1
Q

What is the potential fine of a notice to fix?

A

$200k, +20k a day

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
BCA's are responsible for issuing:
B\_\_ C\_\_
N\_\_ to F\_\_
C\_\_ C\_\_ C\_\_
C\_\_ S\_\_
A

Building consents
Notices to fix
Code compliance certificates
Compliance schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

TA’s are responsible for issuing :
P__ I__ M__
C__ of A__

A

Project information memoranda

Certificates of acceptance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When applying for Project Information Memorandum (PIM): TA (city or district council) provides within __ working days

A

20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When applying for a building consent applications are processed by the BCA within __ working days

A

20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Once consent is given building work must start within __ months of consent unless special arrangements are made with the BCA

A

12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Once consent is given building work must be completed within __ years of issuing consent unless special arrangements are made with the BCA

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Co-ordinate building inspections with BCA:
Generally gas and electrical work is not inspected by the BCA. Licensed professionals conduct this work and provide signed ___ ___ ___ used to get a CCC.

A

energy work certificates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Final sign off:

if building for sale, a CCC is required before a sale can be made - fine up to ___ if such property sold without CCC

A

$200k

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Final sign off:

Applications for CCC (final) inspection is considered within __ working days

A

20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Ongoing maintenance:

TA will administer the annual B__ W__ of F__ aimed and ensuring the compliance schedule is maintained

A

building warrant of fitness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does restricted work mean?

A

Critical work that could cause serious damage if done wrong

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Category 1 buildings have a risk matrix score of above 12 while category 2 buildings have a risk matrix score of below 12. true/false

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Before a property developer can conclude the sales of apartments within his/her project, which of the following must be completed?

  • Apply for a project information memorandum
  • Be issued a code compliance certificate
  • Be issued a building consent
  • Apply for a building consent
  • None of the above
A

be issued a code compliance certificate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

An apartment building with an uppermost finished floor height of 9 metres is considered under the LBP Rules as being a Category __ Building.

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Building height is measured to the finished floor. true/false

A

TRUE