual work packages.
The number of levels of the breakdown depends on the project complexity.
In the physical breakdown, what are the tasks broken down into?
- Major product modules (and activity sub-groups).
- Individual work packages.
The number of levels of the breakdown depends on the project complexity.
When should you employ the functional breakdown?
- When the functional organisation takes place in a functional organisation (i.e. when the team comes from different departments).
- Project manager has little authority over team members in functional units.
When should you employ the physical breakdown?
- Project decomposes naturally into independent modules (construction, software, physical products).
When should you employ the activity breakdown?
- Project outcome is a service (e.g. IT development process).
What is meant by ‘task dependency?
The start/completion time of task B depends on the start/completion time of task A.
There can be multiple dependencies.
What 5 things are mentioned in the task description of the CPA?
- EST: Earliest start time.
- Start time if all predecessor tasks are started ASAP. - LST: Latest start time.
- If started afterwards, project completion will be delayed. - Activity description.
- Duration of task.
- Total float of activity.
- Difference between EST and LST.
- Maximum time that task can be delayed without affecting project duration.
- If total float is zero, then the activity lies on the CRITICAL PATH.
What is the purpose of the forward pass in the CPA?
To determine the earliest start times of the tasks.
- Maximum EST of predecessors + duration.
What is the purpose of the backward pass in the CPA?
To determine the latest start times of the tasks.
- Minimum LST of predecessors - duration.
Is there always a critical path in CPA?
Yes.