Lecture 3 - Construction Bidding Preparation Flashcards

1
Q

Project Development cycle and steps
1. _______ establishment
2. ________ drawings and estimates
3. __________ and _______ design
4. ________
5. _______ contractor
6. construction ______

A

need, conceptual, preliminary, detail, bidding, select, period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Establishing Need:
need recognized by _______ or users

A

owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Conceptual Drawings & Estimates:
very early _________ and cost ________
present to potential _______ _______
architect’s ________ ________
Preliminary _______ plan

A

design, estimate, funding sources, sketch drawings, cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Preliminary and Detail Design
end product is _______ (__________) and _____________ (__________) - binding elements of the contract
typically has two stages: _________ design and _________ design

A

plans, graphical, specifications contextual, preliminary, detailed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Stage 1 - Preliminary design
allows the owner to review his ________ and ___________ status

A

needs, financial

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Preliminary design outputs:
drawings (____% completed)
specifications (____% completed)
preliminary __________

A

40, 40, estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Stage 2 - Detailed design
prepare owner’s ________ (should achieve a determined ________ of accuracy)

A

estimate, range

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

detailed design outputs
____ ____ of integrated drawings
____ ____ of specifications
detailed estimate (+- ______% accuracy)

A

full set, full set, 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Purpose of the detailed design is to establish a reference point in ___________ ____

A

evaluating bids

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is bidding?
Construction bidding is the process of submitting a _________ (tender)
to __________, or manage the _________ of a construction project

A

proposal, undertake, undertaking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why bidding?
To provide _________ and thereby _______ costs

A

competition, reduce

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what are the two ways of obtaining bids methods/approaches

A

competitive bid and negotiated bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Is cost the only factor to consider?
* Lowest tender/bid will not necessarily provide the lowest cost; ____
_______ and ____ ________ may _______ cost
* Prudent owner will consider not only the amount of the bid but also
factors such as __________ and ___________ of the contractor, and
whether the bid is realistic

A

low trust, low control, increase, experience, capability, realistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Public bids - government, _______ authorities
* Basis for award is usually ______ ____ ______

A

public, lowest bid price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Closed bids - _______ individuals & organization
* Basis for award is ___ __________ the ______ bid price

A

private, not necessarily, lowest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Bid _______: Notice to Bidders/Invitation to bid
______________
Bid ________
Bid _________ by Tender
Bid ________, Acceptance and Documentation
Award of _________

A

request, prequalification, package, submission, opening, contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Bid Request: Notice to Bidders/Invitation to bid
A _________ announcing to prospective bidders
that _______ documents are available for consideration and
that the owner is ready to receive bids

A

document, design

18
Q

Bid Request: Notice to Bidders/Invitation to bid
Why: Project opportunity with _________ _____________ with
adequate details reaching quality bidders

A

necessary information

19
Q

Prequalification
* Why?
* To verify that if selected they will have both the
__________ and ___________ to successfully perform the work
they have been contracted to complete.

A

resources, expertise

20
Q

Prequalification: What to consider?
* ___________ competence and experience
* Current ________ position
* Bonding capacity (10 times Liquid Assets/Net Worth)
* Current amount of work underway
* Post project ________ history
* Defaults on contracts
* Small Business __________, MBE, WBE, DBE
* Safety __________
* Willingness to help reduce net project cost

A

technical, financial, litigation, qualifications, records

21
Q

What is Bid Package?
* A set of documents defining project ________ and details and on which a
contractor must base his decision to ____ or not to _____
* Proposal details – cost, duration, value engineering, etc

A

scope, bid, bid

22
Q

Bid Package Proposal form
filled and _________ by contractor
illustrates the ________ and commitment to perform the work

A

submitted, intent

23
Q

Lump-Sum Proposals
* Used for most ______ _________ buildings or other works
with well-defined _______ and requirements of the project

A

fully designed, scope

24
Q

Unit-Price Proposals
* Useful when the scope of the work ________ be well-defined
*Bidders are given __________ quantities

A

cannot, estimated

25
General Conditions * A document that defines the ____________ of the parties affected by the Contract and describe the ___________ that will be used in the administration of the contract.
responsibilities, guidelines
26
Supplementary/Special Conditions * Covers aspects of the contractual relation that are peculiar to a specific _______ An __________ to general conditions include modifications or additional articles
project, extension
27
Addenda A document illustrating any ________, additions, omissions, __________, and contract conditions that arise ________ bidding is finalized
changes, corrections, before
28
Addenda purposes To correct _______ in documents * To ________ to queries from bidders * To authorize design ________ to approve material substitutions * Takes __________ over original documents * Bids should clearly record which addenda have been considered
errors, respond, changes, precedence
29
Decision to Bid: Why is it an important decision? * ”To bid” implies commitment of resources and incurring substantial _____ may not be ________ * Costs of bid preparation may be recoverable if bid is ____ * Approximately ____% of total bid value
cost, recoverable, won, 0.25%
30
Bid Opening, Acceptance, & Documentation * Private Sector - No “____” procedures
rigid
31
Public Sector - Following “__________” rules apply: * Receipt of sealed bids at the designated time and place * Owner/design reps evaluate if each bid is responsive * Acceptance and logging of name and amount for all responsive bidders * Summary of all lump sum and unit price items
inflexible
32
Bid Opening * The date and time at which the bid opening is to take place marks the _______ _____ of the bidding period * Bid box at some central location * e-Bid is commonly adopted * Late bids - _____ accepted * No ________ to withdraw bids prior to bid opening
formal end, not, penalty
33
Owner Notice to proceed Contractor It establishes the _________ relationship from the legal viewpoint * The ______ establishes the reference date from which the ___________ of the project is calculated – “Commencement”
contractual, date, beginning
34
Award of Contract Owner provides successful Contractor: * _________ of intent to award—invitation to discuss and sign the contract * Notice to _________ —upon contract signing and owner readiness
notice, proceed
35
Situations for a “letter of intent” * The project is ________ by other sources (than the owner), and the owner does not wish to _____ the bid prices that have been received.
delayed, lose
36
a letter of intent should be __________ by a formal _________ later A letter of intent may or may not be ___________
followed, agreement, enforceable
37
Contract Document that represents and reflects the ______ agreement between parties and is traditionally made between ________ and the ___________
legal, owner, contractor
38
bidding timeline
notice to bidders, bid opening, sign contract, notice to proceed
39
notice to bidders to bid opening is the _________ _________
bidding period
40
bid opening, sign contract, and notice to proceed are in the ____________ ________
Acceptance period
41
To Withdraw a Bid * A contractor must satisfactorily establish the following: * A __________ was made. * Written _______ given to the agency
mistake, notice
42
Rejection of Bids * _______ in bid requests to state that the owner is not ________ to accept the lowest or any tender. * A person _______ be forced into a contract against their will.
usual, bound, cannot