What is the potential fine of a notice to fix?
$200k, +20k a day
BCA's are responsible for issuing: B\_\_ C\_\_ N\_\_ to F\_\_ C\_\_ C\_\_ C\_\_ C\_\_ S\_\_
Building consents
Notices to fix
Code compliance certificates
Compliance schedules
TA’s are responsible for issuing :
P__ I__ M__
C__ of A__
Project information memoranda
Certificates of acceptance
When applying for Project Information Memorandum (PIM): TA (city or district council) provides within __ working days
20
When applying for a building consent applications are processed by the BCA within __ working days
20
Once consent is given building work must start within __ months of consent unless special arrangements are made with the BCA
12
Once consent is given building work must be completed within __ years of issuing consent unless special arrangements are made with the BCA
2
Co-ordinate building inspections with BCA:
Generally gas and electrical work is not inspected by the BCA. Licensed professionals conduct this work and provide signed ___ ___ ___ used to get a CCC.
energy work certificates
Final sign off:
if building for sale, a CCC is required before a sale can be made - fine up to ___ if such property sold without CCC
$200k
Final sign off:
Applications for CCC (final) inspection is considered within __ working days
20
Ongoing maintenance:
TA will administer the annual B__ W__ of F__ aimed and ensuring the compliance schedule is maintained
building warrant of fitness
What does restricted work mean?
Critical work that could cause serious damage if done wrong
Category 1 buildings have a risk matrix score of above 12 while category 2 buildings have a risk matrix score of below 12. true/false
false
Before a property developer can conclude the sales of apartments within his/her project, which of the following must be completed?
- Apply for a project information memorandum
- Be issued a code compliance certificate
- Be issued a building consent
- Apply for a building consent
- None of the above
be issued a code compliance certificate
An apartment building with an uppermost finished floor height of 9 metres is considered under the LBP Rules as being a Category __ Building.