Lecture 07/08: Planning and Time Management Flashcards
Define project planning
The identification of the project objectives and the ordered activity necessary to complete the project including the identification of resource types and quantities required to carry out each activity or task
Define Project scheduling + project schedule:
→ defines network logic for all activities (tasks either precede of follow other tasks in the PJ)
Project schedule: output of a schedule model that presents linked activities with dates/durations/miletstones/resources
→ network diagram is mainly used for sceduling
What are serial and concurrent activities?
serial: flow from one to the next, in sequence
concurrent: when multiple activities can be done at the same time
→ parallel project paths are constructed
Why use Network diagramm over Gantt Chart?
- ND shows a systemic PJ representation
- enablbes “what-if” analysis
-illustrates interdependence of all task and work packages
→ A before B
→ A and B at the same time
-illustrates interrelationship among activities and PJ personell and communication flows
→ relevant for Person A and B
-helps with master scheduling of organizational resources, shows time, when personnel must commit to an activity
→ companies have more than one PJ
-identifies critical activities
-determine when PJ expected to be done
- gives dates when PJ activities must start/end
- demonstrates activity dependency among each other
What is a network?
-set of nodes linked by arrows, their sequence defina a path
→ if arrows have a sense, the network is called oriented
- usually flow from left to right
- activity can only begin when prior one is done
- each AC has a number
- single nodes are at the beginning/end
What’s the difference in using “Activities on Nodes” instead of “Activities on Arrow” for scheduling?
AC on arrow:
→
What is a Gantt chart + list its characteristics and limitations
-shows when the project and each activity start and end against a horizontal timescale (bar chart)
- easy to read/comprehend
- can be used as a tracking tool
- allow updating/controll PJ
- identifying resource needs + assigning ressource to tasks
- easy to create
- *Limitation:**
- “all PJ view” only good for PJ with few AC
- usually no indicaton of relationship between AC
What are milestones?
-important events in a PJ
What are sources to get AC duration info?
-
Experience
-past examples or similar PJ (often best idea)
→ but assumptions are based on past and wont work today. PJ are effected by external event, which are always unique
→ must be aware of using distorted/outdated info -
Expert opinion
-past PJ manager/expert in an area
→ experts know the easiest paths, best contacts and fastest ways to complete someting. But would his estimation be valid for non-experts? -
Mathematical derivation
-duration probability based of best case, most likely case and worst case scenarios
-popular increasing complex algorithms (data mining etc.)
→ you need to know what you are doing
List precedence constraints among activities + examples and occurance
- Natural
→ digging before building foundation
→ usually constant - Environmental
→ resource availability constraint (only have 1 excavator)
→ can be dynamic - Prefential
→”i prefer eletrical work before mechanical one”
→ can but dynamic
Define the PJ Sceduling Terms Path/Event/Node
Path → sequence of activities defined by the project network logic
Event → point when an activity is either started or completed
Node → defining points of a network; connector to some or all other paths
Difference between Merge activity and burst activity
Merge: AC D can only beginn, when A,B and C are done
Burst: B,C and D can only beginn, when A is done
What is total float?
Amount of time an activity may be delayed from its early start without delaying the finish of the PJ
Define critical path:
path trough the PJ network with the longest duration
→ a delay for any activity belongign to the critical path implies a delay for the whole project
Define Critical Path method
network analysis technique used to determine the amount of scedule flexibily on logical network path in PJ scedule networkt to determin minimum PJ duration