contingencies are added to individual activities. true/false
false
Forward pass = ?
earliest start is based on earliest finish of preceding activity
Backward pass = ?
latest finish is based on latest start of following activity
zero float = critical activity
true/false
true
Which of the following is the most commonly used unit of time in a 'network' consisting of sequentially ordered job activities? Calendar days Manhours Working days Shifts Hours Minutes
working days
The most common project delay is due to _____________.
weather
A special point in time within a network, which signifies the start or completion of a major portion of the project, is called a _____________________.
milestone
The subcontractor selection process should be based on quality prequalification BEFORE price is considered.
true/false
true
Critical path job activity means that it must be completed before the future activities can take place, not necessarily a high value job. true/false
TRUE