Lecture 12 Flashcards

1
Q

Cost Estimating
The estimate is used to:
– set (or compare against) the ________
– obtain project financing – ____ flow estimates
– compare among __________
– _______ order estimates

A

budget, cash, alternatives, change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Types of Estimates: (4)

A

conceptual estimate, preliminary estimate, detailed estimate, and bid estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Levels of detail in estimates
* _________ estimate (also called approximate, preliminary, or budget estimate)
– Broad scope: ________ design begins
– Narrow scope: ________design process

A

Conceptual, before, during

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Levels of detail in estimates
* The details of the estimating procedure (also called ______ _____ estimate)
– Based upon completed drawings and specs
– Requires:
* Accurate _________ survey
* Accurate ______ ______ and production rates
* Estimators understanding of field _________

A

final cost, quantity, unit costs, operation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Procedure for Estimating
1. ___________ review
– “Documents” are drawings, specifications, bid form, other contract documents
2. _________Take-Off (QTO)
3. Unit _________
4. __________
– Contingency, overhead, profit
– Analysis of estimate (adjustments needed?)
– Using the estimate (project control)

A

document, quantity, pricing, compiling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Sources for Pricing and Labor Rates
* ___________ per-unit estimates
* Sub-contractors / work crews
* Past ___________ with similar projects
* Contractor/supplier bids or _______

A

historical, experience, quotes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Direct costs are expenses that can be traced _______ to a specific construction ________, task or project.

A

directly, activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Indirect Field Costs
* Costs that can be charged to a specific _______ but not to a specific _____ _____ on that project

A

project, work item

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Indirect Field Costs
Typically, __-___% (may be much higher %) of total project ____, but must be carefully itemized (i.e., do not simply add a % to the direct cost)
– Also called General Conditions, Project overhead costs, Job
overhead costs, and Direct overhead costs

A

5-15%, cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Fee (or “Mark-up”)
* A contractor’s “fee” for a project commonly refers to home office __________ plus ______

A

overhead, profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Home office overhead
– Also called ________ _________ or indirect overhead or General & Administration (G&A)
– Costs not charged directly to a specific project
– Covers home _______ expenses; _________ for executives, estimators, inspectors, administrators, etc.; misc

A

general overhead, office, salaries

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Profit is _______ money going directly to the ______ company
– Even if a company makes zero profit on a job, all of its expenses, including employee salaries, may still have been paid in full

A

extra, owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Contingency
* An amount added to an estimate to allow for items, conditions, or events for which the state, occurrence, or effect is ________ and that experience shows will likely result, in aggregate, in additional _______

A

uncertain, costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Steps to Preparing a Detailed Estimate
1) Review the ______of Work
2) Determine the __________ of each type of Work (Material Quantity Takeoff)
3) Determine cost of _________ from vendors
4) Determine cost of _______ from direct labor rates
5) Determine cost of construction __________ (owned and rented)
6) Determine cost of _________ work from specialty contractor bids
7) Determine ______, bonds, insurance and general and administrative overhead
8) Determine project __________ (amount set aside for unforeseen negative events or unexpected costs)
9) Determine reasonable _______ for your effort (return on investment)

A

scope, materials, labor, equipment, specialty, taxes, contingency, profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Labor Estimating Procedure
1. Labor __________ Rate
Work per unit time or per other unit or X work hours per unit
2. _________ Takeoff
Required number of units (including waste)
3. Work ______ Required
Productivity rate (work hours per unit) x quantity takeoff
4. Payment ____
hourly crew labor cost
5. Activity _______ Cost
Work Hours Required x hourly crew labor cost

A

Productivity, quantity, hours, rate, labor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Estimating Equipment Costs
* Equipment cost is generally a ___________ component of heavy-civil projects, much less for _________ projects
* Equipment cost can be quite _________ dependent upon:
– Construction methods
– Ownership (owned or rented)
– Field conditions

A

significant, building, variable

17
Q

Lump-Sum Bid
* A lump sum contract is a contract where the contractor agrees to complete the entire project for a _______ ________, regardless of the actual quantity of work done.
* beneficial for projects that have _____-_______ and stable scopes
* allow the contractor to plan and control the budget and schedule more
precisely and efficiently
* reduce the risk of cost overruns or delays

A

fixed price, well-defined

18
Q

Unit Price Bid
* A unit price contract is a contract where the contractor agrees to perform a specific quantity of work for a ______ _______ per ____
* beneficial for projects that have uncertain or ________ _________ of work
* allow the contractor to adjust the price according to the actual work done
* reduce the risk of disputes over changes in scope or unforeseen conditions

A

fixed price, unit, variable quantities

19
Q

Types of construction contracts

A

lump-sum or fixed price contract
unit pricing
cost-plus
time and materials contracts
guaranteed maximum price (GMP)

20
Q

Unit price Reference - CSI
____________ _______________ ___________
(CSI) http://www.csinet.org
* 16 major divisions in the CSI format
(pre-2004, now 50 divisions)
* Grouped by building trades and
related broad scope sections
* Provides the industry __________ for
cataloging design information

A

Construction Specification Institute, standard