L14 M1 Flashcards

1
Q

Management by exception ?

A

handling project by identifying and focusing on the unusual aspects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

___ is a tool used to manage large number of job activities and complicated sequential relationships.

A

critical path method (CPM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CPM is a 3 phase procedure:
1
2
3

A

Planning
scheduling
time monitoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

‘Beginning to end’ adds detail as the project progresses while ‘top down’ looks at the overall project and breaks it down into major components. true/false

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

drawing networks:
arrow notation = activity on arrow (AOA)
precedence notation = activity on node (AON)
true/false

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

One of the reasons why it is good for construction project managers to have excellent people skills is that they are primarily managing people outside their own company.
true/false

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Regarding the ordering of job activities in a ‘network’, erecting formwork and placing rebar prior to pouring concrete is an example of a physical _______________.