Knowledge Areas
Integration Scope Time Cost Quality Human Resource Communication Risk Procurement Stakeholder
Number of knowledge areas.
10
Process Groups and number of processes
Initiating - 2 Planning - 24 Executing - 8 Monitoring and Controlling - 11 Closing - 2
Project Scope Management:
Number of processes
6
Project Integration Management:
Number of Processes
6
Time Management:
Number of Processes
7
Cost Management
Number of processes
4
Quality Management
Number of processes
3
Human Resource Management
Number of processes
4
Communications Management
Number of processes:
3
Risk Management
Number of processes:
6
Procurement Management
Number of processes:
4
Stakeholder Management
Number of processes:
4
List Initiating Process group processes and Knowledge Area
(2)
Integration - 4.1 Develop Project Charter
Stakeholder- 13.1 Identify Stakeholders
List Processes in Planning Process Group / Integration Management Knowledge Area
(1)
4.2 Develop Project Management Plan
List Processes in Planning Process Group / Scope Management Knowledge Area
(4)
- 1 Plan Scope Management
- 2 Collect Requirements
- 3 Define Scope
- 4 Create WBS
List Processes in Planning Process Group / Time Management Knowledge Area
(6)
- 1 Plan Schedule Management
- 2 Define Activities
- 3 Sequence Activities
- 4 Estimate Activity Resources
- 5 Estimate Activity Durations
- 6 Develop Schedule
List Processes in Planning Process Group / Cost Management Knowledge Area
(3)
- 1 Plan Cost Management
- 2 Estimate Costs
- 3 Determine Budget
List Processes in Planning Process Group / Quality Management Knowledge Area
(1)
8.1 Plan Quality Management
List Processes in Planning Process Group / Human Resource Management Knowledge Area
(1)
9.1 Plan Human Resource Management
List Processes in Planning Process Group / Communication Management Knowledge Area
(1)
10.1 Plan Communications Management
List Processes in Planning Process Group / Risk Management Knowledge Area
(5)
- 1 Plan Risk Management
- 2 Identify Risks
- 3 Perform Qualitative Risk Analysis
- 4 Perform Quantitative Risk Analysis
- 5 Plan Risk Responses
List Processes in Planning Process Group / Procurement Management Knowledge Area
(1)
12.1 Plan Procurement Management
List Processes in Planning Process Group / Stakeholder Management Knowledge Area
(1)
13.2 Plan Stakeholder Management
Which knowledge areas are used for the Executing Process Group
(6) Integration Management Project Quality Management Human Resource Management Communications Management Procurement Management Stakeholder
Which knowledge areas are used for the Monitoring and Controlling Process Group
(9) Project Integration Management Scope Management Time Management Cost Management Quality Management Communications Management Risk Management Management Procurement Stakeholder Management
Which knowledge areas are used for the Closing Process Group
(2)
Project Integration Management
Project Procurement Managment
List Processes in Closing Process Group
(2)
- 6 Close Project or Phase
- 4 Close Procurements