Lecture 09: Project controlling Flashcards
Sketch the rate of ressource usage across the PLC
- Phase of initial acceleration
- few qualified RS
- learning curve
- operative conductions - Central Phase
- resource mobilzation
- high and constant usage rate - Phase of final deceleration
- Constraints from work done, physical impediments + procedure
- dragging effect
Why is the S Curve useful during planning of a PJ?
-Assess the time/cost objectives feasibility
-Fix the reference point
→ contracutal + schedule milestones
- plan the RS usage and assess the congruence with the progess rate
- study correlations among macro project phases
What steps does the Earned Value Framework include?
- Planning
- Executing
- Controlling
What are the earned value benefits
- provides manager with info at a practical level of summarization
- alerts PMs about scedule/cost risks early
- provides documented PJ performance trail
- Communcates PJ status
- tracks and monitors discret PJ metrics
- comparison between planned and actual work
- accurate/reliable reading of cost/schedule performance
- PF at the 15% complete point can predict final PF
- The Scedule PF index shows how much work is done
- CPI and SPI can be used for forecast final estimate
Earnes Value Limitations
- traditional EV not intended for “Level of Effort” PJ (e.g design a new logo, write a song)
- EVM states that stakeholders want to measure progress objectively
-Quantifying/measuring work can be difficult
→ time for measurement can be long
- EVM requires thorough/accurate planning of cost
- forecast based on past (if data bad, forecast is bad)
- EV does not measure quality
What are DO’s of the EVM? (1)
-necessary building steps seriously: integrate scope of work, schedule and cost using a WBS
-train ur Stakeholders
→ need to understand variance reports
- document all PF metrics and thesholds in PJ plan (PF plan)
- determine how u will measure ur tasks (discrete options)
- include variances early (not later than 15% in)
- bad news have to be heard
→ take corrective action (staff changes, mid-term evaluation of work, crashing, fast tracking)
What are DO’s of the EVM? (2)
-request that staff monitors their work hours
-give PM reliable labor and overhead rates for research
→ otherwise CPI does noch mean much
- have policies in place for rebaselining
- Re-plan as necessary (budget increase, scope change, schedule change?)
- create a weekly or monthly variance report
- use standart templates for reporting (helps with learning curve/comparing and aggregate data across PJ)
- institute standart reporting cycles
-